Professional Documents
Culture Documents
AND
YARD DRAINAGE
L. N. NIRMALKAR
Asst. Professor /Track
7420041131
1
BAD DRAINAGE
2
BAD DRAINAGE
3
FOR GOOD DRAINAGE
4
WASHABLE APRON AND DRAIN
5
WASHABLE APRON AND DRAIN NGP YARD
6
WASHABLE APRON AND DRAIN NGP YARD
7
UNDER GROUND DRAIN AQ YARD
8
some examples of problems
resulting from poor drainage
Filled with
P-way
Material
which have
been
removed
from the
track but not
carried
9
some examples of problems resulting
from poor drainage
Overflowing of a drain
on top of the cut slope
causes erosion of the
slope.
11
Representative Sketch…
12
Load distribution factor- UIC
13
Continue..
14
Tamping
• The tamping process is commonly used to restore the
track geometry.
Note: 1) Mitre (bevelled ends) drains are connected to cess and catch drains to provide an
escape for water from these drains.
2) Mitre drains (at 45 degree) should be provided at regular intervals to remove water
before it slows down and starts to deposit any sediment that it may be carrying. (shown in
fig.2) 19
Cess drains
Cess drains are most frequently found in cuttings where water running off the
formation cannot freely drain away Surface drains can be constructed on fairly
flat grades, as they are easily cleared of any sediment that may collect in them.
20
Sub surface drainage
• Subsurface drains are used where adequate
surface drainage cannot be provided due to
some restriction or lack of available fall due to
outlet restrictions.
• Following Subsurface drainage systems
classified as per perform of their functions:
21
Collector drains
• Collection of infiltration water that seeps into the
formation (capping layer), as shown in Figure .
22
Drain for lowering water table
• Draw-down or lowering of the watertable,
as illustrated in Figure .
23
Seepage drains
• Drainage of local seepage such as spring inflow.
24
Longitudinal drain
25
Drainage blanket
26
Aggregate drains
These drains consist of permeable granular material. The aggregate
should be coarse enough to be free draining, but not so coarse as to
allow the migration of fines into or through the permeable material.
The graded aggregate is to be wrapped in a geotextile (Figure 14).
27
Pipe drains
These consist of perforated or slotted pipes, installed by trenching
and backfilling. Some type of filter material around the pipe or
permeable backfill is normally required to minimise clogging of the
drain perforations or slots
28
Geotextile Drains
A geotextile drain may be a horizontal, vertical, or inclined
blanket whose purpose is to collect subsurface water and convey it
along the plain of the fabric to an outlet. The drain must also act as
a filter to keep soil particles out of pores and prevent clogging.
29
GEOTEXTILES
30
Jute Geomats
31
32
WOVEN GEOTEXTILES
33
NON-WOVEN GEOTEXTILES
34
WOVEN GEO-GRID
35
8.4 Geo-synthetics
Types of Geo-synthetics
Geo-grids
GEO-CELL AND Typical Geocomposite Drain
37
Pre-fabricated Vertical Drain
38
GEO-STRIP REINFORCEMENTS
39
8.4 Geo-synthetics
Functions of Geo-synthetics
EFFECTIVE DRAINAGE
• Drains in yard, should be designed for velocity range of
0.5 -1.0 metre per second for kutcha drains and 1.0 – 2.0
metre per second for pucca drains.
• Longitudinal drains between two tracks normally should be
saucer shaped.
• Normally, the drain top shall not be above the cess level
for effective drainage of ballast bed. however it is not
feasible than drains to be provided with bottom level weep
hole or four centimetre wide vertical slit at every one metre
interval.
41
42
43
Factors Affecting track drainage
1. Clean, graded and adequate ballast.
2. Condition and cross slope of formation.
3. Side slopes, proper cess and toe of
embankment.
4. Turfing and pitching of side slopes
5. Type of soil in sub grade.
6. Side and catch water drains, retaining walls in
cuttings.
44
EFFECT OF BAD DRAINAGE
45
See ballast condition and observe
46
• 3. Side slopes, cess and toe of embankment:
• Side slopes
•. : In embankment should normally be 2:1 (H:V) and in
cutting depends upon type of soil - 1:1 (H:V) for normal soil and
½H:1V for hard rock.
• Cess on both sides of embankment should be lower than ballast
profile so as to avoid stagnation of water.
• Borrow pits should not be permitted close to the toe of
embankment
• The side drains shall be kept away from toe of bank.
• The series of existing borrow pits should be connected to each
other with small channel and the water finally discharged away
from the embankment.
47
Yard Drainage
48
Concept for design of drainage system...
• Adequate discharge capacity:
The most common method of estimating Flood Discharge for any given
catchment area is by using Rational Formula (RDSO Report RBF-16 also, for
estimating “Flood Discharge”).
Q = 0.278 x C x I x A
Q = Design Flood Discharge (in m3/s)
C = Run-off coefficient
• Velocity of flow in drain shall not be less than 1.0 m/s, for
self-cleansing action to take place.
• will also reduce the duration of open excavation on the side of running
tracks, which is required to be kept minimum from safety point of view.
• May be kept rectangular in shape, with vertical slits on both the vertical
walls, For the ease of casting and laying,
56
LONGITUDINAL DRAINS
• The bed gradient should 1 in 350 or steeper, to get required self-cleansing velocity of flow and to ensure
• To minimise excavation for drains, the gradient of longitudinal drain shall be same as gradient of
track/formation.
