HAI PHONG I (2x300MW) THERMAL POWER PROJECT DEC/MC CONSORTIUM

COAL HANDLING SYSTEM MONITOR


#1 #2 #3 #4 #5 #6 #7 #8 #9 #10
Conveyor No. 5A/5B(HP1)

Status As On 25 Jan 2010

Erection of 1st,2nd finished. Erection of 3rd,4th Unloader in progress


#11 #12
Transfer Tower No. 4

Conveyor No. Conveyor No. 8X/8Y(HP2) 8X/8Y (HP2)

Access Bridge

Access

Access

Limestone Milling House

Unloading room

Berth Electricity House

Coal Handling Control House

Transfer Tower No. 1

Conveyor No.2

Coal Sampling House

Transfer Tower No. 2

Conveyor No. 3

Conveyor No.3

Conv. 6

Dwg. Tag No. 9 & 10 (1 row of support fdn.)


Conveyor No. 1 (Conveyor Floor @ Bunker Bay)

Coal Shed Fdn. Tail Driver #7 Station

and RC Frame
Conveyor No. 7

Conveyor No.7

Transfer Tower No. 5


Booster Pump House fighting

Lighting Room

Coal Shed
Coal conv. Tunnel #10

Open Coal Open CoalStorage Storage

Coal tunne #11l / Room

Transfer Tower (Hai Phong 2)

Sedimentation Basin

Transfer Tower No. 7

Conveyor No.9

Coal Shed Foundation RC Frame

Conveyor No. 9

LEGEND:
GROUND WORKS CIVIL WORKS/FOUNDATION ONGOING STEEL STRUCTURE ERECTION ONGOING STEEL STRUCTURE ERECTION COMPLETED CIVIL / ARCHITECTURAL COMPLETE EQUIPMENT ERECTION ONGOING EQUIPMENT ERECTION COMPLETE TO BE DONE
Tail Driver #8 Station Conveyor No.8 Coal Shed Foundation and RC Frame Bulldozer House Conveyor No. 8

Conveyor No. 11

Dwg. Tag No.: Conv. 7&8 (2 rows of support foundation)

Coal Shed

Open Coal Storage

Transfer Tower No. 6

CHART: 2

STATUS AS ON: 25 MAY 2009 SCHEDULE ACTIVITY


PLAN (Lev.3, Rev.5) START FINISH START ACTUAL FINISH

COAL HANDLING CONTROL HOUSE Ground/ Civil / Architectural 21-Jan-08 Erection (Mech/E&I) 20-Nov-08 BERTH ELECTRICITY HOUSE (JETTY VOLTAGE ROOM) Ground / Civil / Architectural 15-Apr-08 Erection (Mech/E&I) 09-Nov-08 COAL SAMPLING HOUSE (remaining works) Civil / Structural/Architectural 26-Apr-08 Erection (Mech/E&I) 01-Jan-09 BUNKER BAY (Conveyor Floor & Raw Coal Bunkers) Civil / Structural/Architectural 01-Aug-07 Erection (Mech/E&I) 17-Jun-08 TAIL DRIVE STATION #7 Excav / Civil / Architectural 10-Jun-08 Erection (Mech/E&I) 31-Dec-08 TAIL DRIVE STATION #8 Excav / Civil / Architectural 16-Oct-08 Erection (Mech/E&I) 31-Dec-08 TRANSFER TOWER #7 Civil / Structural/Architectural 28-Jun-08 Erection (Mech/E&I) 15-Feb-09 Coal Yard / Coal Storage Shed (Reclaimer/Stacker) Ground / Civil / Architectural (remaining) 02-Apr-08 Erection (Mech/E&I) 13-Jan-09 BULLDOZER HOUSE Civil / Architectural 20-Jan-08 Erection (Upper Structure) 16-May-09 CONVEYORS CONVEYOR # 5 Erection (Mech/E&I) 01-Jan-09 CONVEYOR # 4 Erection (Mech/E&I) 15-Dec-08 CONVEYOR # 3 Erection (Mech/E&I) 15-Dec-08 CONVEYOR # 2 Erection (Mech/E&I) 15-Dec-08 CONVEYOR # 6 Erection (Mech/E&I) 15-Dec-08 CONVEYOR # 7 Erection (Mech/E&I) 24-Jan-09 CONVEYOR # 8 Erection (Mech/E&I) 15-Dec-08 CONVEYOR # 9 Erection (Mech/E&I) 15-Dec-08 CONVEYOR # 10 Erection (Mech/E&I) 15-Dec-08 CONVEYOR # 11 Erection (Mech/E&I) 28-Dec-08 SEDIMENTATION BASIN Ground / Civil 01-Jun-09 BOOSTER PUMP HOUSE Ground / Civil / Architectural 01-Jun-09 Erection (Mech/E&I) 01-Jul-09

19-Dec-08 23-Feb-09 28-Dec-08 23-Feb-09 25-Sep-08 02-Mar-09 02-Dec-08 30-Nov-08 15-Nov-08 08-Feb-09 29-Nov-08 08-Feb-09 23-Jan-09 30-Mar-09 22-Jan-09 12-Apr-09 29-Jun-09 14-Jun-09

21-Jan-08 26-Jan-09 15-Apr-08 11-Feb-09 26-Apr-08 27-Feb-09 01-Aug-07 17-Jun-08 10-Jun-08 07-Mar-09 01-Dec-08

20-May-09

15-Nov-09

27-Nov-08 21-Apr-09 02-Apr-08 26-Mar-09 20-Jan-08 27-Aug-09

20-Nov-09

15-Jun-09 31-May-09 15-May-09 15-Jun-09 12-May-09 31-May-09 15-Jul-09 30-Jun-09 15-Jun-09 30-Jun-09 30-Jul-09 30-Jul-09 15-Aug-09

27-Feb-09 26-Feb-09 14-Oct-08 20-Dec-08 25-Apr-09

29

29 29 29 0 29 0 29

23-Mar-09 10-Sep-09 10-Aug-09 25-Nov-09