Professional Documents
Culture Documents
of EPC Contracts
A Case Study of Delhi Metro
RAJESH AGARWAL
DRM FIROZPUR
1
आ नो भद्राः
क्रतवो यन्तु विश्वतः
Vedic mantra (Rig_Veda 1.89.1)
Time
Forms of Works Contract
EPC
Design,
Design, Build,
Item Build to Design
Build Finance,
Rate Design and
and Operate
Contrac Contrac Construct
Finance and
t t Contract
Contract Maintain
Contract
Increasing Degree of Risk Allocation to Contractor
BOT
5
INGREDIENTS OF SUCCESS
• Work culture
– Empowerment with accountability,
– Trust with transparency,
– Teamwork and No excuses
– Time-bound Commitments
• Emphasis on
– Integrity, prompt decision-making
– Quality, punctuality and targets
– No unproductive layers and babu-dom
Project Phases and its Control
Phase Primary Secondary Tertiary
Control Control Control
Planning Institutional System
Environment
Design Organizational Institutional System
Environment
Construction, Technical Core Organization Institutional
Services & al
Finishing
Testing and Organizational Institutional
Commissioning
Operation Separate Operating Organization
Record Sheet of DMRC
Section Length Target Date Commission
(km) as in 2002 Date
8
MC1A Corridor
Work started in May,2001
completion of works Dec,2004
9
Some Site Photographs
10
A view of Concrete Batching Plant
11
A view of Rebar Fabrication Yard
12
Formwork fixing in Progress on Tunnel Roof
13
Concreting in Progress on Tunnel Roof
14
Work in Progress from Steel Deck inside the Hoarding
15
Work in Progress at Vishwavidyalaya Station
16
Excavation under Steel Struts Supporting Sheet Piles
17
Inside the partially roof casted tunnel
18
Dedicated Footpath on both sides on the Shamnath Marg
19
6.00 Hrs in the morning, traffic stopped for blast
20
Rebar Fixing at floor slab at Vishwavidyalaya Station
21
An aerial view of road and work sites
22
Tunnel Taking Shape- Top Down Construction
23
Steel Deck Access to a Residence in Civil Lines area
24
Vibro Sheet Piler at work
25
Silent Sheet Piler at work
26
Tyre Washing System
27
A safety training in Class
28
Crack Meter on the wall of a building
29
Best Section Manager Award by MD to A-1 Section Manager
30
Safety Talk to Workers on Safe Working at Height in A-2 Section
31
PROJECT MANAGEMENT
• Land - acquisition and rehabilitation
• Fund – debt, equity, internal resources
• Prompt Decision - time value of Capital
– 1 Planning and Review
– 2 Procurement and Tendering
– 3 Measurement and Billing
– 4 Progress Reporting, Monitoring
– 5 Environment, Quality and Safety
– 6 Public information and Convenience
Why CONSULTANTS ?
• Own team may not be experienced and
equipped to handle complex
contracts/projects
41
Key Issues in EPC
Contract
42
Tender Document Constituents
Requirements for preparing Proposals
Proposals to conform to
– Employer’s Requirements-General, Functional, Design,
Construction, Manufacturing-Installation-Testing, Appendices
– Outline Design Specification- For each component of project
– Outline Construction Specification
GCC & SCC
Other submissions
– Tender Program
– Outline Quality Plan, Safety Plan and Environmental plan
– Rate Schedule for major items of work
43
MC1A Contract- Uncertain and Risky
Items in Provisional Sum
Description Amount
44
Activity Milestones Based Payment
Cost Center Based Planning:
– 01 Preliminaries and General Requirements
– 02 Design (A-Civil, B-E&M, C-Tunnel Vent)
– 03 Tunnel Construction (A to D Sections, E-Depot Access)
– 04 Station Construction (A to D Stations)
– 05 Electrical (A to D Stations)
– 06 Water, Plumbing, Drainage (A to D Stations)
– 07 Fire Detection and Suppression (A to D Stations)
– 08 ECS (A to D Stations)
– 09 Tunnel Vent (A to D Stations)
– 10 Testing & Commissioning (A to D Stations)
– 11 Product Support (A to D Stations)
45
Milestones Submission by Tenderers
Cost Center Outline describing activities included in it and
typical activities and their ID numbers provided in tender
Tenderer to prepare its own Milestone Schedule matching its
Program for entire project quoting $ and Re components of
payment demanded together with Week of completion
Typical Milestone Numbers and what it implies
– 3B.20B implies Sheet Plie 50% complete by plan length at Ch
11+002 m to 11+627 m of Tunnel from V V Stn. to OS Stn.
