ENGINEERING AND FACILITIES

MANAGEMENT UNIT

1
COMPLETION/UPGRADING OF
JONI VILLANUEVA GENERAL HOSPITAL

2
COMPLETION/UPGRADING OF
JONI VILLANUEVA GENERAL HOSPITAL
CONTRACTOR:
R.D. SADSAD CONSTRUCTION & TRADING
OWNER:
MR. ROMAN D. SADSAD
ADDRESS:
STO. NIÑO,
CITY OF SAN FERNANDO, PAMPANGA
TOTAL CONTRACT PRICE:
PHP 39,941,178.85
DURATION:
300 CALENDAR DAYS
START DATE: ACTUAL START:
JULY 19, 2023 AUGUST 15, 2023

COMPLETION DATE:
MAY 14, 2024
3
COMPLETION/UPGRADING OF
JONI VILLANUEVA GENERAL HOSPITAL

4
COMPLETION/UPGRADING OF
JONI VILLANUEVA GENERAL HOSPITAL

5
COMPLETION/UPGRADING OF
JONI VILLANUEVA GENERAL HOSPITAL

POSITION NO. OF WORKER


FOREMAN – OVERALL 1

MASON 29

WELDER 3

LABOR 32

COOK 2

DRIVER 1

TOTAL 68

AS OF NOVEMBER 15, 2023

6
COMPLETION/UPGRADING OF
JONI VILLANUEVA GENERAL HOSPITAL

CENTRAL WASTE STORAGE


AND CADAVER HOLDING AREA 7
COMPLETION/UPGRADING OF
JONI VILLANUEVA GENERAL HOSPITAL

MINOR RETOUCHING
AND CLEANING

AS OF NOVEMBER 15, 2023


8
COMPLETION/UPGRADING OF
JONI VILLANUEVA GENERAL HOSPITAL

MAINTENANCE BUILDING
9
COMPLETION/UPGRADING OF
JONI VILLANUEVA GENERAL HOSPITAL

AS OF NOVEMBER 15, 2023 10


COMPLETION/UPGRADING OF
JONI VILLANUEVA GENERAL HOSPITAL

3RD FLOOR OF MAIN BUILDING


11
COMPLETION/UPGRADING OF
JONI VILLANUEVA GENERAL HOSPITAL

AS OF NOVEMBER 15, 2023 12


COMPLETION/UPGRADING OF
JONI VILLANUEVA GENERAL HOSPITAL

ERECTION OF
STEEL COLUMNS AND BEAMS

AS OF NOVEMBER 15, 2023


13
COMPLETION/UPGRADING OF
JONI VILLANUEVA GENERAL HOSPITAL

SUBMITTED REQUEST FOR VARIATION / ADDITION

ACTIVITY PROJECTED START DATE


WINDOW @ MEDICAL RECORDS DECEMBER 2023

REPAIR OF TILES @ RM 202 DECEMBER 2023

REPAIR OF TILES @ RM 207 DECEMBER 2023

REPAIR OF TILES @ DENTAL HALLWAY DECEMBER 2023

REPAIR OF TILES @ ELEVATOR DECEMBER 2023

REPAIR OF TILES @ BREASTFEEDING ROOM DECEMBER 2023


AND NICU WORK AREA
REPAIR OF TILES @ ER RESUSCITATION DECEMBER 2023
AREA
DUCTING OF BIOSAFETY CABINET @ DECEMBER 2023
LABORATORY BUILDING

14
RLED DEFICIENCIES AND UPDATES

15
RLED DEFICIENCIES AND UPDATES

DEFICIENCY UPDATE PROVIDED DOCS


GENERATOR (ATS) FOR CANVASS LETTER OF COMMITMENT

EMERGENCY LIGHTS FOR DELIVERY (4TH WK OF NOV) LETTER OF COMMITMENT

WATER ANALYSIS WITH NTP LETTER OF COMMITMENT

16
RLED DEFICIENCIES AND UPDATES

DEFICIENCY UPDATE
STAFF FOR MAINTENANCE OF EQUIPMENT NEW HIRE – MET (DEC 1, 2023 START)

17
RLED DEFICIENCIES AND UPDATES

DEFICIENCY UPDATE PROVIDED DOCS


CALIBRATION OF MEDICAL REVISED WFP AND PPMP (FOR SIGNING OF RD) LETTER OF COMMITMENT
EQUIPMENT

18
RLED DEFICIENCIES AND UPDATES

DEFICIENCY UPDATE PROVIDED DOCS


ECC -DRAFTING OF NOV LETTER OF COMMITMENT
-TECHNICAL CONFERENCE FOR REDUCTION OF PENALTY
-APPLICATION OF ECC (20 DAYS PROCESSING)

19