You are on page 1of 13

CHECK PROGRESS OF

ANNUAL IMPLEMENTATION
PLAN
SPT will monitor
progress at the
middle and end of
the
implementation
period.
For longer
projects the SPT
will monitor more
than twice.
SPT should guide
and help the project
team in resolving
problems especially
during the early
stage of the project
implementation.
Check progress and
compare the
performance before,
and after
implementing the
solution
The project team
will submit a
progress report
using the project
monitoring report
form for the
information of the
SPT on the status of
the project.
Both the SPT and
PT will discuss the
recommendations/
action points
based on the
results of the
monitoring done
by the SPT.
PROJECT MONITORING REPORT FORM
• Scheduled Dates of Monitoring
• Mid-year:__October_____________ Year:March-
end:_________________
NAME OF PROJECT DATE OF ACCOMPLIS ISSUES/ RECOMMEN SIGNATURE
PROJECT OBJECTIVES MONITORIN HMENTS/ PROBLEMS/ DATIONS/ OF SPT AND
AND G STATUS TO CHALLENGE ACGTION PROJECT
TARGETS DATE S POINTS TEAM
LEADER

To be discuss
----------------- --------- To be Filled by Project team-- ----------------- by SPT and
- - Project Team
PROJECT MONITORING REPORT FORM SAMPLE
• Scheduled Dates of Monitoring
• Mid-year:_______________ Year-
NAME OF end:_________________
PROJECT DATE ACCOMPLISHME ISSUES/PROBLEMS/ RECOMMEN SIGNATUR
PROJECT OBJECTIVES AND OF NTS/STATUS TO CHALLENGES DATIONS/ E OF SPT
TARGETS MONIT DATE ACTION AND
ORING POINTS PROJECT
TEAM
LEADER
Vocabulary To improve the number March 3, Based on the result 1.Only 250 out of 300 1.Teacher to
Enrichment in of learners who answer 2022 of assessment picture words were printed include needed
Grade 3 correctly during recitation conducted, 75% of due to lack of materials materials in
English in English class from the learners 2. 2 of the students PPMP
21% to 80% by the end answered correctly monitored through home 2.Use of ICT
of SY during recitation in visits spend an average of 5 assisted lessons
English class hours in computer games.
SCHOOL AIP CATCH-UP PLAN ­
PPAs to be Reasons ACTUAL Target Date/ Enhancement
Re-Entered for Re- DATE OF Period of Process/Strategy/Activity (If
Entry IMPLE Implementatio Any)
MENTAT n
ION
1.A Construc Inadequ June 2021 August 2021 To be included in the AIP
tion of ate wash adjustment
additional area to
wash area. cater our
learners
The progress report
shall be consolidated
to serve as inputs to
the SRC, which shall
be presented to the
stakeholders during
midyear and yearend.
• Based on the recommendations/action points, the project team and
SPT can now adjust, modify, and write the AIP for the following year.
• In starting the next AIP, the Project team assigned may begin by
collecting, organizing, and analyzing the required school data for the
PIAs to be tackled in the next AIP.
1.Project
Monitoring
Report Form
2. Updated SRC
based on results
and reports.