– 4D.10A implies V V Station Base Slab 50% complete
Monthly cash flow to be submitted by tenderer and that should
generally match with the physical progress of work proposed
e.g.‘S’ Curves for Concrete
Highest tenderer based on cumulative present value of
milestone payment schedule of the tenderer
46
Sub-Contracting Provisions
Tenderer prequalified with Design Consultant and
T&C of proposed contract with it to be submitted
with tender
Sub-contracting for works other than design limited
to 50% of LS Price
Each sub-contract exceeding Rs. 1 million to be prior
approved
Each sub-contract for provisional sum works,
irrespective of value, to be prior approved
47
Interfacing with Other
Contracts
48
Metro Corridor System Wide
Contracts
MC1A Civil Structures VW Station to ISBT (4Km)
MC1B Civil Structures ISBT to Central Secretariat (6.5 KM)
SYS 01 Signalling and Communication
SYS 02 Traction & Power Supply
SYS 03 Track work
SYS 04 Automatic Fare Collection
SYS 05 Lifts and Escalators
MC2 Khyber Pass Depot
RS1 Rolling Stock
49
Key Dates for MC1A Connecting
System Wide Contracts
Key Description of Key Date
Date
KD1 Preliminary Design 14 Weeks
KD5 Definitive Design 39 Weeks
KD8A Hand Equipment Rooms to SYS01 & SYS02-113 Weeks
KD8B Hand Concourse to SYS04 –155 Weeks, station complete
KD8C Handover Basic Structure to SYS 05-120 Week
KD9 Hand Track way to SYS 03 – 120 Weeks, tunnel complete
KD10 Power on to Station/Tunnels – 186 Weeks
KD11 Handover for Integrated Testing-193 Weeks
KD12 Completion of Works – 218 Weeks
50
Key Dates vs Milestones
Both have a date specified in number of weeks from NTP
for each
Key Dates are constraints for Project Network but
Milestones are not
Non adherence to a Key Date invites penalty while that
of a Milestone only delays the respective payment
Achievement of subsequent Key Date gets refund of
penalty on earlier Key Dates while achievement of any
milestone is independent of any other milestone
Key Dates were renegotiated for early commissioning
while Milestones were allowed to be split for improving
cash flow to contractor
51
Use of S- Curve for Project Scheduling
Payment S-Curve
Concrete Consumption
10000
25000 300000
Millions
Monthly Concrete Qty
9000
Actual Monthly Qty
Cumulative Concrete Qty 250000 8000
20000
Cumulative Concrete Qty
7000
200000 Cumm.
INR Equi.
15000 6000
150000 5000
10000 4000
100000
3000
5000
2000
50000
1000
0 0
0
Months
Time Period
52
Monitoring through Cost Center
and Milestones
Cost Center bifurcation helped in distinct responsibility and
monitoring of works of various disciplines in one composite contract
Every conceivable requirement in contract linked to at least one
milestone with coding
– 4A.10A [Vishwa Vidyalaya Station (4A), Station Box external walls (10)
50% complete (A)]
Even Contractor’s monthly supervision (1.12 to 1.61), monthly site
running (1.79 to 1.128), Quarterly Audit reports on
Quality/Safety/Environment (1.62 to 1.78) had one milestone each
Every submission is linked to a milestone
The coding of milestone and the organizational structure ensures
that the responsible person for each milestone is known
53
Milestone is the Focal Point
Network Programme is based on Milestone
Certification of completion of Milestone by GC
enable payment
GC asks Production wing why certain Milestones
that should have been completed in the month
were not completed
Accounts wing computes the achievable
milestones to get required cash flow and chases
Production for completing
54
Milestone Focal Point…
GC asks Quality, Safety and Environment wings
for closure of NCNs and blocks payment of
respective milestones
Accounts chases theses wings for getting
blocked Milestones cleared
Quality, Safety and Environment wings chases
Production for compliances so that they close
the NCNs to release the milestone payment
55
Assuring Cash Flow to Contractor
56
57
Project Scheduling
58
Scheduling Strategy of Contractor
Cumulative Payments ‘S’ curve matched with the
Earthwork and Concrete ‘S’ curve derived from
Schedule
Estimation of cost, payment flows and Programme
logic followed each other
Some key resources centralized for reducing
uncertainties- Lab, Batching Plant, Rebar Fabrication
yard, Plant Maintenance, stone crushing plant
Objective: Latest Start and Highest economy
Proposed: 3 phase construction, for reusing
temporary structural steel
59
Standardization of
Processes
60
Procedures and Method Statements
Deputy Production Manager responsible
for preparing from Contractor side
Resident Engineer from GC responsible for
reviewing and giving comments
Work started only after relevant process
approved through issue of NOC from GC
32 MPs, 56 MSs & ITPs and more than 30
WPs were developed in the contract
61
Request for Qualification
(RFQ)
62
Why need Pre Qualification?