As per Schedule of Dimensions (IRSOD), the Steepest Gradient in yards can vary from 1 in 260 to 1 in
o in cases where the gradient of yard/ formation is 1 in 350 or steeper, the longitudinal drain shall have
•However, in cases where gradient of yard / formation is flatter than 1 in 350, the longitudinal drain shall have
gradient of 1 in 350 and the depth of drain will increase along its’ length in the direction of falling gradient.
57
Design of a Typical Drainage System
Ballast Ballast
Profile Profile
Side Slope Side Slope
100 mm 450 mm 100 mm
A Open Slit of 150 mm Height
Open Slit 150 mm
and 40 mm Width at 250
B mm c/c Spacing
Formation Top Level 150 mm Formation Top Level
C
Pre-Cast 150 mm
RCC Drain D
Suitable Chamfering of Corners
E
150 mm Thick
F Lean Concrete
900 mm
59
Ballast
Ballast Profile
Profile Side Slope
Side Slope
110 110
mm 450 mm mm
A
110 mm
E
150 mm Thick
Lean Concrete
F
900 mm
Location of
Minimum Depth of 900
Longitudinal Drain
Location of
370590
Maximum Depth of
Longitudinal Drain
Fig. 2 B/2: Longitudinal Schematic View of The
Longitudinal Drain (For Track Centre 5300 mm)
62
Pre-c a s t Se
g m e n t of
L e n g t h 0.5
m/1.0 m
L o n g i t u d i n a l D r a i n To p Level
110 m m
A-A
4 R o w s of Circular
110 mm
H o l e s 4 0 m m dia.
a t Ve r t i c a l S p a c i n g
of 1 5 0 m m c/c 150 1 5 0 150
m m m m m m
150 m m
F o r m a t i o n Level
B-B
Invert
Level
Lo c a ti o n of M i n i m u m D e p t h D rain of L o n g 150 1 5 0 1 5 0
itudin
of Lo ngi tudi na l Dra i n al m m m m m m
(All d i m e n s i o n s a r e i n m m . )
Circular holes 40mm dia. have horizontal spacing of 100mm c/c and vertical spacing of 150 mmc/C,
with centre of first hole at 100mm from edge of the element. Thus, 0.5m long element will have 4 holes
in each row and 1m long element will have 9 holes in each row.
The ends of elements shall be cast with grove in one element and projection in matching element on
other side (as shown in details at A-A and B-B above).
Fig. 2A/2 : Side Schematic View of Longitudinal Drain
(For Track Centre 4265mm)
Pre-cast S eg
me nt of
Length 0 .5 m/
1.0 m
Longitudinal Drain Top Level
110 mm
A-A
2 Rows of Circular 150 1 5 0 150
Holes 40 m m dia. m m m m mm
110 mm
at Vertical Spacing
of 150 m m c/c 150 mm
Fo r m a t io n Level
B-B
Location of M i n i m um Depth
of Longitudinal Drain Invert
Level
of L o
ngit udina
l D ra 150 150
Details at J u n c t i o n A-A Details at J u n c t i o n B - B in mm
150
mm mm
Segment 1 Segment 2
Segment 1 Segment 2 Segment 1 Segment 2
30
50
30
50 30 Drain
Drain Vertical 50 Bottom
Portion
Location of M a x i m u m Depth
Wall 30
of Longitudinal Drain
50 50
View from Top View from Side View from Side
Circular holes 40mm dia. have horizontal spacing of 100mm c/c and vertical spacing of 150 mmc/C,
with centre of first hole at 100mm from edge of the element. Thus, 0.5m long element will have 4 holes
in each row and 1m long element will have 9 holes in each row.
The ends of elements shall be cast with grove in one element and projection in matching element on
other side (as shown in details at A-A and B-B above).
Fig. 2B/2 : Side Schematic View of Longitudinal Drain
(For Track Centre 5300mm)
LONGITUDINAL DRAINS
minimum distance between track centres in yards is
4265mm for existing yard and 5300mm for all new yards.
The lower track centre (4265mm) will require deeper drain
to ensure that the ballast profile side slope line cuts the
drain below its’ top.
Ballast
Ballast Profile
Profile Side Slope
Side Slope
100 mm 450 mm 100 mm
A
150 mm
B
65
LONGITUDINAL DRAINS
• The minimum depth of drain is 450mm (track centre 5.3 m) /
750 mm (TC 4.265m) at the starting point and when the depth
reaches 1200mm, a chamber will be provided and the drain
will be continued on other side of chamber starting with a
minimum depth of 450mm/ 750 mm again.
• The longitudinal drains are normally open.
• However, in yards where there is likelihood of drains getting
blocked due to garbage etc. or movement of maintenance staff is
required on longitudinal drains, grated covers can be provided on
top.
• In case the longitudinal drain meets any culvert in the yard, it shall
connect to and discharge in the culvert subject to invert level and
discharge capacity of the culvert permitting it .
66
LONGITUDINAL DRAINS
• The chamber size should be as 0.9m x 1.2m.
• The arrangement at chambers, with cross drain(s)
Grating
100 mm
450 mm
or 750 mm
1200 mm
150 mm
Cross Cross
Drain Drain
100 mm
1200 mm
1800 mm
67
LONGITUDINAL DRAINS
Cross Cross
Drain Drain
300 mm 300 mm
Grating Grating
Longitudinal
Longitudinal
Drain
Drain
450 mm 900 mm 450 mm
1200 mm
X X
Grating Grating
Cross Cross
Drain Drain
68
CROSS DRAINS
69
A yard drainage system, designed in proper manner and
constructed taking into account relevant technical
parameters, will be effective in discharging water away
from the track formation. Not only improve reliability of
assets but will also ensure fruitful utilisation of the
money spent on yard drainage system.
70
THANKS
71