You are on page 1of 71

FUNDAMENTALS

of EPC Contracts
A Case Study of Delhi Metro

RAJESH AGARWAL
DRM FIROZPUR

1
आ नो भद्राः
क्रतवो यन्तु विश्वतः
Vedic mantra (Rig_Veda 1.89.1) 

Let noble thoughts come to me


from all directions
FUND AND PROCUREMENT

Nature Process Condition Accountability


Personal Self determine NIL Your self

Private Not defined Range owner

Pvt Ltd Defined with Lender’s Audit (diversion of


Company Flexibility condition ? Fund?)

Public Ltd, Defined. Open, Pressures? Vigilance, audit


Govt fund competitive &
transparent

Multilateral Rigidly defined Many? + of Funding


Agency?
Activities in Life Cycle of Project
n ing
s sio
Activities m i
m
Co
h ing
in is
F
i ces
rv
Se
n
c tio
tru
o ns
C
ns
ig
D es
n ing
n
Pla

Time
Forms of Works Contract
EPC

Design,
Design, Build,
Item Build to Design
Build Finance,
Rate Design and
and Operate
Contrac Contrac Construct
Finance and
t t Contract
Contract Maintain
Contract
Increasing Degree of Risk Allocation to Contractor
BOT
5
INGREDIENTS OF SUCCESS
• Work culture
– Empowerment with accountability,
– Trust with transparency,
– Teamwork and No excuses
– Time-bound Commitments

• Emphasis on
– Integrity, prompt decision-making
– Quality, punctuality and targets
– No unproductive layers and babu-dom
Project Phases and its Control
Phase Primary Secondary Tertiary
Control Control Control
Planning Institutional System
Environment
Design Organizational Institutional System
Environment
Construction, Technical Core Organization Institutional
Services & al
Finishing
Testing and Organizational Institutional
Commissioning
Operation Separate Operating Organization
Record Sheet of DMRC
Section Length Target Date Commission
(km) as in 2002 Date

Shahdara-Tis Hazari 8.0 Dec 2002 Dec 2002


Tis Hazari-Tri Nagar 4.7 Sept 2003 Sep 2003
Tri Nagar-Rithala 8.8 Mar 2004 Mar 2004
Vishwa Vidyalaya-Kashmere Gate* 4.0 July 2005 Dec 2004
Kashmere Gate-Central Secretariate 5.5 Sep 2005 Sep 2005

Barakhamba Road-Kirti Nagar 6.0 June 2005 Dec 2005


Kirti Nagar-Dwarka 16.4 Sep 2005 Dec 2005

*The Case study is based specifically on this MC1A Contract

8
MC1A Corridor
 Work started in May,2001
 completion of works Dec,2004

 2,31,000 Cum of structural concrete


 12,00,000 Cum of excavation

9
Some Site Photographs

10
A view of Concrete Batching Plant

11
A view of Rebar Fabrication Yard

12
Formwork fixing in Progress on Tunnel Roof

13
Concreting in Progress on Tunnel Roof

14
Work in Progress from Steel Deck inside the Hoarding

15
Work in Progress at Vishwavidyalaya Station

16
Excavation under Steel Struts Supporting Sheet Piles

17
Inside the partially roof casted tunnel

18
Dedicated Footpath on both sides on the Shamnath Marg

19
6.00 Hrs in the morning, traffic stopped for blast

20
Rebar Fixing at floor slab at Vishwavidyalaya Station

21
An aerial view of road and work sites

22
Tunnel Taking Shape- Top Down Construction

23
Steel Deck Access to a Residence in Civil Lines area

24
Vibro Sheet Piler at work

25
Silent Sheet Piler at work

26
Tyre Washing System

27
A safety training in Class

28
Crack Meter on the wall of a building

29
Best Section Manager Award by MD to A-1 Section Manager

30
Safety Talk to Workers on Safe Working at Height in A-2 Section

31
PROJECT MANAGEMENT
• Land - acquisition and rehabilitation
• Fund – debt, equity, internal resources
• Prompt Decision - time value of Capital
– 1 Planning and Review
– 2 Procurement and Tendering
– 3 Measurement and Billing
– 4 Progress Reporting, Monitoring
– 5 Environment, Quality and Safety
– 6 Public information and Convenience
Why CONSULTANTS ?
• Own team may not be experienced and
equipped to handle complex
contracts/projects

• To keep organization lean


• Professional Management
• Bridging the Knowledge Gaps
• Better Relationship with Contractor
• Managing New Contract types
• Requirement of Funding Agency
How to Balance the role?
Client • Payment, Variations, and other
contract management issues
• Planning, procurement and tendering
• Overall responsibility
Contractor • Contractor’s own Safety and Quality
monitoring
• Monthly Progress Reporting
• Measurement and Billing
PMC • Safety and Quality monitoring
• Parallel Progress Reporting
• Checking of measurement and bills
• Assist client in planning, procurement
and tendering
PLANNING AND REVIEW
• OVERALL TARGET OF PROJECT
• CONTRACT PACKAGING (LEAST NUMBER)
• TIME VALUE FOR EACH DAY OF DELAY
• REVERSE CLOCK FOR COMMISSIONING
• FIXING INTERFACE REQUIREMENT
• 4 MONTH AND 4 WEEK ROLLING PLANS
• RECORD DECISIONS, NOT THE VIEWS
Reviewing DPR by DMRC
 Corridors revised to align them to the busiest roads
 Contract Packaging changed for better quality and
control e.g. Metro Corridor:
DPR Contract Package
• 10 Civil Structure Contracts. • Two Contract MC1A & 1B.
• Construct Only. • Design & Construct -EPC
• Tender Documents are • The Packaging is done
prepared on the basis of based on proposed method
traditional multi-contract of construction i.e.(cut &
implementation Strategy Cover vs Tunnel Boring)
• Several E&M Contracts • Civil Engg. Electrical &
Mechanical, Lighting(AC &
• Several Ventilation/AC
Ventilation) all combined.
Contracts
PROCUREMENT & TENDERING
 SINGLE STAGE OR TWO STAGE PROCESS Prequalification
Basically Consist Of
• Technical
– Experience of similar work
– Defining similar work
– Evaluation criterion
• Financial
– Bid Capacity (turnover – order book)
– Cash flow (liquidity, net worth etc)
 OUTCOME
All meeting Criterion or top few qualifying for next
stage of bidding
Single Vs Two Stage Process
SN SINGLE STAGE TWO PACKET TWO STAGE TWO PACKET
1 Separate technical bid and Technical bid in Ist stage. Financial bid from
financial bid but submitted in shortlisted bidders in IInd stage.
single envelope.
2 Technical bid opened first. Technical bids opened and list of qualified
Financial bid of qualified bidder bidders published. Reasonable time given to
opened at short notice. qualified bidder for submission of financial
bid
3 Not aware of competitors, No Qualified bidder : Publicly known, Possibility
Possibility Of Cartelization. of cartelization cannot be eliminated.
4 Bidders do their own due There is an influence of knowledge of
diligence and generally try to be industry standards being followed by their
competitive competitors in their due diligence.
5 When availability of projects are In limited competitive environment,
less, bidders may tend to under possibility of under quote is less.
quote.
Single Vs Two Stage Process
SN SINGLE STAGE TWO PACKET TWO STAGE TWO PACKET
6 Quote will be reasonable even Being a limited competitive
if more number of projects are environment, bidder hands may be
available in the market. full and may lead to higher quotes.
7 Representation/request can be Representation/request will require
promptly disposed off. considered decisions and may take
more time.
8 More suitable for small to More suitable for bigger size (>1000
medium size projects with Cr) and for complex projects which
lesser complexity. require bidders association in
finalizing the tender documents.
9 Possibility of Shortlisted bidder Shortlisted Bidders at times do not
without the Financial bid does participate at Financial bid stage.
not exist.
Founding Principles of Delhi Metro
 No hoardings reads
– “Inconvenience is regretted”,
– “Work in Progress”,
– “Please bear with us”
 Above indicate poor planning & callous approach.
Hoardings at work sites on street should
– be a welcome sign
– Public expect better roads, smooth traffic & safety
– be a brand building for Client, Contractor and
Consultant
General Consultant to DMRC
 Acted as Employer’s Representative on specific corridors
and contracts
 Did for Employer
– review of DPR
– tender management
– monitoring of execution
– NOC to Contractor’s drawings
– Testing and Commissioning different systems
 DMRC kept payment, changes in contract, approval to
key drawings only

41
Key Issues in EPC
Contract

42
Tender Document Constituents
 Requirements for preparing Proposals
 Proposals to conform to
– Employer’s Requirements-General, Functional, Design,
Construction, Manufacturing-Installation-Testing, Appendices
– Outline Design Specification- For each component of project
– Outline Construction Specification
 GCC & SCC
 Other submissions
– Tender Program
– Outline Quality Plan, Safety Plan and Environmental plan
– Rate Schedule for major items of work

43
MC1A Contract- Uncertain and Risky
Items in Provisional Sum
Description Amount

a. Additional Testings Rs. 50 Lacs


b. Furniture, Cabinets & Shelves Rs. 50 Lacs
c. Artwork & Landscaping Rs. 1.5 lacs
d. Architectural finishes including Rs. 15.5 (crores)
false ceiling
e. Diversion & Support of utilities
Rs.15 crores

