NLC India Limited

(A Govt. of India Navratna enterprise)

Meeting of the Consultative


Committee

Ministry of Coal

To review the Compliance of Environmental


norms by
Coal/Lignite Companies
OVERVIEW – NLCIL

Incorporation Incorporated on 14.11.1956 under the Companies Act 1956


Status Schedule “A”, Navratna CPSE Since April 2011
Core Business Diversified and Integrated Lignite, Coal Mining, Power Generation and Power Trading.
Net Worth (Consolidated)
Rs. 13,999 Cr.
As on 31.03.2021
Equity Capital
Rs. 1,387 Cr.
As on 31.03.2021
Assets (Consolidated)
Rs. 53,906 Cr.
As on 31.03.2021

Revenue from Operations


Rs. 9,946 Cr.
(Consolidated) As on 31.03.2021

Share Holding (Standalone) GoI: 79.20 %, Others: 20.80 %

 Largest opencast Lignite Mining CPSE in Asia.


 During last three years mining capacity doubled and power generation capacity increased by 50%.
 Huge foray in Renewable Energy Sector.
 First CPSE to Cross Solar Capacity of 1 GW.
Highlights
 Implemented MDO in Coal Mines allotted by GoI in Talabira II & III OC Coal Mine, State of Odisha and in
Pachwara South Coal Block (PSCB) in Dumka District, Jharkhand State of Jharkhand as end to end
execution project.
 Implemented SDO in Renewable Energy in Tamilnadu and Andaman.
Manpower (01.02.2022) Total Employees: 11,403 Nos. (Exe: 3,581; Non-Exe: 7,432; NUS - 390 Nos.)

2
Consultative Committee Meeting - 23.02.2022
NLCIL PAN INDIA PRESENCE
Operating Units Projects
Beneficiaries
MININGMW %
CAPACITY MW %
SOUTH PACHWARA
9 MTPA Coal Mines Andhra Pradesh
Lignite 313.37 6.75 0
30.60 MTPA 0
Telangana 366.23 7.89 0 0
BARSINGSAR NUPPL - Coal (MDO – Operational) 20.00 MTPA
2.1 MTPA Lig GHATAMPUR Karnataka 651.07 14.03 0 0
Mines & 3 x 660 MW Total Mining
Kerala 396.42 50.60 MTPA
8.54 400 9.13
250 MW Under
TPS Construction Tamil Nadu 1956.30 42.16 1500 34.25
POWER GENERATION 122.62 CAPACITY
Pondicherry 2.64 100 2.28
NLC Minesas Fuel
Lignite 171.00 3.693,640 MW
0 0
Barsingsar 245.00 5.28 0 0
Coal as Fuel (NTPL-JV) 1,000 MW
Odisha 0 0 400 9.13
Solar
Uttar Pradesh 0 0 1,370 MW
1843.68 42.09
TALABIRA-II & III
Unallocated
Wind Energy 418 9.01 51 136.32
MW 3.11
20 MTPA Coal Mines Total NLCIL Thermal Power
Total Capacity 4640.00 100.00
6,0614380
MW 100.00
Generation (Including JVs)
NEYVELI
32.5 MTPA Lig. Mines JV – NLC Tamil Nadu
3640MW TPS, Power Limited (NTPL) JV-Neyveli Uttar Pradesh Power Limited (NUPPL)
NLCIL 141 MW Solar
Registered Office, ANDAMAN
Chennai JV Project of NLCIL (89%) with JV project of NLCIL (51%) with UPRVUNL (49%).
20 MW
TUTICORIN TANGEDCO (11%)
Coal based Solar Power + GTPS PSCB
1000 MW TPS 8 MWHr BESS
First Coal based Plant for NLCIL Capacity: 3 x 660 MW Capacity: 9.0 MTPA
(2 x 500 MW)
4 Districts of South Project Cost – Rs. 7,293.48 Cr Project Cost – Rs. 17,237.80 Cr Project Cost – Rs. 1,795.01 Cr
TN
1209 MW Solar CoD: U #1: May 2022,
COD – Unit # 1: 18.06.15 & Exp. Commissioning Date:
TIRUNELVELI Unit # 2: 29.08.15. U #2: Aug 2022; Sept 2022
51 MW U #3: Dec 2022
Wind Power
3
NLCIL - Operating Mines and its Capacity

S.No Name of the Mine Location of the Mine Capacity/Annum

1 Lignite Mine I Neyveli, Tamilnadu 10.5 MT

2 Lignite Mine II Neyveli, Tamilnadu 15 MT

3 Lignite Mine IA Neyveli, Tamilnadu 7 MT

4 Barsingsar Lignite Mine Barsingsar, Rajasthan 2.1 MT

5 Talabira OC II & III Coal Mine Sambalpur & Jharsuguda, Odisha 20 MT(Normative)/ 23MT(Peak)
Preamble

NLCIL has followed Clean & Green Mining practices for the past 65 years which has
created a sustainable green environment. The enviro-friendly sustainable development
is achieved as a result of habitual activity of NLC India Limited since inception.

