Professional Documents
Culture Documents
Gerhard Galneder
born: 1949
• Studies at the Technical University of Munich:
1975 graduate civil engineering
1978 graduate industrial engineering
• Professional live:
1978 – 2006 H. Brochier Ltd., pipeline construction, civil engineering
– 1988 Site manager and branch manager
– 2006 Chief of controlling and production planning (dept.)
1.Tendering documents:
• Terms of contract, (“FIDIC”)
• Design, (Bill of quantity)
Employer
2. Binding offer
Consultant
(Quantity surveyor)
3. Contract, Order Contractor
Cost Management
0.20 m
Slope 45 o
2.00 m
0.20 m
Binding layer 10 cm
Quatity takeoff:
L B H Quantity Unit
Total
Cost Management:
Introduction
Planning Control
- Estimation - Reporting
- Calculation - Actual values
- Offer - Accounting and
Information Billing
- Variances
- Ratios
- Efficiencies
500,00
degressive)
€ Total costs 400,00
350,00
500.000
300,00
450.000 250,00
400.000 200,00
%-Profit
350.000 150,00
%- OH 0 200 400
300.000
Degressive/Progressive costs
250.000
200.000
150.000
100.000
Proportional costs
50.000
Fix costs
0
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Meter
Meter 0 200 400 600 800 1000 1200 1400 1600 1800 2000
Prop. costs 0 38.000 72.000 102.000 128.000 150.000 168.000 182.000 192.000 198.000 200.000
Degr. Costs 0 14.000 28.000 42.000 56.000 70.000 84.000 98.000 112.000 126.000 140.000
Fix costs 30.000 30.000 30.000 30.000 30.000 30.000 30.000 30.000 30.000 30.000 30.000
Direct costs 30.000 82.000 130.000 174.000 214.000 250.000 282.000 310.000 334.000 354.000 370.000
10% OH 3.448 9.425 14.943 20.000 24.598 28.736 32.414 35.632 38.391 40.690 42.529
cost price 33.448 91.425 144.943 194.000 238.598 278.736 314.414 345.632 372.391 394.690 412.529
3% Profit 1.034 2.828 4.483 6.000 7.379 8.621 9.724 10.690 11.517 12.207 12.759
Total Offer 34.483 94.253 149.425 200.000 245.977 287.356 324.138 356.322 383.908 406.897 425.287
Unit price 471,26 373,56 333,33 307,47 287,36 270,11 254,52 239,94 226,05 212,64
= Production costs
+ Overhead cost
_____________________________________________________________________________________________________
27.9
-31.3 31.3
90.3 40.5
Allocation service cost centers -78.3 -43.6 64.3 54.6 3.0 121.9
Allocation of 0.0 1.9 -3.4 12.0 -3.1
General overheads / Production costs Production 596.1 1,058.8 24.3 1,679.2
*100%(151,4.0-15.0) /(1,678.2-300.0) * 10.0% -151.4 costs
Overheads 51.6 98.0 1.8 151.4
100% 16.6 Cover amount Full costs 647.7 1,156.8 26.1 1,830.6
Material: 270.0 Performance 676.0 1,306.0 22.6 2,004.6
Sub contractors: 30.0 28.3 149.2 -3.5 174.0
Amount: 300.0 Cover amount -24.0
G-OH-%: 15.0 5.0% Operation Result 150.0
Performance
- Direct manufacturing expenses
(wages, equipment, other own costs)
- Additional direct costs
(Material and Subcontractors)
_____________________________________________________________________________________________________
Cost Management:
Calculation
