PROJECT OVERVIEW % COMPLETE

Status for all top-level tasks. To see the status for subtasks, click on the chart
and update the outline level in the Field List.
-
% COMPLETE

26%

Total Budget : 6,847,541.00 Php


Project DP : 1,370,000.00 Php
Remaining Billing : 4,248,541.00 Php
Total collection to date : 1,229,000.00 Php Remarks:
• Phase 2 of the project was completed ahead of time.
Schedule Performance Index (SPI): 1.08 • Next milestone is the completion of 2nd floor slab that is due on January 20,
2022.

SPI > 1 Project is ahead of schedule SPI = 1 Project still on schedule SPI = 1 Project is delay
Camera view A
PROGRESS PHOTOS AS
OF 1/2/2022

Camera view A

Camera view B

Camera view B
Camera view C
PROGRESS PHOTOS AS
OF 1/2/2022

Camera view E

Camera view D
Camera view A
PROGRESS PHOTOS AS
OF 12/18/2021

Camera view A

Camera view B

Camera view B
Camera view C
PROGRESS PHOTOS AS
OF 12/18/2021

Camera view C

Camera view D

Camera view D
Camera view A
PROGRESS PHOTOS AS
OF 12/04/2021

Camera view A

Camera view B

Camera view B
Camera view C
PROGRESS PHOTOS AS
OF 12/04/2021

Camera view C

Camera view D

Camera view D
Camera view A
PROGRESS PHOTOS AS
OF 11/28/2021

Camera view A

Camera view B

Camera view B
Camera view C
PROGRESS PHOTOS AS
OF 11/28/2021

Camera view C

Camera view D

Camera view D