Protection of Lines • The probability of faults occurring on the lines is much more due to their greater length and exposure to atmospheric conditions. This has called for many protective schemes. The requirements of line protection are : • (i) In the event of a short-circuit, the circuit breaker closest to the fault should open, all other circuit breakers remaining in a closed position. • (ii) In case the nearest breaker to the fault fails to open, back-up protection should be provided by the adjacent circuit breakers. • (iii) The relay operating time should be just as short as possible in order to preserve system stability, without unnecessary tripping of circuits. • The protection of lines presents a problem quite different from the protection of station apparatus such as generators, transformers and busbars. • While differential protection is ideal method for lines, it is much more expensive to use. The two ends of a line may be several kilometres apart and to compare the two currents, a costly pilot-wire circuit is required. Time-graded overcurrent protection • Over current protection of a radial feeder by definite time relays. The time of operation of each relay is fixed and is independent of the operating current. • Thus relay D has an operating time of 0·5 second while for other relays, time delay is successively increased by 0·5 second. • If a fault occurs in the section DE, it will be cleared in 0·5 second by the relay and circuit breaker at D because all other relays have higher operating time. In this way only section DE of the system will be isolated. • If the relay at D fails to trip, the relay at C will operate after a time delay of 0·5 second i.e. after 1 second from the occurrence of fault. Disadvantages: • Back up time takes too much time. • Breaking time is higher near generation. Discrimination by Current • Discrimination by current relies on the fact that the fault current varies with the position of the fault because of the difference in impedance values between the source and the fault. • Hence, typically, the relays controlling the various circuit breakers are set to operate at suitably tapered values of current such that only the relay nearest to the fault trips its breaker. • PILC (Paper Insulated, ZL = 0.24 Ω • Lead Covered ) Cable.
• For a fault at F1, the system short-circuit current is given by:
• I = 6350 / (ZS + ZL1) A (6350=11000/√3 per phase vol.) • where: • ZS = source impedance = 112 / 250 = 0.485 Ω. • ZL1 = cable impedance between C and B = 0.24 Ω • Hence, • I = 6350 / 0.725 = 8800 A • So, a relay controlling the circuit breaker at C and set to operate at a fault current of 8800A would in theory protect the whole of the cable section between C and B. • Point #1 – It is not practical to distinguish between a fault at F1 and a fault at F2, since the distance between these points may be only a few metres, corresponding to a change in fault current of approximately 0.1%. ZL1 = 0.24 Ω ZL2= 0.04 Ω
• Now, assuming a fault at F3, at the end of the 11kV cable feeding the
4MVA transformer, the short-circuit current is given by: • I = 6350 / (ZS + ZL1 + ZL2) • Thus, assuming a 250MVA source fault level: I = 6350 / (0.485 + 0.24 + 0.04) = 8300A • Thus Relay is Set at 8300A. • This is how Relay value is set by current graded process. Discrimination by both Time and Current • Evaluate the actual Relay timing in each bus bar of following system using time-current grading. Relay current Setting for Relay B
Plug Setting Multiplier for Relay B
Corresponding Operating Time for
Relay B of above PSM
Actual Operating Time for Relay B
Relay - A Thus according to time grading system, the required time of operation At Relay A is 0.80 sec by considering 0.5 s coordination time interval
Relay current Setting for Relay A
Plug Setting Multiplier for Relay A for
Fault at Bus B
Hence, the time of operation of Relay A
for fault at Bus – B is But the required TSM for Relay A can be obtain from the ratio of Required time of operation at Relay A by time grading and Operating time of Relay A for fault at Bus -B