Preparation of High Value EPC Bid: a time consuming
and costly affair
Good parties do not invest in bidding unless they
have a 20% chance of winning
Pre-qualified bidders provide a structured and
meaningful feedback on the bid process and
documents
They become stakeholders in the faster completion
of the bid process
Necessary for bigger and complex projects
63
Value Addition During
Tendering
64
Alternative Proposals/ Negotiation
Tenderers allowed to offer alternative technical offers with price
discounts
Based on pre-bid queries and meetings eight amendments issued
GC teams of experts in each field evaluated proposals
211 clarification questions covering every aspect of the proposal
raised- many repeated to get clear confirmation
Answers/ confirmations sought in unambiguous terms together with
revised proposals in many cases
Final negotiated bids including technical proposal invited
KSHI JV came lowest in this bid process
65
Value Addition in Tender Process
Interactions with tenderers lead to understanding of
break up of offer and risks that were priced
A reduction of more than Rs. 60 crore was achieved in
LS Price
– By including Utility Diversion in Provisional Sum and increasing it
by Rs.15 crore
A reduction of more than Rs. 200 crore was achieved in
LS price due to following changes
– Min soil cover over tunnel/station box roof relaxed from 2m to
1m at localized places like subways
– Road allowed to be raised and regraded at localized places to
meet min soil cover without raising tunnel alignment
66
Monitoring System
67
Building Site Organization- MC1A
Contract
4 Sections, A to D (corresponding to cost center names)
comprising one km of tunnel including one station
GC Organization parallel to Contractor’s
– Section Manager (Contractor) vs Section Engineer (GC)
Quality, Safety and Environment Managers reporting
directly to the Project Leader
– Respective GC Experts reported to PD whereas SE Spl was the
counterpart at site reporting to RE
Traffic and Utility Coordinator appointed by the contractor
for coordination with sub contractors and authorities
68
Organizational
Structure of MC1A
MD (DMRC) CPM-Chief Proj
Manager; PM-Proj
Manager; CRE-
Dir Proj Proj Dir (GC) Chief Resident
Engineer; RE-
Resident Engineer;
CPM (MC) PM (MC)
SE-Section
Engineer; EE-
Dy. CE North CRE (MC1A) PL (MC1A)
Executive
MC Engineer; PL-Proj
Leader; PM-
RE PM Production
Manager; SM-
Section Manager;
E. E.-1 SE Section A SM Section A RMs-Resource
Managers
E. E.-2 SE Section B SM Section B
SE Section D SM Section D
Line of Command
SE Spl RMs 1,2,3,4
69
Schedule of Meetings
• Chaired By DMRC
– Quarterly Community Interaction Meeting
– Monthly progress meeting by Director
– Field meeting by MD after inspection
• Chaired by GC
– Weekly Progress Meeting
– Weekly Design Coordination meeting
70
Schedule of Meetings…contd.
• Chaired by Contractor
– Monthly Safety Meeting
– Site coordination meeting by each Section Manager
– Interface Coordination meeting with other contractors
How it Paid: Complex issues got resolved fast to
every one’s satisfaction, Accountability for
commitments
71