You are on page 1of 2

- KSA Team

Daily Activity Report


Dated 7/1/2020 Report No. 67

Team Lead Haidar Ali Zaidi Location Work From Home

Team Members Haidar

Project Name Services, Sakaka, Marjan TCF, Sabic HQ

Weekly Planned Activities Daily Planned Activities

S.No Description Status Activities Planned Activities Performed

Services : VAT Increase Intimation to Client MAPA : Preparation of ABG/PBG Request MAPA : Preparation of ABG/PBG Request
1
(MAPA) forms & submission forms & submission

Services : ABG/PBG Preparation & Follow Ups For MAPA : Submission of DCR & RFI with MAPA : Submission of DCR & RFI with regards
2
MAPA regards to Level Transmitters to Client to Level Transmitters to Client

Services : BPR Release For Materials Required in Services : Meeting with Sales & RMP Team Services : Meeting with Sales & RMP Team to
3
FAT for MAPA to discuss RMP AMC Case discuss RMP AMC Case

MAPA : Discussion with E&H with regards


MAPA : Discussion with E&H with regards to
to compliances & scheduling meeting with
4 Services : Instrumentation finalization for MAPA compliances & scheduling meeting with
Engineering team to finalize the
Engineering team to finalize the requireement
requireement

Services : PLC/Server/Telecom cabinets order Services : Preparation of base costing for Services : Preparation of base costing for RMP
5
placement for MAPA RMP AMC AMC

Sakaka : Preparation of costing for Sakaka Sakaka : Preparation of costing for Sakaka
6 Marjan : June Invoice Submission For Deliverables
Spares Supply & AMC Spares Supply & AMC

Marjan : PR approval request for OEM


Marjan : PR approval request for OEM Services
7 Sabic : BPR Creation & Finalization Services (Aruba, Huawei etc) required at
(Aruba, Huawei etc) required at site
site
Issues & Bottlenecks Being Faced Work From Home Inputs

S.No Description On Hold With Particulars Yes/No

Industrial switches requirement for Marjan yet to be finalised & My IS and I know what deliverables we have
1 Projects Yes
order to be re-issued. planned to complete today

Inputs awaited from Client (MAPA) for field instrumentation I was able to adhere to my normal work
2 Client Yes
finalization. timings today

I have attended to & returned all phone calls


and have responded to all my internal and Yes
external official mails

There is no action pending with me regarding


my business responsibilities including with a Yes
customer

I have not left my home today Yes