You are on page 1of 13

EEE 403 : Engineer and Society

Topic: The West Gate Bridge Collapse


Group 1

▪ Group Members:
▪ Muaz S. M. Anan (2020-1-80-055)
▪ Kazi Abid Shahnewaz (2020-1-80-066)
▪ Tanvir Hossain (2020-1-80-084)
• A. M. Nazmus Sadat (2020-1-80-090)
1
Table Of Contents :
Case Background …………………………………...... Slide 3-4
Engineering
….. Ethical Issue…………………………………. Slide 5
Engineer’s Responsibilities to Public Safety…….. Slide 6
Engineer’s Rights and Responsibilities………..….... Slide -7
Right Actions…………….......................................... Slide 8
Social & Environmental Impacts.......................... Slide 9
Conclusion………………………………….........................Slide 10-11
References…………………………………………………………Slide 12

2
Case Background
• West Gate bridge is located over Yarra river in
Malborne Australia[1]
• The construction of west gate bridge began in 1968
with an estimated completion date in 1970.[2]
• At 11.50 am on 15th October 1970, a span of the
west gate bridge collapsed during constructions.[1]
• 35 construction workers were died[1], 18 got
injured[2]
• The span 10-11 of the bridge collapsed during
construction due to a combination of design flaws
and construction errors.[1] Fig-1:Aerial shot of collapse of the west gate
Bridge in October 1970[3]

3
Case Background
 Design was done by FF&P(Freeman
Fox and partners) and they failed to
give a proper check[1]
 JHC and WSC were involved in
construction and erection of the
bridge[1]
 Unusual method was proposed by
WSC for erecction of span 10-11[1]
 To solve the problems, resident
engineer Hindshaw had every
intention of eliminating the buckle by
removing the bolts[1] Fig-2:Workers stand on the fallen span of the West Gate Bridge after its collapse[3]
* WSC– World Services and Constructions Co . Ltd**
* JHC-John Holland (Constructions) Pty. Ltd. **
4
Ethical Issues
❑ Lack ofresponsibility : ❑ Lack of professionalism

1. FF&P failed to give a proper 1. Hindshaw without proper


check[1] calculation gave permission
for the kentledge[1]
2. Unusual method proposed by
WSC[1] 2. Being unaware of the
situation during bolt
3. Absence of proper calculation[1]
removal[1]
4. Not obeying superior’s command[1]

They did not act in an ethical manner


5
Engineer’s Responsibility to Public Safety

 To follow usual and convenient method which is safe for public health and
welfare
 Ensuring designs, drawings and instructions are being clearly understood
 Ensuring all sort of safety measurements in construction site
 To do proper calculation before erecting any structure

6
Rights and Responsibilities of Engineers
Rights: Responsibilities:
 To get proper guidance before  To let the public know about possible risks
executing any action and danger
 Right of each employee to be  Review calculation properly and executing
protected and not be pressured proper designs
into doing things
 Always make decision with proper
 Right of getting proper safety
justification
while working
 Estimating load calculation properly
 Be concerned about public
 Take proper and immediate step if
safety while executing any
project mistakes have been identified
7
Environmental and Social impact
❑ Environmental impact:  Social impact:
 Material waste and resource  35 losses of lives and 18 injuries
consumption  Community distress
 Air and water pollution  Employment and livelihoods
 Noise and visual pollution  Public perception of infrastructure

 Ecosystem recovery safety


 Impact on workers and their families
 Long-term psychological effect

8
Right Action
 Proper design by FF&P and WSC had to be done

 WSC should have proposed an usual method

 Hindshaw ought to have made an accurate calculation


before giving permission for kentledge

 David Ward, the section engineer, should have left the


buckle in position until a later stage of construction.

 JHC engineers should have followed the instructions


of Hindshaw regarding keeping the kindledges on the
bridge
9
Conclusion
The West Gate Bridge collapse investigated by the Royal Commission
resulted in the following conclusions:
1. The bridge had structural design deficiencies that contributed to its
collapse
2. Poor communication between design and construction teams hindered
problem-solving
3. Faulty calculations underestimated stress loads, leading to insufficient
support for the bridge
4. Safety concerns were disregarded and inadequate precautions were
taken during construction

10
Conclusion
5. The safety of the lifting process was judged based on an inadequate analysis of
the situation
6. Neither FF & P nor WSC had a comprehensive understanding of the stresses
imposed on the bridge
7. The bridge's collapse resulted from an unfortunate combination of errors rather
than a well-informed engineering calculation
8. The collapse emphasized the need for thorough design, meticulous
calculations, and robust safety measures in engineering projects

11
Reference
[1] Westgatebridge.org. [Online]. Available:
https://www.westgatebridge.org/sites/default/files/downloads/report-of-royal-
commission.pdf
[Accessed: 19-Aug-2023].
[2] “West Gate bridge 50th anniversary,” OHS Reps. [Online]. Available:
https://www.ohsrep.org.au/west_gate_bridge_50th_anniversary
[Accessed: 19-Aug-2023].
[3] “From the archives, 1970: The West Gate Bridge collapses,” The Age, The Age, 14-Oct-
2020.
[4] “The error,” Westgatebridge.org. [Online]. Available: https://www.westgatebridge.org/node/110.
. [Accessed: 19-Aug-2023].

12
13

You might also like