N e t w o r k D e v e l o p m e n t - R o a d Wi d e n i n g - S e c o n d a r y R o a d s -

Catarman-Calbayog Rd - K0764 + 205 - K0764 + 620


Lope de Vega, Northern Samar

CID No.

22IH0004
Project Description:

Road widening with a total length of


0.83km with a width of 3.35m and
thickness of 280mm
Project Amount:

Php. 12,378,020.18
Notice to Proceed:

February 21, 2022


Date Project Started:

February 25, 2022


Contractor:

EFC Development Corporation


Project Accomplishment Status as of today:

As planned Actual

18.51%
Organizational Chart
FEBRUARY PROJECT ACCOMLISHMENT
Project Billboard/Signboard
Occupational Safety and Health
Program
Traffic Management
Mobilization/Demobilization
MARCH PROJECT ACCOMLISHMENT
Grouted Riprap, Class A
March 2, 2022 (Left side 41m)
Structure Excavation
March 2, 2022 (51m)
Surplus Excavation
March 2, 2022 (100m)
Grouted Riprap, Class A
March 9, 2022 (Left side 85m,
Right side 40m)
Surplus Excavation
March 9, 2022(160m)
Embankment from Borrow,
Common soil
Subgrade Preparation
March 17, 2022
Field Density Test
Quality Assurance Section
March 18, 2022
Field Density Test
Quality Assurance Section
March 18, 2022
PCCP 0.28m thk.
March 19, 2022 (57.5m)
PCCP 0.28m thk.
March 19, 2022 (57.5m)
PCCP 0.28m thk.
March 21, 2022 (160m)
PCCP 0.28m thk.
March 21, 2022 (160m)
Grouted Riprap
March 22-26, 2022 (147m)
Subgrade Preparation
March 26, 2022 (120m)
Cutting of PCCP
March 26, 2022
APRIL PROJECT ACCOMLISHMENT
PCCP 0.28m thk. (336m)
Right side=276m, Left side=60m
April 5, 2022
Grouted Riprap (175m)
Right side=40m, Left side=135m
April 5, 2022