Recent Innovations in Coke Ovens & Coal Chemicals

By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami


1
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
Agenda

INNOVATIONS IN:

• COKE OVEN BATTERY AREA

• COAL AREA

• COAL CHEMICAL AREA

By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami


2
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
Agenda:

1. INNOVATIONS IN COKE OVEN BATTERY AREA.

By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami


3
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
A Glance at Coke Oven Batteries
in
Bhilai Steel Plant
4.3 metre tall Batteries 7 metre tall Batteries
(8 nos.having 65 ovens each) (2 nos. having 67 ovens each)

Batteries: 1 to 8 Batteries: 9 & 10


&
Oven Oven
Dimensions Dimensions
Length : 16 mt
Length : 14 mt
Avg Width : 407mm Avg Width : 410 mm
Volume : 21.6m3 Volume : 41.6 m3

By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami


4
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
TITLE OF THE INNOVATION

Redesigning and Modifying the Charging hole bricks in

Battery # 5 to address the issues related to production,

safety & environment.

By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami


5
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
THE PROBLEM:

During commissioning of the Battery it was found that while

opening the charging hole cover (hatch cover) for charging

the ovens with the help of magnetic lid lifters mounted in

charging car, the charging hole frame (hatch ring) was

getting uprooted and thus hindering the charging process.

At times the uprooted hatch ring got stuck with the oven top

paving also making it’s repositioning more difficult


By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami
6
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
This led to:

Production stoppages

Damage to CC lid lifters

Repositioning of H/R leading to time consumption

and labour wastage

Besides, Ovens remaining empty in newly rebuilt

Battery posed a threat, too.


By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami
7
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
THE ANALYSIS:

The bricks around the hatch ring, which is meant to hold

the ring/frame in its position, was not having proper

holding to restrict the hatch ring getting uprooted during

the hatch opening operation by the CC. 2 3

4
1

By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami


8
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
THE ANALYSIS (contd.):

Further in-depth analysis revealed that the bricks was not

having proper groove to support the seating of the hatch

ring. The brick design was changed by the designer !


2 3

1 4

By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami


9
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
INITIAL THOUGHTS……

It was decided to make a groove in all the bricks, which was

not possible as this caused cracks in the brick and its

thickness being less it further weakened the brick. It was then

proposed to replace the bricks with bricks being used in other

Batteries. But then it would take some time as the spare bricks

2 3
were not available in store.
1 4

By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami


10
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
In this perplexed situation …..the only ray of hope was

INNOVATION….

as, the situation demanded this problem to be addressed

2 3
adequately & most importantly……URGENTLY!
1 4

By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami


11
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
Innovation = Creative Idea / Invention

+
its useful application
2 3

1 4

By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami


12
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
INNOVATING……..THE HATCH RING BRICK DESIGN

 A frame using dia 10 mm MS rod was fabricated. In the centre


of this frame hatch ring was placed and grouted using HC
Castable powder. It was allowed to dry for 24 hours.

 Then this structure was shifted to the oven where the hatch

O N
brick had to be changed. The old hatch ring & cover were
removed, along with the bricks.
T I
V A
 After cleaning the area, 40mm thick fireclay brick lining was
laid at the surface ofO
N the area where the new casted structure

IN This was done to align the movement of lid


has to be placed.
lifters.
By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami
13
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
INNOVATING……..THE HATCH RING BRICK DESIGN(contd.)

Then the new structure of hatch ring was placed and

fireclay mortar was poured on all four sides to ensure proper

sealing.
N
Ounder observation for a
T
The implemented design was kept I
week for improvement if A
O V any and then the same was

N
IN
implemented for all charging hole (195 nos.) in Battery-5.

By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami


14
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
O N
T I
VA
NO
IN

By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami


15
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
HIGHLIGHTS OF THIS INNOVATION

 Quality of sealing around the hatch ring with this

modification is excellent.

N
 The new casted structure has resulted in zero
O
breakdowns for the past 8 T
I
V A months. There has been no

N O
case of hatch ring dislodgement and brick damages

IN
after changing all the bricks with new design.

By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami


16
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
HIGHLIGHTS (contd.)

 The modification has also been incorporated in

N
Battery No: 6, which is being rebuilt, to avoid
O
T I
A
recurrence of the same problem.
V
N O
IN
By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami
17
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
O N
T I
V A
NO
IN
By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami
18
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
O N
T I
V A
NO
IN
By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami
19
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
BATTERY- 5 BATTERY- 6

By: S K Ghosh, Pushpa Ambrose, B L Chandwani & Atul Goswami


20
© 2011 BHILAI STEEL COKE PLANT_ RECENT INNOVATIONS IN CO&CCD
Thanks