You are on page 1of 1

Materials Stones Natural Stones Natural Stones (Walling) Machine Cut Decorative Sand Cement Ballast Reinforcement Bars

Y-12 Y-10 Y-8 R-8 Water Labour Supervisor Fundi KYM Dressing Natural Stones Tying the Reinforcement Bars Trenching DPM Hoop Iron Binding Wire Gate Nails Electricals Cabling Conduits Sockets Gate Lights Gate Bulbs Security Enhancers Metal Fabrications Concertina Wire Others Wheelbarrow Tiling (Wall sills) Spades Wood - Formwork

Cost per Item Kshs 8,500 Kshs 8,500 Kshs 13,000 Kshs 35,000 Kshs 710 Kshs 22,000 Kshs 720 Kshs 520 Kshs 390 Kshs 380 Kshs 120 Kshs 1,000 Kshs 600 Kshs 300 Kshs 10 Kshs 5 Kshs 100 Kshs 3,500 Kshs 150 Kshs 120

Qty 3 9 7 1 1 30 1 11

Cost Kshs 21,318 Kshs 78,166 Kshs 89,661 Kshs 35,000 Kshs 21,300 Kshs 22,000 Kshs 7,920

Comments Laying as foundation Perimeter Details Meters 76 Feet Courses Foundation 251 11 3

Decorating the Gate

Half a lorry in the compound For the Pillars - 6 Pillars Max

6 0 4 30 40 2759 251 76 3 5 4

Kshs 2,280 Kshs 0 Kshs 4,000 Kshs 18,000 Kshs 12,000 Kshs 27,588 Kshs 1,254 Kshs 7,600 Kshs 10,500 Kshs 750 Kshs 480

Water available in compound

3 Fundis Working 10 Days Max 4 KYMs To be done by the Fundis

Kshs 1,900 Kshs 250

2 2

Kshs 3,800 Kshs 500

TOTAL Contigency GRAND TOTAL

Kshs 274,456 Kshs 27,446 Kshs 301,902

Add 10% Contigency