You are on page 1of 12

Mumbai-Ahmedabad High Speed Rail Project

11.09.19
GANDHINAGAR 1
MAHSR LAND ACQUSITION REQUIREMENT / ACQUIRED
(Area in Ha.)

Total Forest Railways Government Private


District

Acquired/ Proposal
Scope scope Diversion scope Transferred scope scope Acquired
Transferred Submitted

939.69 550.16 2.83 2.83 125.87 125.87 86.86 62.22 724.13 359.24
Gujarat

431.2 72.80 95.85 0.00 1.63 1.63 66.07 56.07 267.65 15.10
Maharashtra

8.7 2.42 0.00 0.00 0.00 0.00 1.70 0.00 7.00 2.42

Dadra & Nagar


Haveli

1379.59 625.38 98.68 2.83 127.50 127.50 154.63 118.29 998.78 376.76
Total

  45.33% 2.87% 100% 76.50% 37.72%


Status of Land Acquired (C-6) 401.900 to 489.500
Start Chainage 401.9 416.5 442.16 484.5
End Chainage 416.5 442.16 484.5 489.5 Total
District Vadodara Anand Kheda Ahmedabad
Scope (Km) 14.6 25.66 42.34 5 87.6
60% of Scope 8.76 15.40 25.40 3.00 52.56
Stretches
Total Linear Length
SN Stretches length No. of Stretches (km) Cummulative Linear Length (km)
1 Sum of ≥ 1500 m & < 2000 m 3 4.76
2 Sum of ≥ 1000 m & < 1500m 3 3.41
18.54
3 Sum of ≥ 500 m & < 1000m 17 10.37
4 Sum of ≥ 300 m & < 500m 53 26.53 above 300 m - 45.07 Km
5 Sum of < 300 m 128 18.64          
Total Streches acquired 204 64          

Percentage Acquired 72.64          

23-08-2018, 16th TEC 3


Status of Land Acquired (C-5) 393.700 to 401.900
Start Chainage 349.446
This Week
End Chainage 393.700 (in km)
District Vadodara
Total Scope 8.2  

Sum of ≥
300m 6.221 -
No. of 7
Streches  
Stretches Sum of ≥
100m & < 0.932 -
300m
No. of
Streches 6
 

Sum of
0.203 -
<100m
No. of
2
Streches  

Total (km) = 7.356 -


Percentage Acquired 89.71
 

23-08-2018, 16th TEC 4


STATUS OF LAND ACQUISITION (GUJARAT)
(Area in Ha.)
District Total Forest Railways Government Private

Scope Acquired/ Scope Transfer Scope Transfer Scope Transfe Scope Acquir
Transferre red red rred ed
d
Ahmedabad 133.7 118.71 0.00 0.00 104.12 104.12 2.04 2.04 27.54 12.55
Kheda 110.12 73.94 0.00 0.00 0.66 0.66 10.70 10.70 98.76 62.58
Anand 52.49 34.76 0.00 0.00 0.06 0.06 5.96 5.96 46.47 28.74
Vadodara 134.88 102.00 0.00 0.00 20.81 20.81 17.37 12.63 96.70 68.56
Bharuch 128.4 68.07 0.00 0.00 0.07 0.07 11.38 10.61 116.95 57.39
Surat 166.11 88.67 0.00 0.00 0.11 0.11 15.94 9.49 150.06 79.07
Navsari 88.66 5.26 0.00 0.00 0.04 0.04 7.69 5.22 80.93 0.00
Valsad 125.33 58.75 2.83 2.83 0.00 0.00 15.78 5.57 106.72 50.35
Guj. Total 939.69 550.16 2.83 2.83 125.87 125.87 86.86 62.22 724.13 359.24

* Forest Clearance Stage -1 given by MOEFCC on 24/01/2019.


STATUS OF JOINT MEASUREMENT SURVEY (Pvt. Plots)
(No. of Villages)

Total Pvt Land JMS Completed


Consent Agreement signed
Requirement
S.No. District
No. of
No. of Area Area No. of
Villages
Plots
(Ha.)
Village
(Ha.) Plots
Area (Ha.) % LA
s
1 Ahmedabad 16 144 27.54 16 27.54 92 12.55 46
2 Kheda 23 790 98.76 23 98.76 505 62.58 64
3 Anand 11 544 46.47 11 46.47 304 28.74 62
4 Vadodara 35 795 96.7 34 92.69 524 68.56 71
5 Bharuch 27 794 116.95 26 114.67 415 57.39 49
6 Surat 28 677 150.06 20 116.74 294 79.07 53
7 Navsari 28 711 80.93 23 57.67 0 0.00 0
8 Valsad 30 986 106.72 30 106.72 468 50.35 48
Sub- Total
9
(Gujarat)
198 5441 724.13 183 661.26 2602 359.24 50
STATUS OF JOINT MEASUREMENT SURVEY (GUJARAT)
(No. of Villages)
District Total JMS completed JMS JMS completed but
pend Consent not done Remarks
ing Yet to Held up
Start

• Chenpur, Dariyapur & Asarva : R&R issue


Ahmedabad 16 16 0 0 3
• Mahij (low Jantri Rate)
Kheda 23 23 0 0 1
Anand 11 11 0 0 0
• Mangrol (JMS Pending) - PAPs are
Vadodara 35 34 1 0 0
resisting for low jantri rate
• Vantarsa & Karela - Consent not yet done
Bharuch 27 26 1 0 3
due to resistance against low jantri rate,
Ankleshwar rate calculation is not
proovided
• Vareili & Kadodara- Consent to be started
Surat 28 20 8 2 0
• Kesali, Pati, Amadpur, Vejalpore &
Navsari 28 23 5 0 23
Parthan- JMS not yet done.
• In 23 villages resistance due to low Jantri
rate
• Chanvai- Consent to be started.
Valsad 30 30 0 1 0
Total 198 183 15 3  30
STATUS OF LAND ACQUSITION (PRIVATE)
(No. of Villages)

JMS
JMS
completed
completed
JMS , consent Status of Private Land acquisition
, consent
Villages pending
yet to
held up (villages)
Villages due to Consent
with Start Total
District Villages No. Pvt having resistance
(A+B+C)
in
Pvt Land A B C progress 100% 75-100% 50-75% <50%
Land

Ahmedabad 16 5 11 0 0 3 3 8 1 4 2 1
Kheda 23 0 23 0 0 1 3 21 1 5 11 3
Anand 11 0 11 0 0 0 0 11 0 2 4 5
Vadodara 35 0 35 1 0 0 1 34 4 12 13 5
Bharuch 27 0 27 1 0 3 4 23 1 6 3 13
Surat 28 0 28 8 2 0 10 18 2 8 3 5
Navsari 28 0 28 5 0 23 28 0 0 0 0 0
Valsad 30 0 30 0 1 0 1 29 1 3 20 5

Total 198 5 193 15 3 30 50 144 10 40 56 37


Income Restoration Plan
Implementation
• 26 youths from PAPs families of Kheda and Anand Districts were trained under
Entrepreneurship programme. 45 days training was given for Computer
Hardware and Networking at RUDSET Institute, Nadiad.

Certificate distribution in a fuction at Piplag village of Kheda district


• 60 youths from PAPs families of Vadodara District are being trained for
Computer Hardware & Networking, Computer accounting and welding
fabrication programme at TeamLease Institute, Vadodara.
THANK YOU