You are on page 1of 51

View Publication

You have asked to view a publication

When you have finished viewing, click on

Now choose one of the following options:

view
publication
chosen

in the toolbar to return to this screen.

return to
publications
list

A survey of 40 office buildings


with long-span concrete floors
P.W. Matthew BE, MSc, MIE(Aust)
and D.F.H. Bennett BSc, MSc, CEng, MICE

FOREWORD
This publication was commissioned by the Reinforced
Concrete Council.
The Group was set up in 1988 to promote better
knowledge and understanding of reinforced concrete design
and building technology.
Its members are Co-Steel Sheerness plc and Allied Steel
& Wire, representing the major suppliers of reinforcing steel
in the UK; and the British Cement Association, representing
the major manufacturers of Portland cement in the UK.
The authors of this publication are Peter Matthew, partner
with consulting engineers Powell, Tolner & Associates and
David Bennett, Senior Engineer in the Marketing Division
of the British Cement Association.

ACKNOWLEDGEMENTS
The authors wish to thank the following organizations for
their considerable help in providing the building data for
the survey:
Anthony Hunt/YRM Partnership
Beers
Bison Limited
Bunyan Meyer & Partners
Composite Structures Limited
DGI International plc
Ferguson & McIlveen
Frank Hodgson & Associates
James-Carrington and Partners
Jan Bobrowski and Partners
Ove Arup & Partners
Powell, Tolner & Associates
Skidmore, Owings & Merrill
Waterman Partnership
Thanks are also due to Brian Dyer of Tower Associates
for drafting the floor plans.

97.311

Published by the British Cement Association on behalf of


the industry sponsors of the Reinforced Concrete Council.

ISBN 0 72101386 4

British Cement Association


Telford Avenue, Crowthorne
Berks RG45 6YS

First published 1990


Reprinted 1994, 1995

Price Group F

Tel (01344) 762676


Fax (01344) 761214

@ British Cement Association 1990


All advice or information from the British Cement Association is intended for those who will evaluate the significance and limitations of
its contents and take responsibility for its use and application. No liability (including that for negligence] for any loss resulting from such
advice or information is accepted. Readers should note that all BCA publications are subject to revision from time to time and should therefore
ensure that they are in possession of the latest version.

CONTENTS
INTRODUCTION

NOTES ON SURVEY

DESIGN FEATURES OF SPECIAL INTEREST

CHOICE OF FLOOR SLAB DESIGN

Solid flat slabs


Ribbed slabs
Waffle slabs
One-way spanning solid slabs and beams
Precast slabs
Composite precast slabs

CONCLUSION

SURVEY DATA

Section 1:

Solid flat slabs


Reinforced - Buildings 1 to 7
Prestressed - Buildings 8 to 12

Section 2:

Ribbed slabs
Reinforced - Buildings 13 to 15
Prestressed - Buildings 16 to 22

Section 3:

Section 4:

Section 5:

15-19

20-22
23-29

Waffle slabs
Reinforced -Buildings 23 to 25

30-32

Prestressed - Buildings 26 to 28

33-35

One-way spanning solid slabs


and beams
Buildings 29 to 33

36-40

Precast slabs
Buildings 34 to 36

Section 6:

8-14

41-43

Composite precast slabs


Buildings 37 to 40

44-47

INTRODUCTION
Traditional concrete designs for office building have been
associated with either beam and slab or flat slab floors,
typically with 6 to 7.5 m spans. Occasionally, longer-span
floors have been designed using ribbed or waffle
construction. In recent times, changes in the requirements
of end-users and in developers specifications have led to
more open-plan offices and larger floors. This has
increased spans from 6 to 9 m, even to 15 m and more.
To verify the competitiveness of concrete long-span
floors, a survey has been conducted of concrete-framed
office buildings, the majority constructed in recent years.
Forty buildings of in situ, precast and composite
construction with long spans have been surveyed. In each
category, examples were found of floors designed in
reinforced and prestressed concrete to carry similar office
floor loadings.
For in situ structures, solid flat slabs and ribbed slab
designs were common, with spans varying from 6 to 15 m.
A number of precast structures with long spans, some
over 20 m, are reported, with composite in situ slabs acting
with precast ribs or other precast members.

