INTRODUCTION

                                                                                                                        
Unitized curtainwalls are factory-assembled and -glazed, then shipped to the job site in units
that are typically one lite wide by one floor tall. Only one unit-to-unit splice (usually
a silicone sheet or patch) needs to be field-sealed, and only one anchor per mullion needs to be
attached to the face or top of the floor slab. Interlocking unitized curtain
wall frame members are weatheripped to seal to one another, both horizontally and vertically.

A GLASS AND ALUMINUM CURTAIN WALL FABRICATED AND INSTALLED AS A PANEL


SYSTEM IS REFERRED TO AS A UNITIZED CURTAIN WALL SYSTEM.
THE UNITIZED SYSTEM IS ASSEMBLED ON THE BUILDING AS PANELS INSTEAD OF
TUBULAR SECTIONS, WHICH MATE AT ASSEMBLY TIME TO FORM THE CURTAIN WALL
SYSTEM.
THE PANELS ARE INSTALLED IN SHINGLE FASHION, STARTING FROM THE BOTTOM OF
THE BUILDING AND GOING AROUND EACH FLOOR AND UP THE BUILDING.
COMPONENTS OF UNITISED WALL
SYSTEM
 STEEL OR ALUMINUM ANCHORS
 MULLIONS (VERTICAL TUBES)
 RAILS (HORIZONTAL MULLIONS)
 VISION GLASS
 SPANDREL GLASS
 INSULATION AND METAL BACK PANS
IN ADDITION, THERE ARE VARIOUS HARDWARE
COMPONENTS TO INCLUDE
• ANCHORS,
• ALUMINUM CONNECTORS,
• SETTING BLOCKS,
• CORNER BLOCKS,
• PRESSURE PLATES,
• CAPS,
• GASKETS AND
• SEALANTS. 
Unitised systems are used where the
movement or deflections in a building are
such that a stick system is inappropriate.
Unitised systems are popular because they eliminate, or reduce, the need Most unitized curtainwall systems are
for on site sealing, therefore making them LESS RELIANT on the installed in a sequential manner around
standard of site workmanship. However, for unitised systems to perform to
each floor level, moving from the bottom
their full potential, it is critical that the BRACKETS to which the
components are fixed are ACCURATELY INSTALLED. Unitised systems
to the top of the building.
do not require decanting during refurbishment contracts. The unitised Their principal benefits ARE SPEED OF
systems offer the benefits of factory fabrication in controlled environment, INSTALLATION, MINIMAL ON SITE
and very rapid assembly on site. However, they are GENERALLY MORE LABOUR, AND LOWER
EXPENSIVE than stick systems and require longer lead times.
INSTALLATION COSTS. However,
these are obviated to an extent by the
increased storage and shipping cost, the
need for very careful site handling, and
the requirement for expensive lifting
equipment on site.
CHARACTERISTICS OF UNITISED WALL SYSTEM

Selection Criteria Unitized Curtainwall


Project Size Large

Repetitive
Wall Configuration
(Large expanses of flat wall)

Joint Pattern Uniform horizontal sill line


Glazing Factory

Inter-story Movements Inter-locking frames accommodate movements

Quality Control Controlled factory conditions

Modification Pre-engineered
Sealing Minimal field sealing
Field Labor Cost Low

Fast
Field Labor Duration
(Often setting 75 sqft or more per unit)
Set from the interior
Access and Safety
(Exterior optional
FEATURES:
●As the unitized panel is of high bunch production and, its assembly being completed in factory, high assembly precision,
the quality is easy to be controlled.
●Inlaying method is used for connection among unitized panels. Meanwhile, it has a powerful absorbing capacity for
temperature deformation, displacement between stories, seismic deformation, etc.
●Inlaying method is used for connection among unitized panels, which ensures a high degree of accuracy for installation
and positioning as well as high degree of facade flatness.
●The structural sealing method is adopted among unitized panels, and the traditional jointing sealing sealant has already
been replaced by sealing sealant strip, which ensures not only sealing property but also an effective decrease on pollution
level on the surface of curtain wall, nice appearance and neatness, with improvement of decorative effect.
• For the structural system, the multi-layers continuous integrated sealing
method is applied at inlaying area among unitized panels, which forms
many air cavities. Meanwhile,the use of“Rain Screen Principle”as well as
the step-by-step pressure reduction is to achieve the goal of sealing
and water resistance. Because of a concealed drainage system
built inside, a limited number of rain water
infiltrated into the curtain wall will be released outside the system in
layered and cross-bedded way. The sealing property of system is reliable,
which can prevent the rain water leakage and air infiltration.
 Excellent thermal performance and perfect energy-saving
TYPES OF UNITISED effect.
STRUCTURES AND ●Various sorts of finishing materials, such as glass, metallic
sheet material, stone and artificial sheet material, can be
MATERIAL adopted flexibly.
UNITISED CURTAIN WALL WITH UNIQUE  According to the actual circumstances, the unitized glass
STRUCTURES, SUCH AS: curtain wall can be fabricated into a variety of frame
appearances, such as
◇TRIANGLE PANEL UNITIZED CURTAIN  exposed-frame system,
WALL
◇TRAPEZIUM/PARALLELOGRAM PANEL
 hidden-frame system,
UNITIZED CURTAIN WALL  semi-hidden frame system and
 exposed concealed frame mixed system.
◇HORIZONTAL SINGLE DIRECTION ARC
UNITIZED CURTAIN WALL o If necessary, vertical decorative fin (glass, aluminum and
◇VERTICAL SINGLE DIRECTION ARC terra cotta panel), horizontal decorative panel and sun-shading
UNITIZED CURTAIN WALL panel (support frame), etc. can be fixed.
◇BIDIRECTIONAL ARC
(HYPERBOLOID) UNITIZED CURTAIN WALL
◇DEFORMED ELEVATION WARP PANEL
UNITIZED CURTAIN WALL AND ETC.
In this system, all the panels are pre-assembled
before arrival on-site, so the speed of construction
is fast.
Due to the main assembly occurring in a carefully
controlled factory environment, this system has
higher quality and also easier to manage.
For mid to tall rise buildings with large areas of
curtain wall, unitized systems are typically
reserved

ADVANTAGES AND
DISADVANTAGES The factory processing of unitized glass curtain
wall is complicated, the form of the component
increases the amount of aluminum profile, so the
cost is higher than the frame curtain wall of the
same material.