Professional Documents
Culture Documents
446primavera Sample Project
446primavera Sample Project
Sample Project
Prepared by: Luay Dwaikat,
MSc. Construction Management
1) Project information:
Schedule the following project using Primavera Project Planner considering that the project will start on 1 Jan. 07 without any day off.
Activity
Description
I.D
Duration
Predecessor
Excavation
--
leveling
anti termite
Foundation
2,3
inspection
Ground slab
4,5
Plumbing
Columns
Luay Dwaikat
6,7
Resources
Resource
Qty.
(Units/day)
Excavator
helper
Helper
mason
Helper
Helper
Steel fixer
Carpenter
Mason
Helper
1
8
9
5
7
5
5
5
5
4
Helper
Steel fixer
Carpenter
Mason
Helper
Plumber
Helper
Steel fixer
Carpenter
Mason
8
5
5
5
2
2
4
5
5
5
Material
Quantity
(Budgeted)
unit
--
--
--
--
--
--
200
30
5
M2
M3
Ton
--
--
--
Concrete
Steel
5
1
M3
Ton
4 PVC Pipes
15
Concrete
Steel
2
1
M3
ton
Material
Termite Material
Concrete
Steel
S.
N.
1
2
3
4
5
6
7
8
9
10
Resource
excavator
helper
Steel fixer
Carpenter
Mason
Plumber
4 PVC pipes
Concrete
steel
termite
Unit price
($)
40 / hr
7 / day
10 / day
11 / day
10 / day
3 /hr
2/m
40 / m3
200 / ton
2 / m2
S.n
Engineer
Responsible for
Foundation
Inspection
Ground slab
Columns
Excavation
Leveling
Anti-termite
Plumbing
Luay Dwaikat
4) Progress Update:
The site feedback indicates the following activities status in 18th of Jan 2007:
S.
N.
1
2
3
Activity
Description
Excavation
leveling
anti termite
Original
Duration
1
9
5
Remained
Pct
Duration
100 %
0
100 %
0
100 %
0
Foundation
100 %
5
6
7
8
inspection
Ground slab
Plumbing
Columns
4
4
6
1
0
4
0
1
100 %
0%
100 %
0%
Notes
Started & finished on time
Started & finished on time
Started on 3rd of Jan. and Delayed tow
days
Started on 12th of Jan. and Delayed one
days
Started on 8th of Jan
Started on 18th of Jan
Started & finished on time
--
Using Primavera Project Planner, update your schedule and answer the
followings:
1)
2)
3)
4)
Luay Dwaikat