Pipeline (WPS & WQT)

Sample of Process Flow


Commence

3d
pWPS

21d
WPQT

7d
WPS

14d

Resources
1 Welding Engineer: 360hrs
1 Welder Foreman: 280hrs
1 Fitter Foreman: 280hrs
1 QC Supervisor: 336hrs
1 QC Inspector: 1344hrs
1 Production manager: 40hrs

Total Duration = 45 days


*subject to how many test is required.

WQT

Pipeline (Transportation Study)


Sample of Process Flow
AFC Drawings
Consultant Report
General
Arrangement
Load-out Info
Sea State
Barge Confirmation

Transportation
Study

8d

Analysis/Report

2d
Documentation/
First Rev.
Submission

10d

Reviewed by
Company

7d

Issued for Approval

Resources
1 Marine Engineer: 80hrs
1 Lead Engineer: 8hrs
1 Drafter: 80hrs
1 Lead Drafter: 8hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 10 days
2

Pipeline (Pipelay Analysis)


Sample of Process Flow
AFC Drawings
Consultant Report
DL Barge Details

Pipelay Analysis

21d
Analysis/Report

3d
Documentation/
First Rev.
Submission

10d

Reviewed by
Company

7d

Resources
1 Marine Engineer: 168hrs
1 Lead Engineer:24hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 24 days

Issued for Approval

Pipeline (Pipelay Procedure)


Sample of Process Flow
AFC Drawings
Consultant Report
Pipelay Analysis
Pre-lay Survey
Report
pWPS
Barge Confirmation

Resources
2 Field Engineer: 336hrs
1 Lead Engineer: 24hrs
1 Drafter: 80hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 24 days

Pipelay Procedure

21d

Constructability
Review

Analysis/Report

3d
Documentation/
First Rev.
Submission

10d

HAZID

Reviewed by
Company

7d

Issued for Approval


Readiness Review
Pipelay Commence

Structure (On-Bottom Analysis)


Sample of Process Flow
AFC Drawings
Consultant Report
Soil Report
Fabrication WCR
Specification

On-Bottom
Analysis

7d

Jacket Model

21d
Analysis/Report

3d
Documentation/
First Rev.
Submission

10d

Reviewed by
Company

3.5d

Resources
1 Structure Engineer: 248 hrs
1 Lead Engineer: 16hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 31 days

Issued for Approval

Structure (Upending)
Sample of Process Flow
AFC Drawings

Jacket Upending

Consultant Report

5d

Sling Confirmation
Single Block
WCR
Crane Barge
Confirmation
Jacket Main model

Double Block

8d
Analysis

3d
Documentation/
First Rev.
Submission

10d

Reviewed by
Company

Resources
1 Structure Engineer: 128hrs
1 Lead Engineer: 24hrs
1 Drafter: 40hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 16 days

7d

Issued for Approval

Structure (Transportation Study)


Sample of Process Flow
Transportation
Study

AFC Drawings
Consultant Report
General
Arrangement
Fabrication WCR

Jacket/Topside

Piles

15d

10d

Sea State
Analysis/Report

Analysis/Report

Barge Confirmation
Load-out Info

3d

2d Resources
Documentation/
First Rev.
Submission

10d

Reviewed by
Company

7d

Issued for Approval

1 Marine Engineer: 144hrs


1 Lead Engineer: 24hrs
1 Drafter: 144hrs
1 Lead Drafter: 24hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 18 days
7

Structure (Conductor Hang-off)


Sample of Process Flow
AFC Drawings
Consultant Report
Conductor Make-up
Hanger Selection
Specification

Conductor Hang-off
Analysis

15d
Report/Analysis

2d
Documentation/
First Rev.
Submission

10d

Reviewed by
Company

7d

Issued for Approval

Resources
1 Structure Engineer: 136hrs
1 Lead Engineer: 24hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 17 days

Structure (Pile Drivability Study)


Sample of Process Flow
Pile make-up
Hammer Details
Soil report
Sea state Criteria
(underwater Piles)

Piles Drivability
Analysis

7d

Report/Analysis

2d
Documentation/
First Rev.
Submission

10d

Reviewed by
Company

3.5d

Resources
1 Structure Engineer: 72hrs
1 Lead Engineer: 16hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 9 days

Issued for Approval

Structure (Pile Upending)


Sample of Process Flow
Pile Make-up
Barge Info
General
Arrangement
Sea state Criteria
Crane Lift Chart
Clamp Details

Piles Upending

15d
Report/Analysis

3d
Documentation/
First Rev.
Submission

10d

Reviewed by
Company

7d

Issued for Approval

Resources
1 Marine Engineer: 144hrs
1 Lead Engineer: 24hrs
1 Clerk/QA: 8hrs
Total Duration for first
submission = 18 days

10

Structure ( Jacket/Topside Installation


Procedure) Sample of Process Flow
Constructability
Review

AFC Drawing
Rigging Calculation

Final WCR
Consultant Design
Report

14d

Info From
Fabricator

Loadout
Coordination
Manual
Rigging Calculation

Total Duration for first


submission = 31 days

3d

Documentation/
First Rev.
Submission
HAZID

Resources
2 Field Engineer: 448hrs
1 Lead Engineer: 24hrs
1 Drafter: 112hrs
1 Clerk/QA: 16hrs

14d

Installation
Procedure

10d

Reviewed by
Company

7d

Issued for Approval


Readiness Review
Installation
Commence

11