44
Activity Milestones Based Payment
 Cost Center Based Planning:
– 01 Preliminaries and General Requirements
– 02 Design (A-Civil, B-E&M, C-Tunnel Vent)
– 03 Tunnel Construction (A to D Sections, E-Depot Access)
– 04 Station Construction (A to D Stations)
– 05 Electrical (A to D Stations)
– 06 Water, Plumbing, Drainage (A to D Stations)
– 07 Fire Detection and Suppression (A to D Stations)
– 08 ECS (A to D Stations)
– 09 Tunnel Vent (A to D Stations)
– 10 Testing & Commissioning (A to D Stations)
– 11 Product Support (A to D Stations)

45
Milestones Submission by Tenderers
 Cost Center Outline describing activities included in it and
typical activities and their ID numbers provided in tender
 Tenderer to prepare its own Milestone Schedule matching its
Program for entire project quoting $ and Re components of
payment demanded together with Week of completion
 Typical Milestone Numbers and what it implies
– 3B.20B implies Sheet Plie 50% complete by plan length at Ch
11+002 m to 11+627 m of Tunnel from V V Stn. to OS Stn.
– 4D.10A implies V V Station Base Slab 50% complete
 Monthly cash flow to be submitted by tenderer and that should
generally match with the physical progress of work proposed
e.g.‘S’ Curves for Concrete
 Highest tenderer based on cumulative present value of
milestone payment schedule of the tenderer

46
Sub-Contracting Provisions
 Tenderer prequalified with Design Consultant and
T&C of proposed contract with it to be submitted
with tender
 Sub-contracting for works other than design limited
to 50% of LS Price
 Each sub-contract exceeding Rs. 1 million to be prior
approved
 Each sub-contract for provisional sum works,
irrespective of value, to be prior approved

47
Interfacing with Other
Contracts

48
Metro Corridor System Wide
Contracts
 MC1A Civil Structures VW Station to ISBT (4Km)
 MC1B Civil Structures ISBT to Central Secretariat (6.5 KM)
 SYS 01 Signalling and Communication
 SYS 02 Traction & Power Supply
 SYS 03 Track work
 SYS 04 Automatic Fare Collection
 SYS 05 Lifts and Escalators
 MC2 Khyber Pass Depot
 RS1 Rolling Stock

49
Key Dates for MC1A Connecting
System Wide Contracts
Key Description of Key Date
Date
KD1 Preliminary Design 14 Weeks
KD5 Definitive Design 39 Weeks
KD8A Hand Equipment Rooms to SYS01 & SYS02-113 Weeks
KD8B Hand Concourse to SYS04 –155 Weeks, station complete
KD8C Handover Basic Structure to SYS 05-120 Week
KD9 Hand Track way to SYS 03 – 120 Weeks, tunnel complete
KD10 Power on to Station/Tunnels – 186 Weeks
KD11 Handover for Integrated Testing-193 Weeks
KD12 Completion of Works – 218 Weeks

50
Key Dates vs Milestones
 Both have a date specified in number of weeks from NTP
for each
 Key Dates are constraints for Project Network but
Milestones are not
 Non adherence to a Key Date invites penalty while that
of a Milestone only delays the respective payment
 Achievement of subsequent Key Date gets refund of
penalty on earlier Key Dates while achievement of any
milestone is independent of any other milestone
 Key Dates were renegotiated for early commissioning
while Milestones were allowed to be split for improving
cash flow to contractor
51
Use of S- Curve for Project Scheduling
Payment S-Curve
Concrete Consumption

10000
25000 300000

Millions
Monthly Concrete Qty
9000
Actual Monthly Qty
Cumulative Concrete Qty 250000 8000
20000
Cumulative Concrete Qty
7000
200000 Cumm.
INR Equi.
15000 6000

Cumulative INR. Equivalent


Concrete Qty

150000 5000

10000 4000

100000
3000

5000
2000
50000

1000

0 0
0

Months
Time Period

S-Curve for Concrete Pouring S- Curve for Milestone


Payment

52
Monitoring through Cost Center
and Milestones
 Cost Center bifurcation helped in distinct responsibility and
monitoring of works of various disciplines in one composite contract
 Every conceivable requirement in contract linked to at least one
milestone with coding
– 4A.10A [Vishwa Vidyalaya Station (4A), Station Box external walls (10)
50% complete (A)]
 Even Contractor’s monthly supervision (1.12 to 1.61), monthly site
running (1.79 to 1.128), Quarterly Audit reports on
Quality/Safety/Environment (1.62 to 1.78) had one milestone each
 Every submission is linked to a milestone
 The coding of milestone and the organizational structure ensures
that the responsible person for each milestone is known

53
Milestone is the Focal Point
 Network Programme is based on Milestone
 Certification of completion of Milestone by GC
enable payment
 GC asks Production wing why certain Milestones
that should have been completed in the month
were not completed
 Accounts wing computes the achievable
milestones to get required cash flow and chases
Production for completing

