MANHOLE CONSTRUCTION

AWARENESS

1
Table of Content

- Introduction

- Pre-Construction

- Typical Manhole Drawing Layout

- Construction
INTRODUCTION

The Purpose of this Presentation for Manhole Construction Awareness to all


the Project Site Team.

For the strict compliance of the contract documents, project specification for
concrete works and under Qatar Construction Specification (QCS) 2014 ,
Section 08 : Drainage Works, Part 04 : Pipeline Installation, Item 4.5 :
Pipeline Structures and Appurtenances , Sub-Item 4.5.1 : Manholes for
Foul Sewerage. Sub-Item 4.5.2 : Manholes for Surface Water Sewerage
PRE-CONSTRUCTION

Mandatory Training

- Site Engineer, Foreman, Labor and Safety Officer were mandatory trained to
make sure that the workers are competent to perform the activities in safe way

Method Statement

- The purpose of this Method Statement is to describe the sequence and


methodology for the construction of Manhole with the strict compliance of the
contract and specifications.
PRE-CONSTRUCTION

Licenses & Permits

- All the operators and drivers shall have the valid operating licenses /
permits form relevant authorities

Traffic Management

- Before commencing with any work that is likely to cause


disturbance to the existing road network, diversions shall be addressed
and approved by Ministry of Interior (MOI)
PRE-CONSTRUCTION

Inspection and Test Plan

- Contractor will plan the inspection date and test to be conducted for
this particular work

Risk Assessment

- Contractor will conduct Risk Assessment before executing the


works regarding the safety, quality plan and environment issues. i.e. dust
and noise at the surrounding.
PRE-CONSTRUCTION

Material Approval / Pre-qualification of the Subcontractor

- Contractor needed to submit the Materials to be used for Engineer – ITAL


approval and ensure this is the required materials as per Contract Agreement,
and submit Subcontractor Company profile for pre-qualification purpose.

Approved Schedule

- Before commencing , Contractor will prepare and submit the


Schedule for Execution and to be approved by Engineer - ITAL
TYPICAL MANHOLE DRAWING LAYOUT

Precast concrete
setting rings Min 300mm width
foam concrete from
base to road formation
TYPICAL MANHOLE DRAWING LAYOUT
TYPICAL MANHOLE DRAWING LAYOUT
CONSTRUCTION

SITE CLEARING & SETTING-OUT

EXCAVATION

LEVELING & COMPACTION

BLINDING & SCREEDING WORKS


FIRST
– 75mm Blinding with SRC 25 and 50mm OPC 25
Screed
STAGE
SURVEY CHECKING

MANHOLE BASE

MANHOLE WALLS Rebars, Formworks & Casting

MANHOLE BOX-OUTS

MANHOLE CURING Curing needed 24 hours and covered with hessian cloth
CONSTRUCTION
OUTER WALL 2 Coats of Bitumen Paint, 3mm Waterproofing
Membrane & 6mm Protection Board) in normal
REMOVAL OF FORM WORKS
areas without foam concrete
TANKING MEMBRANES & PROTECTION BOARDS
FOAM CONCRETE SURROUND SHALL BE USED (IF AREAS ARE NOT
POSSIBLE TO BE COMPACTED USING SUITABLE BACKFILL MATERIALS)
SECOND
INTERNAL WALL

FLOOR BENCHING WORKS After Pipes Installed within manhole walls


STAGE
Shutter works
Concrete by
approved Mix Acid Resistant Epoxy Mortar 1:2
Design Epoxy Internal Coating to be Applied
PRE-CAST COVER SLAB

INSTALLATION WORKS Manhole Cover Frame to be installed prior to casting works


CONSTRUCTION

MANHOLE COVER FRAME

GROUTING WORKS
Approved Non Shrink Grout to be used
FINAL
MANHOLE COVER STAGE
INSTALLATION WORKS

Manhole Cover and Frame will be delivered


in one (1) Set, shall be kept together

INSPECTION FOR HANDING OVER

SNAGLIST WORKS

As-Built Drawings, Operation Manual & Other Project Close-out Requirements