You are on page 1of 1

PROJECT MASTER SCHEDULE

DATED AUG 13 2013


ID
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38

Task Name

Duration

Start

Finish

Master Scehdule
Clients Approval
Test Fit Confirmation
Project management confirmation
Kickoff meeting
DB&B Contractor Confirmation
Pre qualification of contractor
Preparation of RFP
Selection of General contractor
GC Interview and price Negotiation
Contract Award
Submission
Site Handover
Submission Drawing
Landlord / Building Management
Government Authority approval ( 20 working Days )
Schematic and Detail design period
Schematic Design preparation
Schematic design review and confirmation
Detail design and construction drawing preparation
Long Lead Item ( System furniture procurement)
Place order and Production
Delivery on site
Construction Period
Site marking , Review & Approval
Fitting out Construciton
Carpet Installation
Furniture Installation
IT Room Handover
IT Equipment Installation
Test and Commissioning
DTZ & Client First Inspection
Final Approval and Inspection
Landlord inspection and Approval
Government Inspection and Approval ( 20 working days )
Defect Rectification
DTZ & Client Final Inspection
Client Move-In

44 days
2 days
1 day
1 day
1 day
7 days
1 day
1 day
3 days
2 days
1 day
11 days
1 day
2 days
3 days
6 days
11 days
3 days
4 days
4 days
23 days
22 days
1 day
24 days
1 day
20 days
1 day
1 day
1 day
8 days
1 day
1 day
10 days
3 days
6 days
9 days
1 day
1 day

8/12/2013
8/12/2013
8/12/2013
8/13/2013
8/13/2013
8/14/2013
8/14/2013
8/14/2013
8/15/2013
8/20/2013
8/22/2013
8/23/2013
8/23/2013
8/23/2013
8/27/2013
8/30/2013
8/23/2013
8/23/2013
8/28/2013
9/3/2013
9/9/2013
9/9/2013
10/16/2013
9/9/2013
9/9/2013
9/10/2013
10/15/2013
10/16/2013
10/4/2013
10/7/2013
10/17/2013
10/17/2013
10/18/2013
10/18/2013
10/23/2013
10/18/2013
10/31/2013
10/31/2013

10/17/2013
8/13/2013
8/12/2013
8/13/2013
8/13/2013
8/22/2013
8/14/2013
8/14/2013
8/19/2013
8/21/2013
8/22/2013
9/6/2013
8/23/2013
8/26/2013
8/29/2013
9/6/2013
9/6/2013
8/27/2013
9/2/2013
9/6/2013
10/16/2013
10/15/2013
10/16/2013
10/17/2013
9/9/2013
10/14/2013
10/15/2013
10/16/2013
10/4/2013
10/16/2013
10/17/2013
10/17/2013
10/31/2013
10/22/2013
10/30/2013
10/30/2013
10/31/2013
10/31/2013

Notes : The above Schedule Can be acheived if the approval of FSB and BMO all can follow the dates of the above schedule

Aug 11, '13

Sep 1, '13

Sep 22, '13

Oct 13, '13

You might also like