(Figure 1) indicates a braced structure where the horizontal


forces are transmitted to shear walls by the floors acting as
diaphragms. In the case of an unbraced structure [Figure 2),
stability is provided from within the frame by the
interaction of columns and floors and referred to as frame
action.
All tables should be read in conjunction with the
corresponding floor plans and section details.

Shear walls

NOTES ON SURVEY
The survey data are presented in the second part of this
publication, beginning on page 7. The information has
been arranged according to structural floor types as
follows:
Section 1 - Solid flat slabs
Section 2 - Ribbed slabs
Section 3 - Waffle slabs
Section 4 - One-way spanning solid slabs and beams
Section 5 - Precast slabs
Section 6 - Composite precast slabs
The structural information and quantities of material
for each building surveyed are presented in tabular form
and are accompanied by a typical floor plan and floor
section.
For each building studied, quantities of concrete,
reinforcement and prestressing steel are expressed in
units/m2 of floor area. All quantities related to vertical
components, i.e. columns, walls, etc., have been excluded,
thus the effect of storey height and number of storeys is
eliminated.
The span/depth ratios given in the tables are based on
the maximum spans.
Notes on the design Code of Practice, concrete grade
and method of achieving frame stability have been added
to provide useful information on the design of the
structure.
The column headed Design loads gives the floor
loadings used in the structural design, i.e. imposed load,
finishes, partition and service loads: it does not include the
self-weight of the floor.
The method of achieving frame stability for each
building is indicated in the column headed Stability by
shear walls or frame action. The term shear walls
2

Figure

I:

Lateral stability provided by shear walls.

Figure 2: Lateral stability provided by frame action.

DESIGN FEATURES

Overall to suit column size


c

OF SPECIAL
INTEREST

J--r
650

Notes on a few of the buildings surveyed are given below to


highlight certain construction and design features that
provide particular economic advantages for a given floor
tY Pe.
Building 5
310 mm reinforced solid flat slab, span 9.5 x 7-3 m.
Lightweight aggregate concrete with a compressive
strength of 30 N/mm2 was used in order to reduce the
self-weight of the floor and the cost of the foundations.
As the span/depth ratio exceeded the guiding limits in
the Code (CPllO), compliance with maximum deflection
in the serviceability limit state was proved by calculation.
The floor slab was designed as a beam supporting a
one-way spanning flat slab, all within the 310 mm depth of
construction. The beam, 2.5 m wide, spans longitudinally
from the interior column to the lift core. The one-way
spanning slab is simply supported at the perimeter and
continuous over the beam.

-A-

Plan

Building 7

255 mm reinforced solid flat slab, span 9.2 x 6-0 m.


The deflection of the 255 mm flat slab was checked by
finite element analysis, taking full account of edge
stiffening from the perimeter columns and beams in
addition to the internal columns and frame. A lateral
stability check was carried out on a three-dimensional
computer model of the structure. The inherent stiffness of
the perimeter beams and columns plus the internal frame
eliminated the need for shear walls.

Section

Figure 3: Detail of steel shearhead.

Building 10
300 mm post-tensioned solid flat slab, span 9.4 x 9.0 m.
Steel cross-bracing, in combination with the floor slab
acting as a diaphragm, provided the lateral stability. Drop
panels were eliminated by forming shearheads within the
slab depth (Figure 3). All external columns were connected
to steel beams, composite with the slab, to cater for
punching shear.
Building 13
450 mm reinforced ribbed slab, span 9.0 m.
The wide-rib profile, spaced at 1.5 m centres, provides
adequate flexibility to accommodate small and large
service openings in the floor. The rib profile made it
possible to use table forms with integral grp rib moulds to
ensure a fast building programme (Figure 4).
Building 14

425 mm reinforced ribbed slab, span 9.0 m.


