Timing plan for balance works

S.No

as on 25.12.12

Description
Switchyard

Supply and installation of capacitors


1
2 S&I of HT cables and termination
3 S&I of windows in control room
4 TNEB portion of switchyard works
5 TNEB metering room construction
6 TNEB tower erection works
7 HT cable works from Transformer to Panel board
8 Testing and pre commissioning of EHT and HT system
9 Gate works + fencing works
Downstream works
HT cable works from HT Panel board to Soft starters and LBS panels
10
11 630 KVA transformer earthing
630 KVA transformer cabling and termination - Primary and secondary
12
13 S&I of of Main panel, SSB, MCC,MLSB and APFC panel
14 Cabling between main panel and sub panels
15 Equipment cabling and termination
16 Earthing for plant

as on 25.12.12

Completion date
31/12/12
5/1/13
25/01/13
25/01/2013
25/01/2013
25/01/2013
8/1/13
30/01/2013
8/1/13

10/1/13
10/1/13
10/1/13
30/01/2013
10/1/13
20/01/2013
20/01/2013