You are on page 1of 18

Safety

at
Coal Unloading System
Penna Power Plant ,
1
Ganesh Pahad.
Safety at
Coal Unloading System

Vehicle moving on to lift Vehicle moving on to lift

Penna Power Plant ,


2
Ganesh Pahad.
Safety at
Coal Unloading System
Vehicle engine switched off &
Door Locking
Driver comes out from vehicle

Penna Power Plant ,


3
Ganesh Pahad.
Safety at
Coal Unloading System

Chain locking to Vehicle Confirming Chain Locking

Penna Power Plant ,


4
Ganesh Pahad.
Safety at
Coal Unloading System
Don’t clean Slowly Vehicle to be lifted
hopper while
vehicle is on
lift table

Penna Power Plant ,


5
Ganesh Pahad.
Safety at
Coal Unloading System

Don’t beat vehicle or


external cleaning

Don’t clean when vehicle


in lifting position

Penna Power Plant ,


6
Ganesh Pahad.
Safety at
Coal Unloading System
No manual cleaning while vehicle is in lifting position

Penna Power Plant ,


7
Ganesh Pahad.
Safety at
Coal Unloading System

Pull Cord Switch

Emergency Push Button


Penna Power Plant ,
8
Ganesh Pahad.
Safety at
Coal Unloading System

Don’t cross over Belts Don’t clean under belts while


running

Penna Power Plant ,


9
Ganesh Pahad.
Safety at
Coal Unloading System

Don’t clean chutes while


belt running

Don’t do belt centering


while running

Penna Power Plant ,


10
Ganesh Pahad.
Safety at
Coal Unloading System

Don’t do maintenance Keep safety guards after


works while belt running Maintenance works

Penna Power Plant ,


11
Ganesh Pahad.
Safety at
Coal Unloading System

Don’t clean Head/Tail drum Chain locking to BC3 Trolley


pulley while belt running

Penna Power Plant ,


12
Ganesh Pahad.
Safety at
Coal Unloading System
General Instructions
 Before starting the plant, check which of the equipment
is available and accordingly plan an appropriate path for
the movement of coal.
 Ensure that the path so planned, is clear for coal
movement i.e. Flap Gate position, Chute position,
Interlocking etc.
 Before starting any equipment ensures that the
equipment is not subject to a P.T.W. (Permit To Work).
 Check from each location that the equipment is ready for
start and no persons are working on the equipment.
Penna Power Plant ,
13
Ganesh Pahad.
Safety at
Coal Unloading System
General Instructions
 Line up the system by starting each equipment from the
last conveyor in the up-stream path.
 Good communication between the control room and
different equipment locations is essential before starting
the system.
 Ensure that all Metal Detectors and Magnetic Separators
are working properly on running conveyors and foreign
material removed, where necessary.
 Ensure that all Electrical systems are healthy and all the
protection systems mentioned below are in service.
Penna Power Plant ,
14
Ganesh Pahad.
Safety at
Coal Unloading System
Electrical & Protection Systems
 Hooters  Magnetic Separators
 Emergency Push Buttons  Metal Detectors
 Pull Cord switches  Adequate lighting
 Zero-speed switches should be ensured in all
the areas.
 Belt sway switches
 Interlocks

Penna Power Plant ,


15
Ganesh Pahad.
Safety at
Coal Unloading System
The following precautions are to be taken before taking any
conveyor into service

There is no oil leakage at gearboxes / fluid couplings and the oil levels
are correct.
The Inlet and Discharge chutes are free from jamming and choking.
The Flap Gates are in correct positions.
All inspection doors are in the closed position.
All pull-cords are reset and the Push Button is released and ensure that all
protections are healthy.
The Alarm Siren is in working order.
Communication facility is available.
The lighting is adequate.
No Permit To Work (Isolation) is pending against that conveyor.

Penna Power Plant ,


16
Ganesh Pahad.
Safety at
Coal Unloading System
Belt Sway Switch Pull Chord Switch Zero Speed Switch

Penna Power Plant ,


17
Ganesh Pahad.
Penna Power Plant ,
18
Ganesh Pahad.