Indeterminate Frame Analysis
using Force Method
Presented to
Sourav Ray
Associate Professor
Department of Civil and Environmental Engineering
Shahjalal University of Science and Technology
Presented by
Group - 5
2019333015-Tasnia Tahsin
2019333026-Md. Daniel Hossain Tonmoy
2019333048-Mahfujur Rahman Joy
2019333083-Fahmida Rahman
2019333086-Dipjoy Roy Dip
2018333062-Sufal Chakraborty
10k
3k/ft
Solution:
2’ 2’
B C
6’
2I
Degree of indeterminacy for rigid frame, I 5’
5’
5’
4
Let us choose Dx as redundant,
10k 10k
3k/ft 3k/ft
2’ 2’
6’
= +
2I
5’
5’
I
2k I Dx 2k Dx
ΔD DxδD
5’ Dy Dy
Ax Ax
Ay Ay
𝐿
𝑚𝑀
Δ=∑∫ 𝑑𝑥
0 𝐸𝐼
6
Calculation for ΔD:
10k
3k/ft
2’ 2’
6’ 10’
5’ 5’ 5’
5’ 14.4 k 0.5 k
2k 1k
13.6 k 0.5 k
∑Fy = 0 ∑Fy = 0
=> Ay = (3×6) + 10 - 14.4 ⸫ Ay = 0.5k (↓)
⸫ Ay = 13.6k (↑) 7
3 4 5 3 4 5
10k
3k/ft
2’ 2’
6’
3 4 5 3 4 5
5’
2 2 2 2
5’ 6 6 6 6
2k Real Load Virtual Load 1k
5’
1 1 1 1
8
3 4 5
Real Moment (M) and Virtual Moment (m) Calculation 10k
3k/ft
2’ 2’
Section
Moment for real load, M Moment for virtual load, m 6’
3 4 5
1-1 5’
2 2
5’ 6 6
2k Real Load
2-2
5’
1 1 14.4 k
2k
3-3
13.6 k 3 4 5
4-4
3 4 5
2 2 6 6
1k
Virtual Load
5-5
1 1 0.5 k
1k
6-6
0.5 k 9
Now, according to virtual work equation,
Section M m
1-1
2-2
3-3
4-4
5-5
6-6
10
Calculating δD
𝐿
𝑚𝑀 δD
Δ=∑∫ 𝑑𝑥
0 𝐸𝐼
11
Calculation for δD: 2
10’
∑Fx = 0
2
=> Ax = 1k (→) 3 3
5’
10’
1k
∑MA = 0 1 1
1k
∑ Fy = 0
12
2
Section 10’
Moment for virtual and real load, m
1-1 2 3 3
5’
2-2 1 1 1k
10’
0.5 k
3-3
1k
0.5 k
Now, according to virtual work equation,
δD
From compatibility condition:
ΔD = DxδD
Dx =
Dx = 2.36k (←)
13
10k
3k/ft
So, 2’
2’
∑Fx = 0
6’
=> Ax = 2.36 - 2
2I
=> Ax = 0.36 k (→) 5’ I 5’
∑Fy = 0 0.36 k
14
14.78 22.81
21.07
14.63
B C B C
3.22
13.22 11.8
13.6
2.36 2.36
SFD BMD
1.8
D D
0.36
A A
15