The irregular floor plan of the building and the clients
requirement for minimum column sizes resulted in it being
inappropriate to provide stability by frame action. Shear
walls, with no returns and a minimum of cross walls, were
specified to facilitate rapid construction of walls.

Figure 4: Grp rib moulds fixed to table forms.


3

Building 26
500 mm prestressed/reinforcement waffle slab,
span 12.0 X 12-O m.
The solid beam strips were post-tensioned, with the waffle
section reinforced. This allowed the waffle section to be
reinforced independently of the beams, thus speeding up
construction, whilst maintaining an economical floor
depth.
Building 31
335 mm one-way spanning prestressed solid slab,
span 12.6 m.
The frame was designed as a stacked portal, with 160 mm
precast perimeter walls supporting a 335 mm
post-tensioned solid slab. An important benefit in
post-tensioning the slab was that the end moments
transferred to the precast walls, due to dead load, were
negligible. This in turn led to manageable transfer
moments in the wall under ultimate load conditions.
The structural solution proved both economic and fast
to build, with a maximum net to gross floor area.
Building 36
200 mm precast floor slab, span 7.7 m.
The precast columns were designed as vertical cantilevers
fixed at the base to provide frame stability. The precast
floor beams were simply supported and designed as pin
joint connections to the columns.
Building 37
560 mm double-T floor units with in situ topping,
span 14.5 m.
Stability was achieved by a combination of shear walls at
the ends of the building and frame action developed from
the precast perimeter H frames. The H sections are formed
by adjacent perimeter columns and the perimeter edge
beam (Figure 5a). The precast column joints are positioned
at mid-storey height, i.e. the point of contra-flexure, so a
full moment connection to the double-T floor beam was
possible (Figure 5b). The precast frame was erected in just
under ten weeks.

2400

-II/

(a) Elevation

Figure 5: Detail of precast H frame.


4

4800

CHOICE OF FLOOR
SLAB DESIGN
In assessing the structural cost of a multi-storey building, it
is evident that the bulk of the cost is often for the floor slab
construction. Therefore, the overall economy of a structure
may depend on the efficiency and economy of the floor
slab system. While quantities of materials reflect the
efficiency of the design and structural layout, the actual
cost of the structure may also depend on such factors as
s p e e d o f construction, local market conditions,
competitive tendering, availability of labour and
equipment and cost of construction finance. Consequently
a structural design that has proved to be competitive in one
region may not always be competitive in another.
For a building to meet the needs of major financial
occupiers in todays market, the choice of floor design is
often determined by one or more of the following
considerations:
l

The need for long spans to provide floor space


uninterrupted by cores and columns.

0 A maximum floor-to-floor height which allows


adequate space for services and ducts, balanced against
planning pressure to limit overall building height.
0 An adaptable floor structure which can accommodate
future tenant alterations with maximum speed and
minimum disruption.
The wide range of floor construction in both
reinforced and prestressed concrete, highlighted in this
survey, demonstrates that concrete floors can be designed
economically to meet these requirements.
The types of floors and the reasons for choosing them
are given opposite.

I/

I I
I
I

2400
4,

(b) Section

Solid flat slabs (with or without


drops)
The principal feature of the dropless floor is its flush soffit
which requires only simple formwork and is easy to
construct (Figure 6a). The overall depth of this floor is a
minimum and it allows great flexibility for locating
horizontal services. However, the economical span range
of a reinforced floor is limited by shear in the vicinity of the
column supports and the need to control long-term
deflection.
The provision of drop panels at the column supports
(Figure 6b) avoids the need for shear reinforcement and
increases the stiffness of the slab and the economical span
range. Alternatively, a structural steel shearhead can be
incorporated to maintain a flush soffit to allow for easy
construction and efficient use of large forming systems
(Figure 6c).

