Implementation of

Environmental Safeguards
Second City Region evelopment Project
Loan 3808/3809-BAN
1. Environmental Category of subprojects
The project CRDP-II is classified as category B for environmental
safeguards per ADB Safeguard Policy Statement (SPS), 2009,
consequently the subprojects under the project are considered
Category B. Construction and Rehabilitation of Roads and
associated drainage improvements of targeted subproject packages
are categorized as Orange B category subprojects
 
For the purpose of obtaining the environmental clearance certificate
(ECC) from DOE for the Second CRDP, an application was filed by
PMCU vide LGED memo 46.02.000.913.99.001. 1-07; dated 30/08/2018
and 27/12/2018. Accordingly DOE issued an Environmental Clearance
Certificate by means of a letter No. DOE/ Clearance/5194/2013/
(clearance Certificate Number 53)/ issue Date 10/02/2019.

 
2. Initial Environmental Examination (IEE)
Initial Environmental Examinations (IEEs) of 13 (thirteen) readiness
sub-projects have been prepared, and concurrence on the IEEs of
ADB has already been obtained.
Table : Package-wise IEE Documentation Status
Name of Detailed Submitted to Disclosed on Site-specific Remark
Subprojects Design ADB’s Project
EMP
(Submission website Final IEE
approved by
Date Provided
Project
  Director?
(Yes/No)
(Yes/No)
1. Gazipur City Detailed Design Ref to ADB’s Disclosed ADB
Corporation: Complete website for the website Yes Yes
GCC (W-01) Date
2. Gazipur City Detailed Design Disclosed ADB
Corporation: Complete --“-- website Yes Yes
GCC (W-02)
3. Araihazar Detailed design Disclosed ADB
Upazila: Complete website
--“-- Yes Yes
Araihazar (W-
01)
4. Araihazar Detailed design Disclosed ADB
Upazila: Complete website
--“-- Yes Yes
Araihazar (W-
02)
2. Initial Environmental Examination (IEE)…contd
Table : Package-wise IEE Documentation Status
Name of Detailed Submitted to Disclosed on Site-specific Remark
Subprojects Design ADB’s Project
EMP
(Submission website Final IEE
approved by
  Date Provided
Project
(Yes/No)
Director?
(Yes/No)
5. Araihazar Detailed design Disclosed ADB
Upazila: Complete website
--“-- Yes Yes
Araihazar (W-
03)
6. Savar Detailed design Disclosed ADB
Upazila: Savar Complete --“-- website Yes Yes
(W-01)
7. Savar Detailed design Disclosed ADB
Upazila: Savar Complete --“-- website Yes Yes
(W-02)
8. Savar Detailed design Disclosed ADB
Upazila: Savar Complete --“-- website Yes Yes
(W-03)
2. Initial Environmental Examination (IEE)…contd
Table : Package-wise IEE Documentation Status
Name of Detailed Submitted to Disclosed on Site-specific Remark
Subprojects Design ADB’s Project
EMP
(Submission website Final IEE
approved by
  Date Provided
Project
(Yes/No)
Director?
(Yes/No)
5. Araihazar Detailed design Disclosed ADB
Upazila: Complete website
--“-- Yes Yes
Araihazar (W-
03)
6. Savar Detailed design Disclosed ADB
Upazila: Savar Complete --“-- website Yes Yes
(W-01)
7. Savar Detailed design Disclosed ADB
Upazila: Savar Complete --“-- website Yes Yes
(W-02)
8. Savar Detailed design Disclosed ADB
Upazila: Savar Complete --“-- website Yes Yes
(W-03)
9. Araihazar Detailed design Disclosed ADB
Upazila: Complete website
--“-- Yes Yes
Araihazar (W-
03)