Presentation Manhole Construction - Revised
Presentation Manhole Construction - Revised
AWARENESS
1
Table of Content
- Introduction
- Pre-Construction
- Construction
INTRODUCTION
For the strict compliance of the contract documents, project specification for
concrete works and under Qatar Construction Specification (QCS) 2014 ,
Section 08 : Drainage Works, Part 04 : Pipeline Installation, Item 4.5 :
Pipeline Structures and Appurtenances , Sub-Item 4.5.1 : Manholes for
Foul Sewerage. Sub-Item 4.5.2 : Manholes for Surface Water Sewerage
PRE-CONSTRUCTION
Mandatory Training
- Site Engineer, Foreman, Labor and Safety Officer were mandatory trained to
make sure that the workers are competent to perform the activities in safe way
Method Statement
- All the operators and drivers shall have the valid operating licenses /
permits form relevant authorities
Traffic Management
- Contractor will plan the inspection date and test to be conducted for
this particular work
Risk Assessment
Approved Schedule
Precast concrete
setting rings Min 300mm width
foam concrete from
base to road formation
TYPICAL MANHOLE DRAWING LAYOUT
TYPICAL MANHOLE DRAWING LAYOUT
CONSTRUCTION
EXCAVATION
MANHOLE BASE
MANHOLE BOX-OUTS
MANHOLE CURING Curing needed 24 hours and covered with hessian cloth
CONSTRUCTION
OUTER WALL 2 Coats of Bitumen Paint, 3mm Waterproofing
Membrane & 6mm Protection Board) in normal
REMOVAL OF FORM WORKS
areas without foam concrete
TANKING MEMBRANES & PROTECTION BOARDS
FOAM CONCRETE SURROUND SHALL BE USED (IF AREAS ARE NOT
POSSIBLE TO BE COMPACTED USING SUITABLE BACKFILL MATERIALS)
SECOND
INTERNAL WALL
GROUTING WORKS
Approved Non Shrink Grout to be used
FINAL
MANHOLE COVER STAGE
INSTALLATION WORKS
SNAGLIST WORKS