Ribbed slabs
Providing ribs to the soffit of the floor slab can reduce the
quantity of concrete and reinforcement, and thus the
weight of the floor. The deeper, stiffer floor permits longer

spans to be used. Formwork complexity can be minimized


by the use of standard modular, re-usable formwork. When
flying form panels are used, the ribs should be positioned
away from the column lines. Ribbed slab floors are very
adaptable for accommodating a range of service openings
(Figure 7).

Waffle slabs
Waffle slab floors are commonly used when buildings are
subjected to heavy imposed loading. They are very
efficient in the use of materials and provide very
economical long spans, but the additional complexity of
formwork can often slow the construction. Where speed of
construction is critical, a ribbed slab or a shallow beam
solution is often preferred.

One-way spanning solid slabs


and beams
A wide, shallow beam profile is often preferred in order to
reduce the overall depth of the floor, whilst permitting
longer spans. The one-way spanning solid slab between
the beams facilitates the use of table forms for fast
construction (Figure 8).

1-2-1:::
1r-1

I--

~~-~~-l'-'

'-::-~J--,:-;:-:

:-,r-

Figure 7: Ribbed slab for flexibility to accommodate openings.

(b)

Figure 6: Solid flat slab: (a) without drop panels;


(b) with drop panels; (c) with shearhead.

Figure 8: Band beam and slab construction using tableforms.


5

Precast slabs

Composite precast slabs

Precast slabs offer the advantage of off-site manufacture,


with a reduction in site labour and site formwork. When
the slabs are prestressed there are additional benefits of
longer spans and higher load capacity. A popular type of
precast floor is the hollow core slab (Figure 9). The
relatively lightweight units form a flush soffit when
placed. A shear key between units ensures load sharing
and the construction is commonly capable of developing
diaphragm action without the need for a structural
topping. The precast units are easy to remove and can
accommodate a wide range of floor openings.

Composite precast slabs combine precast floor elements


with in situ concrete in an economical way, eliminating
traditional formwork for floor construction, and providing
long-span floors. Thin precast concrete floor plates can be
combined with an in situ topping to form composite
one-way spanning floors up to 6 m long, or, in combination
with precast beams, to form a composite ribbed slab
(Figure lOa). For extremely long spans, double-T precast
beams and a composite in situ topping is preferred
(Figure 10b).

CONCLUSION
The buildings surveyed in this publication demonstrate
that reinforced and prestressed concrete floors with spans
ranging from 6 to 20 m, are technically feasible and
economically competitive.
This is a direct consequence of improved design and
analysis techniques, higher strength materials, better
construction methods and finally, more construction-led
design.

Figure 9: Precast hollow core planks:flexibility for alterations.

Figure IO: Composite floors: (a) precast ribbed floor;


(b) double-T beam floor.
6

SURVEY DATA
Section 1:

Solid flat slabs


Reinforced - Buildings 1 to 7
Prestressed - Buildings 8 to 12

Section 2: Ribbed slabs


Reinforced -Buildings 13 to 15
Prestressed -Buildings 16 to 22

Section 3: Waffle slabs


Reinforced -Buildings 23 to 25
Prestressed - Buildings 26 to 28

Section 4:

One-way spanning solid slabs and beams


Buildings 29 to 33

Section 5: Precast slabs


Buildings 34 to 36

Section 6:

Composite precast slabs


Buildings 37 to 40

SECTION 1
SOLID FLAT SLABS

7.2x7.2

mm
I

ratio
I

300

24

m3 1

0.30

Jr

kg
I

30.0

3600

Ji

1
I

6-O

Solid flat slab -reinforced

r ~~~~

Frame

action

3600

1"

GradeC40
Code BS 8110

7200

'i

3600

1"