NLCIL is practicing the Environmental management system to monitor the EC/FC


conditions periodically in all industrial units of NLCIL by conducting monthly Unit
Environment Cell meeting by Corporate Environment Cell division for so many years.
As a result, all the Environmental norms are compiled as per the MoEF& CC.
1. Environmental Monitoring System
Air Quality Management
 Environmental External Monitoring system
Tamil Nadu Pollution Control Board (TNPCB) conducts periodical surveys to
monitor the Ambient Air Quality (AAQ) in the mining units. The results of the
TNPCB for Neyveli Mines and NABL accredited labs for outside projects are
well within the permissible limits.
 Internal Environmental Monitoring system
NLCIL installed 13 AAQ stations and 1 CAAQM Station in Neyveli, Tamilnadu
in approval with TNPCB for monitoring the Air Quality Parameters, out of 13
AAQ stations, 10 AAQ stations in the surrounding villages are monitored by
the renowned institute, IIT-Madras & 3 station are monitored by an in-
house lab (Centre for Applied Research & Development) accredited with NABL.
The results are within the permissible limits and submitted to Statutory officials
too. No Non Compliances have been reported so far.
EV Based Mobile Air Quality
AAQ Survey by SPCB
Monitoring by IIT-M & NLCIL
1. Environmental Monitoring System
Air Quality Management

 The dust generated in the mines are controlled by water spraying using sprinklers, Spray guns etc., on the
roads and planting of dense green belts roadsides and around the mines.

VEHICULAR WATER SPRAYING

HAUL ROAD – MANUAL WATER SPRAYING

AUTOMATIC REVOLVING TYPE RAIN GUN ARRANGEMENT

16-06-2021 8
CONVEYOR WATER SPRAYING
Automated Water Spray Arrangements
for Dust Suppression in Conveyors &
Lignite Stock Yard
1. Environmental Monitoring System
Air Quality Monitoring

 Details of Continuous Ambient Air Quality Monitoring Station (CAAQMS) in NLCIL:


a. Total CAAQMS installed: 11
b. Proposed CAAQMS for installation: 14
1. Environmental Monitoring System
Water Quality Management
 NLCIL has taken lot of efforts in water management by utilizing the waste water generated in the mines
and power stations for definite use. The storm water from the mines is treated and supplied to the
township for domestic usage and for the thermal power stations for industrial usage there by conserving
the precious ground water for advantageous use.

 The effluent generated from the mines in the areas of canteen, service yards are treated and sent to the
nearby area for agricultural activities.

 NLCIL has taken several measures towards rain water harvesting and recharge of ground water which
includes construction of check dams, percolation wells, observation wells, Piezometric wells and recharge
wells. These efforts have positive effect on the improvement of the ground water status in the nearby
areas.

 SPCB officials collect effluent and water samples from the mining units on a monthly basis for testing in
their Advanced Environmental Lab (AEL). The results of the effluent samples are well within the
permissible limits.
1. Environmental Monitoring System
Water Quality Management
Regulation of mine water through sluices for irrigation Sewage Treatment Plant in NLCIL
nearby Neyveli, NLCIL

12
Palm sapling plantations along the bunds of desilted
Desilting of lakes lakes

Walajah Tank after desilting Mangrove forest in East coast of Tuticorin


1. Environmental Monitoring System
Noise Management

Periodical noise level survey in all the industrial units by NLCIL & SPCB is being
conducted in all the industrial units of NLCIL.

The test results show that the noise levels are well with in the prescribed norms.

Also the personals working in high noise level areas are provided with personal
protective equipment such as ear plug.
1. Environmental Monitoring System
Land Management in Mines

 Reclamation of mined out area within the shortest duration using Integrated Farming system (IFS).

