Gold Ridge Mine Heap

Leaching Construction Plan


Five main tasks

 Oxidized ore mining

 Heap leaching site construction

 Installation and maintenance

 Civil engineering construction

 Plant maintenance
Oxidized ore mining
 Measured ore reserve 1.6mt

 Geology team locate the boundary of oxidized zone and give the advice for
dilution control when mining. (13/10/2020)

 Mining technical team make the pit design according to geology team and
calculate the stripping ratio.(29/10/2020)
 Find out the appropriate place for waste rock dumping
 Road design
 Guidance at mining site
Preliminary Oxidized Ore Mining Zone
 Construction team focus on transportation road

 Spillway, cut-off ditch construction (06/10/2020)

 Road pavement and foundation (13/10/2020)

 Start stripping (14/10/2020)

 Mining start on (19/10/2020)


Heap Leaching Site Construction

 Top soil removing(23/09/2020) 5

 Transfer road (27/09/2020) 4

 Earth excavation (16/10/2020) 15

 Anti seepage engineering (01/11/2020) 11

 Absorption excavation (09/11/2020) 7


Installation and maintenance

 Sodium cyanide warehouse maintenance (23/10/2020) 30

 Tailing tank removal (15/10/2020) 25

 Drinking water pipeline installation (21/11/2020)26

 Absorption tower installation (15/10/2020) 20

 Pipeline to mining site (10/11/2020) 21

 Power supply room installation (30/11/2020) 31


Civil Engineering Construction

 Lab transformer basement construction

 Power house and pump basement construction (15/10/2020) 18

 Drinking water dam (20/10/2020)

 Floating process plant basement replacement (25/10/2020)


Plant Maintenance

 Sodium sulphide warehouse maintenance (24/09/2020) 2

 Mechanical workshop maintenance (29/09/2020)2

 Power plant workshop maintenance(01/10/2020) 3

 Other project (20/11/2020) 31