3600

I-

300 slab

7
J

_I

Solid flat slab -reinforced

No.
of
floors
10

Materials per m2
Design
of floor area
load
Depth Span/depth Conc;ete Rebar kN/,,$
Slab

Span
m

mm

ratio

7.5x6.1 3 0 0

Stability

Notes

Shear
walls

Grade C35
Code BS 8110

kg

25

0.30

45.0

6-O

300 slab
I

Typical floor plan

Solid flat slab -reinforced

3000

3000

5 i(J 7500

A
i

8
2

400 slab

400 slab

mi

n
1

_L

1 /

Typical floor plan

10

Solid flat slab -reinforced

No.
of
floors
7

Materials per m*
Design
of floor area
load
Depth Span/depth Conc;ete Rebar kN/,-,-,*
mm
ratio
kg
Slab

Span
m
65x45

250

26

0.25

29.0

5 0

Stability

Notes

Shear
walls

Grade C35
Code BS 8110

17 ccc 45
Typical floor plan

1`

Solid flat slab -reinforced

No.
of
floors
4

Materials per m*
Design
of floor area
load

Slab
Span
m

Stability

Depth Span/depth Conc;ete Rebar kNirn2


mm
ratio
kg

9-5x 7.3 310

30.6

0.31

Typical floor plan

41.5

5.0

Shear
walls

Notes
(See page 3)

C30 lightweight
Code CP 110

Solid flat slab -reinforced

Materials per m2
Design
of floor area
load
Depth Span/depth Co;;ete Rebar kN/r-$
mm
ratio
kg
Slab

No.
o
f
Span
floors
m
13

5800

8 0x7.2

275

3 irr 7200

275 slab

Typical floor plan

29

0.28

5800

40.7

5-o

Stability

Notes

Shear
walls

Grade C35
Code BS 81 10

Solid flat slab -reinforced

Stability
I

9.2x6.0

7
I

I
I

255
II

0.26

36

Notes
(See page 3)

II

24.0
II

5.2

6200

5 ((I 6000

255 slab

Typical floor plan

14

Solid flat slab - prestressed

Span
m

Design
load
Depth Span/depth Con$ete Rebar Strand kN/r-$
ratio
mm
kg
kg

8.0x8-0 275

29.1

10-2

0,275

,.~- . .

Gl

Materials per m2
of floor area

Slab

No.
of
floors

10..0

Stability

Notes

Shear
walls

Grade C40
Code BS 8110

.j----

X
i..t

:*

x
x
x

Eico

Atrium

PI

P1

First-floor plan

Column head detail

15

Solid flat slab - prestressed

Stability

7.2x 7.2 240

30.0

0.240

2.4

4.7

Notes

Shear
walls

6.5

* See Concrete Society TechnIcal Reports No 17 and No 25

3 ((I 7200

4800

0
0

cu

P-

Typical floor plan

:i,

950

I /
Column head detail

475

240
$ 50
i 250

Solid flat slab - prestressed

Materials per m
of floor area

Slab

No.
of
floors

Span
m

Depth Span/depth Conx$ete


mm
ratlo

9 4x9-o 300

31 3

0 300

Design
l o a d
Rebar Strand kN/mz
kg
kg

14-l

78

50

Stability

Steel
bracing to
columns

Notes
(See page 3)
Grade C40
Code BS 8110
CS TR 17 & 25*
Steel c o l u m n s
with shearheads

