You are on page 1of 2

- KSA Team

Daily Activity Report


Dated 8/18/2020 Report No. 22

Team Lead Haidar Ali Zaidi Location Work From Home

Team Members Haidar

Project Name Services, Sakaka, Marjan TCF, Sabic HQ

Weekly Planned Activities Daily Planned Activities

S.No Description Status Activities Planned Activities Performed

Services : Meeting with SWCC & MAPA for


proposed Scada Solution discussion.

SWCC & MAPA explained the salient features of


Wonderware Scada proposed for Ihsa Water
Improvement Project.

1 Services : Submission of techno-commercial offer Services : Meeting with SWCC & MAPA for SWCC impressed with our presentation &
to Sinopec for Telecom Systems proposed Scada Solution discussion. approved the proposed solution on video call
meeting. On paper approval shall be taken by
MAPA.

Finalised commercial offer of 970K USD has


been submitted to MAPA by Sales Team.
MAPA's response awaited to start with projects
work.

Services : Submission of revised techno- Services : Discussion with iVision team, Sales
✘ Services : Offer preparation for Sinopec team & Telecom Proposals teams with regards
2 commercial offer to Ma'aden Aluminium Smelter Telecom System to Sinopec Telecom System. Costing work in
Plant as per comments received
progress


Services : Submission of revised offer to Denys
3 Marjan : Submission of invoices for April & May Services : Submission of revised offer to Arabia team for Telecom Services.
(advance) Denys Arabia team for Telecom Services
Service case value : 9K USD

Marjan : Submission of draft invoice &


4 Sakaka : Invoicing for Poles & other materials to be packing list to Accounts for invoice Marjan : Submission of draft invoice & packing
delivered list to Accounts for invoice generation.
generation

Marjan : Services PR creation & release for OEM Services : Discussion with Procurement with
General : Online training for Schneider &
5 services required at site during commissioning Nokia regards to Field instruments procurement in
stage MAPA Service case.


Sabic HQ : Finalization of Price breakdown (Supply,
6 Installation, Commissioning) & submission to
Client

Services : Finalization with MAPA with regards to ✘


7
Ihsa Water Improvement Project
Issues & Bottlenecks Being Faced Work From Home Inputs

S.No Description On Hold With Particulars Yes/No

Sakaka : 48V DC power supplies (Meanwell) not yet dispatched from


Dubai for site. HS Code issues going on between Procurement/QC Procurement/QC & My IS and I know what deliverables we have
1 Yes
and Vendor. If further delayed, site activities going to be severly Vendor (Enpower) planned to complete today
affected for petty amount of 8K SAR

Marjan : OTS System switches PO has been cancelled due to delivery


2 issues owing to COVID19. Alternatives being reviewed. Moxa Procurement/ I was able to adhere to my normal work timings Yes
equivalent is exceeding our budget. Projects today

I have attended to & returned all phone calls


and have responded to all my internal and Yes
external official mails

There is no action pending with me regarding


my business responsibilities including with a Yes
customer

I have not left my home today Yes

REMARKS :
*Site surveys to Maaden & SWCC , with regards to Services cases, have been postponed by Client due to Covid19 Pandemic. No outsiders are being allowed
presently to visit industrial zones.