Total 79,588.10
7 Offer sum (OS) without tax Quantity x €/unit 1,000.00 x 66.42 = 66,420.00
Example: Calculation
Project 71147 Trough building Site manager Galneder Currency: T€ Financial status per 10/03/07
(A) (C) (D) (E) (F) (G) (H) (I) (K) (L) (M)
=(F)-(G) =(F)-(G) =(G)+(I)
Act. Booked
G-OH BOQ EOS Act.Perf. Costs Activate Accruals Variance Actual Costs
0. Cost types % total total Mth. Cum. Mth. Cum. Accruals Mth. Cum. Mth. Cum. Mth. Cum. Month
6. Production costs 70.7 71.6 23.8 22.4 1.9 -0.5 24.3 24.3
7. Sum G-OH 7.6% 5.4 5.5 1.8 0.1 0.0 1.8 1.8
8. Full costs 76.1 77.1 25.6 22.4 2.0 -0.5 26.1 26.1
10. Operation Result (OR) (9-8) 3.5 3.6 1.0 0.5 0.5
11. OR - % 4% 4% 4% 2% 2%
12. Contribution Margin (CM) (9-6) 8.9 9.1 2.8 2.3 2.3
13. CM - % 11% 11% 11% 9% 9%
Department/No: Civil works / 10 PROFIT AND LOSS OVERVIEW Financial status per 10/03/07 Created 10/03/07
71127 Site F 431.8 P 231.0 322.2 356.9 415.2 334.7 348.2 369.1 431.8 431.8 431.8 431.8 0.0
28.5% 123.0 OR 24.0 101.0 111.8 130.1 104.9 109.1 115.6 123.0 123.0 121.6 28.2% -1.4
71128 Site H 4,321.1 P 1,487.1 1,670.0 1,875.4 2,106.1 2,365.1 2,656.0 2,982.7 3,349.6 3,484.7 3,693.2 4,321.1 4,321.1 4,321.1 4,321.1 0.0
2.8% 123.0 OR 4.6 5.2 5.8 57.1 64.2 72.2 81.2 91.4 102.8 115.6 123.0 123.0 123.0 2.8% 145.9 0.0
71131 Site L 1,325.0 P 15.0 27.4 50.1 91.6 167.6 306.7 561.3 1,027.1 1,068.5 1,132.5 1,325.0 1,325.0 1,325.0 1,325.0 0.0
-6.9% -91.4 OR -1.1 -2.1 -3.8 -6.9 -12.7 -23.2 -42.4 -77.6 -80.7 -85.6 -91.4 -91.4 -101.7 -7.7% -10.3
71132 Site M 542.0 P 64.1 102.6 164.1 262.6 420.2 437.1 463.2 542.0 542.0 542.0 587.0 0.0
-4.4% -24.0 OR -3.1 -5.0 -8.0 -12.8 -20.5 -21.3 -22.6 -24.0 -24.0 -24.0 -4.4% 213.9 0.0
71133 Site N 876.6 P 146.5 190.4 247.5 321.8 418.3 543.8 706.9 749.2 876.6 876.6 876.6 876.6 0.0
3.9% 34.0 OR 7.8 10.2 13.2 17.2 22.3 29.0 30.2 32.0 34.0 34.0 31.8 3.6% -2.2
71145 Site A 981.8 P 128.0 235.8 467.0 676.0 342.9 209.0
6.8% 67.0 OR -6.0 8.9 17.3 28.3 4.2% 377.2 11.0
71146 Site B 1,891.0 P 213.9 401.6 980.6 1,245.0 1,306.0 1,342.8 61.0
3.0% 56.0 OR 14.2 75.4 122.6 129.2 149.2 11.4% 76.4 20.0
71147 Trough building 80.7 P 26.6 30.0 26.6
4.5% 3.6 OR 1.0 3.8% 10.0 1.0
Month Performance P 246 376.4 374.6 611.2 521.8 600.5 834.6 1,035.3 583.9 677.5 1,776.1 495.6 296.6 9,257.2 296.6
Month Op.-Result OR -73.8 -0.4 6.7 71.5 79.4 9.3 8.4 -51.2 27.1 70.1 71.7 15.0 18.1 6.1% 823.4 18.1
Year Performance P 372.8 749.2 1,123.8 1,735.0 2,256.8 2,857.3 3,691.9 4,727.2 5,311.1 5,988.6 7,764.7 495.6 792.2
Year Op.-Result OR -9.8 -10.2 -3.5 68.0 147.4 156.7 165.1 113.9 141.0 211.1 282.8 15.0 33.1 4.2%
Estimating:
• RIB –Arriba: www.rib.de/ Construction Suite (400 – 2500 €), (German/English)
(www.synergy-software.com/Solutions/ProductDetails/RIB/more_than_33.htm)
Estimator 2.0 www.estimator.in (100 US $)
• Pulsar www.estimatingsystems.com (3,128 US $)
• Win estimator WinEstPro www.winest.com (?? >3,000 US $)
Time Scheduling:
Estimating: