You are on page 1of 2

- KSA Team

Daily Activity Report


Dated 6/2/2020 Report No. 44

Team Lead Haidar Ali Zaidi Location Work From Home

Team Members Haidar

Project Name Services, Sakaka, Marjan TCF, Sabic HQ

Weekly Planned Activities Daily Planned Activities

S.No Description Status Activities Planned Activities Performed

Services : Review with PEG Telecom team for


Services : Submission of techno-commercial offer Services : Review with PEG Telecom team
1 SeaDrill CCTV Requirement. PEG team to share
to Sinopec for Telecom Systems for SeaDrill CCTV Requirement
solution & prices within 2 days

Services : Follow up with Marafiq team for VFD


Services : Submission of revised techno- Services Case. Client to issue NTP (Notice to
Services : Follow up with Marafiq team for
2 commercial offer to Ma'aden Aluminium Smelter Proceed) for issuance of PO with its
VFD Services Case
Plant as per comments received Procurement once mobilization of L&T
Engineer from India Pool confirmed.

Marjan : Submission of invoices for April & May Marjan : Preparation of BPR for 12U Marjan : Preparation of BPR for 12U Cabinet
3
(advance) Cabinet requirement for UPS in Marjan requirement for UPS in Marjan

Marjan : Updating Cisco vendor regarding Marjan : Updating Cisco vendor regarding
Marjan : Services PR creation & release for OEM
mismatch in delivered components & mismatch in delivered components &
4 services required at site during commissioning
coordinating with Client at site to share coordinating with Client at site to share
stage
required inputs required inputs

Marjan : Preparation & submission of Marjan : Preparation & submission of delivery


Sabic HQ : Preparation of S-Curve for Master log
5 delivery notes for IP Phone & Firewall with notes for IP Phone & Firewall with Client as per
to review Procurement & Projects progress
Client as per revised version revised version

Sakaka : Discussion with DG Set vendor


Sakaka : Discussion with DG Set vendor
Services : Finalization with MAPA with regards to (Sawari) regarding punch point of level
6 (Sawari) regarding punch point of level
Ihsa Water Improvement Project indication received at site from Client. Vendor
indication received at site from Client
to revert with solution within 2 days

Marjan : Revision of site deliverable inputs &


Services : Submission of AMC & Spares Supply Marjan : Revision of site deliverable inputs
7 master log as per latest updates & submission
offer to NOMAC for Sakaka Power Plant & master log
to Projects with records
Issues & Bottlenecks Being Faced Work From Home Inputs

S.No Description On Hold With Particulars Yes/No

Industrial switches for Marjan to be re-ordered, previously


My IS and I know what deliverables we have
1 considered OTS switches having deilvery issues since manufacturing Projects Yes
planned to complete today
work being done in China

I was able to adhere to my normal work timings


Yes
today

I have attended to & returned all phone calls


and have responded to all my internal and Yes
external official mails

There is no action pending with me regarding


my business responsibilities including with a Yes
customer

I have not left my home today Yes

REMARKS :
*Site surveys to Maaden & SWCC , with regards to Services cases, have been postponed by Client due to Covid19 Pandemic. No outsiders are being allowed
presently to visit industrial zones.