GIS Roof Casting at 11.

250m (25th March-22)


IN GPQS, PGGI 2226
Project Name - BALCO POWER RELIABILITY PROJECT
Teams: Mr.Tanmoy Ghosh, Mr. Pradip Adhikary, Mr. Bikram Gouda,,Mr. Madasu Bhaskar, Mr. Susanta Behera, Mr. Dilip Sahoo
2021-10-20 © Hitachi Energy 20:2021. All rights reserved.
GIS Roof Casting at 11.250 M
Material Requirement Planning and Received Record .

2 © Hitachi Energy 20:2021. All rights reserved.


GIS Roof Casting at 11.250 M

Drawing for GIS Roof Beam Layout

3 © Hitachi Energy 20:2021. All rights reserved.


GIS Roof Casting at 11.250 M

Drawing of Roof slab with reinforcement steel details

4 © Hitachi Energy 20:2021. All rights reserved.


GIS Roof Casting at 11.250 M

Daily Progress Review and Pictorial View

5 © Hitachi Energy 20:2021. All rights reserved.


GIS Roof Casting at 11.250 M

Scaffolding Checklist and Approved by Balco

6 © Hitachi Energy 20:2021. All rights reserved.


GIS Roof Casting at 11.250 M

Quality Checklist and Approval

7 © Hitachi Energy 20:2021. All rights reserved.


GIS Roof Casting at 11.250 M

Safety Check list and Evidences

8 © Hitachi Energy 20:2021. All rights reserved.


GIS Roof Casting at 11.250 M

Preparations before casting of slab:


• In detailed Checklist was formulated to check and confirm each and every points that has to be ensured from bottom of the
scaffolding to top of shutting boards
• 3 level inspection was carried out by M/s Karan, M/s Hitachi and BALCO teams and also a joints inspection was carried out
before signing off check list by all three parties.
• Scaffolding checked and approved by BALCO’s scaffolding champion. And same has been verified by HSE. Also,Safety team
will be present during casting.
• Rescue team has been already informed and will be present during activity.
• All documents required for gate entry of 5 nos of miller vehicles checked by security. They will be entering plant without any
waiting at gate at highest priority.
• Installation of concrete pump and pipeline up to casting level has been completed. Same has been checked and verified by
M/s Hitachi.
• Fitness certificate of concrete pump shared by RMC.
• In case of any breakdown of batching plant, RMC has tied up with other batching plant to ensure uninterrupted supply of
concrete.
• Standby pump will be entered plant on 25.03.2022 morning and sufficient amount of additional diesel stock will be
maintained for continuous pump operation.

9 © Hitachi Energy 20:2021. All rights reserved.


GIS Roof Casting at 11.250 M

Preparations on the day of casting:


Miller Vehicle Entry: Reception and unloading of miller:
BALCO Shikha Soni BALCO Bikram Kumar
Hitachi Dileep Hitachi Sushant
Karan Dhananjay Shukla Karan Purna Chandra Biswal

Casting activity and supervision Sample collections and testing


BALCO Rishabh Kumar
BALCO Rishabh Kumar
Hitachi Pradip Adhikari
Hitachi Shafiq Khan
Karan Prashant
Karan Mano Ranjan Behera

Overall Coordination for entire activities

BALCO A Niranjan Kumar


Hitachi Tanmoy Ghosh
Karan Amit Kumar Sahu

10 © Hitachi Energy 20:2021. All rights reserved.


GIS Roof Casting at 11.250 M

Site Pictures

11 © Hitachi Energy 20:2021. All rights reserved.