PROJECT UPDATE 27

LAS LUCAS
CONSTRUCTION AND DEV’T CORP.

Project Construction of Bunkering Pier at Mandaue


Terminal
Location C. Ouano St., Brgy. Looc, Mandaue City, Cebu.

Contractor Oceaneering Contractor (Phil), Inc.

Contract Amount Php 28,249,743.52

Original date of start November 28, 2009

Target Completion April 16, 2010 (150 Calendar Days)

Revised target May 31, 2010


completion (OCPI to submit the revised project completion)

% Actual Accomplishment= 84.85% Delay= -15.55%


% Target Accomplishment= 100.00%
Major Causes of Delay:
Project should have been completed last April 16, 2010. Bunkering Pier Construction
 Delayed driving of steel and concrete piles, activities
after pile driving are subsequently delayed as well.
Vessel’s arrival and departure contributed delays.
Status as of Catch up plan:
July 27, 2010  Maximizing the window given to OCPI during pier
opening and closely monitoring the tidal schedule.
Technical issue:
 OCPI’s original contract expires last May 31, 2010.

ACTIVITIES:
 Completed installation of rebar’s, forms and bolts for the
new breasting dolphin.
 Hauling of aggregates prior to concrete pouring.
 Completed concrete pouring of pile cap at the new
breasting dolphin.
 Dismantling of formworks at bunkering pier.
 Rehabilitation of causeway approach.
 Installation of bolts for the new rubber fenders.

Breasting Dolphin Construction


Prepared by:
PROGRESS PHOTOS JOSEPHE RIGGETS M. RIEGO
Project Engineer, LLCDC
Preparation for actual pouring of concrete for the
new breasting dolphin:

Tremie that was used during concreting

Completed concrete pouring of


cast-in-place slab

Installation of mooring bollard


Installed mooring bollard prior to
actual concreting

Four (4) unit of bagger mixer was used


Aggregates for concrete pouring at
simultaneously during concreting
crane barge
Prepared by:
PROGRESS PHOTOS JOSEPHE RIGGETS M. RIEGO
Project Engineer, LLCDC
Actual start of concrete pouring for the new breasting
dolphin:

Safety orientation and briefing


regarding the actual concreting Preparation for actual pouring
activities

Bagger mixer and


concrete bucket

Concrete bucket,
tremie and vibrator

Actual mixing of concrete

Actual pouring of concrete


Prepared by:
PROGRESS PHOTOS JOSEPHE RIGGETS M. RIEGO
Project Engineer, LLCDC
Continuous concrete pouring for the new breasting
dolphin:

A one (1) cubic meter concrete


Continuous concrete mixing
bucket was used during the actual
pouring

Concrete vibrator and


tremie pipe extended to the
bottom portion of pile cap

Vibrator was used after the


concrete has been poured to the
bottom portion of pile cap
Prepared by:
PROGRESS PHOTOS JOSEPHE RIGGETS M. RIEGO
Project Engineer, LLCDC
Continuous concrete pouring for the new breasting
dolphin:

Vibrator was used after the


concrete has been poured.

Continuous concrete mixing

Concrete mix from the bucket to


the pile cap
Prepared by:
PROGRESS PHOTOS JOSEPHE RIGGETS M. RIEGO
Project Engineer, LLCDC
Continuous concrete pouring for the new breasting
dolphin:

Almost completed
concrete pouring

Finishing of the poured concrete


for the new breasting dolphin
Prepared by:
PROGRESS PHOTOS JOSEPHE RIGGETS M. RIEGO
Project Engineer, LLCDC
Almost completed construction of bunkering pier and
causeway rehabilitation:

After dismantling of formworks and


Bunkering pier panoramic view completed installation of pipe supports at
cast-in-place beams

Location of pipe supports

Rehabilitation of causeway approach prior for


the installation of the remaining pipe supports