54
Milestone Focal Point…
 GC asks Quality, Safety and Environment wings
for closure of NCNs and blocks payment of
respective milestones
 Accounts chases theses wings for getting
blocked Milestones cleared
 Quality, Safety and Environment wings chases
Production for compliances so that they close
the NCNs to release the milestone payment

55
Assuring Cash Flow to Contractor

 Weekly cash disbursal monitored by MD


 80% payment within 3 days of submission of contractor
prepared bills
 Recovery of Advance suspended for certain period
 Advances against ‘under consideration claims’
 Milestones allowed to be split for faster cash flow
Motto: No Contractor should suffer for want of cash flow

56
57
Project Scheduling

58
Scheduling Strategy of Contractor
 Cumulative Payments ‘S’ curve matched with the
Earthwork and Concrete ‘S’ curve derived from
Schedule
 Estimation of cost, payment flows and Programme
logic followed each other
 Some key resources centralized for reducing
uncertainties- Lab, Batching Plant, Rebar Fabrication
yard, Plant Maintenance, stone crushing plant
 Objective: Latest Start and Highest economy
 Proposed: 3 phase construction, for reusing
temporary structural steel

59
Standardization of
Processes

60
Procedures and Method Statements
 Deputy Production Manager responsible
for preparing from Contractor side
 Resident Engineer from GC responsible for
reviewing and giving comments
 Work started only after relevant process
approved through issue of NOC from GC
 32 MPs, 56 MSs & ITPs and more than 30
WPs were developed in the contract

61
Request for Qualification
(RFQ)

62
Why need Pre Qualification?
 Preparation of High Value EPC Bid: a time consuming
and costly affair
 Good parties do not invest in bidding unless they
have a 20% chance of winning
 Pre-qualified bidders provide a structured and
meaningful feedback on the bid process and
documents
 They become stakeholders in the faster completion
of the bid process
 Necessary for bigger and complex projects

63
Value Addition During
Tendering

64
Alternative Proposals/ Negotiation
 Tenderers allowed to offer alternative technical offers with price
discounts
 Based on pre-bid queries and meetings eight amendments issued
 GC teams of experts in each field evaluated proposals
 211 clarification questions covering every aspect of the proposal
raised- many repeated to get clear confirmation
 Answers/ confirmations sought in unambiguous terms together with
revised proposals in many cases
 Final negotiated bids including technical proposal invited
 KSHI JV came lowest in this bid process

65
Value Addition in Tender Process
 Interactions with tenderers lead to understanding of
break up of offer and risks that were priced
 A reduction of more than Rs. 60 crore was achieved in
LS Price
– By including Utility Diversion in Provisional Sum and increasing it
by Rs.15 crore
 A reduction of more than Rs. 200 crore was achieved in
LS price due to following changes
– Min soil cover over tunnel/station box roof relaxed from 2m to
1m at localized places like subways
– Road allowed to be raised and regraded at localized places to
meet min soil cover without raising tunnel alignment

66
Monitoring System

67
Building Site Organization- MC1A
Contract
 4 Sections, A to D (corresponding to cost center names)
comprising one km of tunnel including one station
 GC Organization parallel to Contractor’s
– Section Manager (Contractor) vs Section Engineer (GC)
 Quality, Safety and Environment Managers reporting
directly to the Project Leader
– Respective GC Experts reported to PD whereas SE Spl was the
counterpart at site reporting to RE
 Traffic and Utility Coordinator appointed by the contractor
for coordination with sub contractors and authorities

68
Organizational
Structure of MC1A
MD (DMRC) CPM-Chief Proj
Manager; PM-Proj
Manager; CRE-
Dir Proj Proj Dir (GC) Chief Resident
Engineer; RE-
Resident Engineer;
CPM (MC) PM (MC)
SE-Section
Engineer; EE-
Dy. CE North CRE (MC1A) PL (MC1A)
Executive
MC Engineer; PL-Proj
Leader; PM-
RE PM Production
Manager; SM-
Section Manager;
E. E.-1 SE Section A SM Section A RMs-Resource
Managers
E. E.-2 SE Section B SM Section B

SE Section C SM Section C Line of communication

SE Section D SM Section D
Line of Command
SE Spl RMs 1,2,3,4

69
Schedule of Meetings
• Chaired By DMRC
– Quarterly Community Interaction Meeting
– Monthly progress meeting by Director
– Field meeting by MD after inspection
• Chaired by GC
– Weekly Progress Meeting
– Weekly Design Coordination meeting

70
Schedule of Meetings…contd.
• Chaired by Contractor
– Monthly Safety Meeting
– Site coordination meeting by each Section Manager
– Interface Coordination meeting with other contractors
How it Paid: Complex issues got resolved fast to
every one’s satisfaction, Accountability for
commitments

71

You might also like