Stress Deliverables

Stress critical line list preparation


Inlet, outlet and vent due to PSV can be
considered critical. Drain can be neglected

Vent lines are inter connected and taken to the


flare header which is routed to the flare knock
out drum and fired in the flare tower

All drains are connected and taken to the blow


down drum. 4” is not considered

Pig launcher receiver??

The flare header is sloped and the flare lines


are connected using 45 degree to push the
fluid towards the knock out drum
• Non critical lines Category 1 • Flexibility Analysis Category 2
Checked visually using isometrics and 3D model • B31.3 (319.4)
* Critical line complete analysis of pipes is required, • Dy/(L-U)^2
detailed study of support types and loads. Stress
B31.3
report is to be provided.
Table C-1M Thermal expansion coeff
Table C-6 Young’s modulus
Allowable stress Table A1-M