You are on page 1of 43

KALIPAY

B. MENDOZA ST., BGY. KALIPAY,


PUERTO PRINCESA CITY, PALAWAN

GROUP 5C1

BONITE, ZARINA JOY D.


FRANCISCO AIZA B. FERNANDEZ,CZAR ALEXIS
HILARIO, JUDY MAY F. NANGIT, IAN OLIVER
MANGA, GHILYN M. PUNZALAN, DAN LUIS
HISTORY

From the City Charter of PD dated January 1, 1970, Republic act 5906 with the
1970 date of plebiscite/ratification of Ref, July 10, 1969, mother barangay Culto was
created.

Memorandum Circular was passed by the City Government of Puerto Princesa


1986 - 1987
which ordered for creating and renaming of Culto 1 to Barangay Kalipay.
 Kalipay is a Cuyunon word meaning “happy or cheerful”.

 The new name is exactly describing the characterisics of the early Cuyunon and

Visayan residents of the barangay.

 Most residents found in the barangay were Roman Catholic believers.


POLITICAL
HISTORY
FIRST TINIENTE DEL
BARRIO APPOINTED
HON. ERNESTO D. HON. PABLO C.
HON. DELFIN C. FUERTES HON. FURTUNATO BALLARES
FUERTES F. YUMOL

APPOINTED
HON. JUANITO D. HON. BINO HON. EDWIN C. HON. EDUARDO
MARCELO M.ARZAGA BALLARES A. TIMBANCAYA
JR.

NEW ELECTED
HON. RUTH B. PUNONG BARANGAY,
NAGULAT HON. CHERYL E.
CUYOS
Bgy. Kalipay is an urban barangay with a total land
area of 5,568.8 sq. kilometers.
Bounded by Bgy. Maligaya in North, Bgy.
Princesa and Bgy. Magkakaibigan in East,
Bgy. Liwanag in West and Bgy. Masigla in
South.

 It has a distance of 5 km from provincial


capitol and 1 km from the national highway.
 Describing the topographical features of the
barangay, it is 0-25% hilly area and 51-75%
plain area.
 The total area of the barangay stated above
is 100% residential.
8

POPULATION
512
Based on 2018 Barangay Census of Population in the year 2018
0 to
19
5 y ea

d)
rs o l d

ol
44
rs
ea
7y 1
to
13 145
CHILDREN

82 e ar s
o ld
12 y
6 to
165
18 to 35 years old

65 367 95
ADULT 36 to 50 years old
51 to 65 years old

43
66 and above
12

₱2,400,387.72
BARANGAY INTERNAL REVENUE
ALLOTMENT
Based on 2018 Barangay Census of
Population
• 120 households with an average number of 5 persons
per household with an average annual income of
150,000.
• At present, the barangay is renting a place that serves as
their barangay hall, no health center and day care center.
• The barangay is not capable of putting a day care center
because of the decreasing number of children and
population because some private land owners gradually
improving their land resulting to demolition of some
affected residents.
PROPOSED
BARANGAY HALL
16
17

PERSPECTIVE
FLOOR PLAN
18
ELEVATIONS
19
20
ELEVATIONS
21
ROOF PLAN
22
23
24
25
26
27
28
29

DOORS AND WINDOWS


30
ESTIMATE
32
MATERIAL COST

▫ Container cost:
▪ ₱ 90,000.00 x 2
▪ = ₱ 180,000.00
EARTHWORKS
33
CONCRETE WORKS & REBARS
34
35

CARPENTRY WORKS
36

ROOFING
37

ELECTRICAL
WORKS
38

PLUMBING WORKS
39

PAINTING
40

DOORS &
WINDOWS
41

LABOR COST
▫ Labor cost: 35% of Material cost
▫ ₱ 364,779.98 x 0.35 = ₱125,671.70
42

BILL OF QUANTITIES
THANK