CRAWL SPACE WITH COFFOR

TWO METHODS

Method 1:
In two steps: foundation then crawl
space Two pouring

1. Pouring a rough concrete at bottom of foundation


2. Placement of foundation rebarPouring foundations
3. Starter bar are ready to receive the COFFOR panels

Rough concrete 8-10 cm

5. Placement of COFFOR panels The COFFOR panels are


placed horizontally

Rough concrete 8-10 cm

6. The COFFOR panels are cut with an electric saw to leave


the thickness of the slab.

Thickness of slab

6. Positioning of rebar for the crawl space

7. Placement of the horizontal formwork for the slab The


formwork can be a COFFOR single panel or any other type
of formwork
8. Placement of rebar for slab.

BEFORE POURING CONCRETE


- The plumber must come to insert all
conduits (evacuation of water and all
plumbing).
- Installation of ventilated grids.
- The electrician must come to insert all
conduits for electrical.

9. Pouring of the crawl space together with the slab resulting in a


full monolithic structure.

Method 2:
In one step: foundation and crawl space
are built at the same time only one
pouring

1. Pouring a rough concrete at bottom of foundation


2. Mise en place des armatures de fondation
3. Mise en place des armatures verticales du vide sanitaire

Rough concrete 8-10 cm

10

4. Placement of the COFFOR panel Panels are placed


hotizontally. The COFFOR panel goes down up the rough
concrete.

Rough concrete 8-10 cm

11

5. The COFFOR panel is cut with an electric saw to leave the


thickness of the slab

Thickness of slab

12

6. Concreting of foundation

13

7. Placement of the horizontal formwork for the slab.


8. Placement of rebar for the slab.

14

BEFORE POURING CONCRETE


- The plumber must come to insert all
conduits (evacuation of water and all
plumbing).
- Installation of ventilated grids.
- The electrician must come to insert all
conduits for electrical.

15

9. Pouring of the crawl space together with the slab resulting in a


full monolithic structure.