 The high overburden dumps were creating soil erosion and water pollution problems and NLCIL has
taken efforts to stabilize the overburden dumps (slope stabilization) by afforestation which has improved
the soil binding capacity and prevents soil erosion

 So far, a total area of about more than 2000 ha. of land is reclaimed for afforestation, agricultural,
horticulture crops in all the NLCIL mines.
Land Management in Mines

INTERNAL DUMPING PHYSICAL RECLAMATION

BIOLOGICAL RECLAMATION

High Tech Cultivation Paddy Cultivation in reclaimed Mines


ENVIRONMENT RESTORATION INSIDE MINES - NLCIL
ENVIRONMENT RESTORATION INSIDE MINES - NLCIL
ENVIRONMENT RESTORATION INSIDE MINES - NLCIL
Green Zone Development
Even before the advent of Environmental Laws & Regulations implemented in our country, NLCIL had given
prime importance to Environmental Protection through various eco-friendly activities including green belt
development
So far, NLCIL has raised about 23 lakhs trees in the region over a period of 6 decades in and around Neyveli
Township and production units.

Arial view of NLCIL – Neyveli Township


2. Statutory Reports
Environment Statement
Annual filing in the form of Annual Environment Statement consisting of all the
Environmental related data pertaining to the Industrial Units of NLCIL is being
submitted to TNPCB, CPCB and MoEF&CC every year and is being accepted and
there is no violation.

EC/FC Compliance Reports


The EC/FC compliance reports of the units are being submitted to MoEF&CC on
timely basis as stipulated in the EC/FC conditions.

Hazardous Waste, E-Waste & Battery Waste


Annual Filing of Hazardous waste, E-Waste & Battery Waste are being submitted
every year.
3. HQ Level EC/FC Compliance Monitoring System
In order to streamline the issues pertaining to Environment clearance (EC) and
Forest Clearance (FC) and to develop a uniform structure and efficient
environment Management system, NLCIL has formed the Environmental
Monitoring Committees at Area level and at HQ level.

The monthly meetings convened by the Area level Committees to monitor the
compliance of EC/FC conditions are reviewed by the HQ level Committee every 3
months. The report of the HQ level Committee is being submitted to the MoC.

The Compliance statuses of EC/FC conditions and the Environment Monitoring


data are regularly updated in MDMS portal.
4.0 Consent To Operate (CTO)
All the units of NLCIL are operating with valid Consents from every year from
SPCB’s. This is issued after complete inspection of the mining units and verifying the
compliances norms of MoEF&CC. So far, no violations or non-compliances have
been received.

5.0 ISO 14000 Certification


All the industrial units have obtained ISO certificates, including ISO 14000 obtained
for sound Environment Management activities carried out by the Units.
6.0 Environmental Awareness
Observation of Environmental Days:
NLCIL as a part of creating awareness of maintaining Good & Clean Environmental
practices among the employees of NLCIL, School students and general public,
observes important environmental Days such as World Environment Day, World Earth
Day, World Biodiversity day, World ozone day, World Soil Day, World Water Day,
World Forest Day etc., and ensures the involvement of all the Units through the Unit
Environmental Cell members.

Vriksharopan Abhiyan:
In view of the only single solution to the Global Climate Crisis, Govt of India had
launched Tree Plantation Campaign (Vriksharopan Abhiyan) 2021 on 19th August 2021.

During the Vriksharopan Abhiyan event NLCIL had carried out mass tree plantation &
distribution events at all its Mines & industrial Units. On a single day 2.4 lakhs tree
plantations was carried out.
Plantation Carried out in NLCIL Mines area on the eve of observing World Soil Day - 2021
NLCIL - Hi-tech Cultivation
The Vriksharopan Abhiyan 2021 event presided over by the Hon’ble Union Home
Minister and Hon’ble Minster for Coal & Parliamentary Affairs through video
conference.
 

 
 
 
Photographs of Mass tree plantation and Video conferencing of Hon’ble Ministers
NLCIL- Green Awards
As a gesture for acknowledging the extensive Sustainable Environmental practices in the
Environmental front and for complying with the EC/FC conditions, the following Environmental
Awards were bestowed upon NLC India Limited recently:
• EKDKN Environmental Platinum Award 2020 for Environmental Protection
• 21st Annual Greentech Environment & Sustainability award 2021- Winner for Outstanding
achievement under “Environment Protection Category”
• Grow Care India Environment Excellence platinum Award 2021 under Environment Preservation
Category

Ek Kaam Desh Ke Naam (EKDKN) Award – 2020


Concluding Remarks
As a Responsible public sector, NLCIL has implemented all the
Environmental norms prescribed by statutory Authorities and strictly
following it. Apart from, implementing Environmental norms, NLCIL
has developed a vast Green zone to maintain Environment sustainable
manner. Green Belt Development also reduces air pollution.
THANK YOU