* See Concrete Society TechnIcal Reports No 17 and No 25

45000

Typical floor plan

Cross-bracing

17

Solid flat slab - prestressed

No
of
floors

Materials per m*
of floor area

Slab
Span
m

11 5 x 7 5 325

35 4

O-325

11

See Concrete Society TechnIcal Reports No 17 and No 25

Typical floor plan

Design

load
Depth Span/depth Concrete Rebar Strand kN/mz
mm
ratio
m3
kg
kg

65

50

Stability

Notes

Frame
action

Grade C40
Code BS8110
CSTR 17&25*

Solid flat slab - prestressed

Slab
Stability

7200

3600

Typical floor plan

Typical column head detail

7200

2400
*II

7200

3600

7200

Notes

SECTION 2
RIBBED SLABS

Ribbed slab -reinforced

Materials per m*
Rib
Beam
No.
Des
of floor area
,__ign
of
wad
floors Span Depth Span/depth Span B x D Span/depth Concrc ?te R e b a r kN/m*
10

mm

ratio

mm

ratio

m3

kg

9.0

450

20.0

8.0

1200
x 450

13.3

0.23

39.5

7.5

Notes

Stability

(See page 3)

Frame
action

Grade C35
Code BS 8110

7 ((1 9000

Typical floor plan

Typidal rib section

20

Typical beam section

Ribbed slab - reinforced

No.
of
floors
11

Materials per m2
of floor area f$$ Stability

Beam

Rib

Notes
(See page 3)

Span Depth Span/depth Span B x D Span/depth ConcJete Rebar kN/m*


mm
ratio
kg
m
ratio
mm
m
9.0

425

9000

21 .l

9.0

1800
x425

6750

21.1

4 @ 7500

5.0

38.5

0.27

6750

Shear
walls

Grade C35
Code BS 8110

9000

5 (u, 9000
Typical floor plan
1500
_~~ __~
125
L

-t

T 1425
I I

l-l

7Ii

425

:
1800

250

Typical rib section

Typical beam section

Ribbed slab - reinforced

floors Span Depth Span/depthSpan


m

mm

9.0 3 0 0

Materials per m2
of floor area Dri,n Stability

Beam

Rib

No.

ratio

30.0

B x D Span/depth

mm

1800
7-2 x 4 0 0

ratio
18.0

0.32

6 ((I 7200

29.0

5.0

Shear
walls

9000

1800
Typical rib section

22

Notes

Conc;ete Rc??r kN/mz

Typical beam section

Grade C35
Code BS 8110

7200

Ribbed slab - prestressed

No.
of

Rib

Materials per m*
of floor area

Beam

Design
load

Stability

Notes

Frame
action

Grade C35
Code BS 8110

floors Span Depth Spacing Span/depth Span B x D Span/depth Type Concrete Rebar Strand kN/&
m
mm
mm
ratio
m
mm
ratio
kg
kg
3

9.0

3 2 5

1200

27-7

1800

18-5

6.0 x 3 2 5

Pt

0 194

12 6 3.65

6.0

Prestressed

Typical floor plan

100
325

Typical rib section

ki!

23

Ribbed slab - prestressed

No.

-I
of
floors

Materials per m*
of floor area

Beam

Rib

Stability

Notes

Span Depth Spacing Span/depth Span B x D Span/depth Type Con;;ete Rebar Strand kN/t-$
m

22

9.0

mm

mm

250

750

ratio

36.0

mm

ratio

2200
7.5 x 2 5 0

30.0

kg

Pt

0.186

kg

7 . 0 3 5.79

*Prestressed

10 @ 7500

Typical floor plan

2200

750
125

A -

-r

.250

250

I-

175
Typical rib section

24

Design
load

Column head detail

5.0

Shear
walls

Grade C40
Code CP 110

Ribbed slab - prestressed

Materials per m2
Beam
Rib
NO.
Design
of floor area
of
load
floors Span Depth Spacing Span/depth Span B x D Span/depth Type Con;;ete Rebar Strand kN/m*
mm

mm

ratio

9.8 400

725

24.5

ratio

mm

1 9 4 1200
x 800

24.2

Pt

0.354

kg

kg

16.9

9.76

6.0

Stability

Shear
walls

Notes

Grade C40
Code CP 110
Prestressed

I.

I.

I.
13000

9350

9350

I.

10000

Typical floor plan

725

75

725

725

Typical rib section

25

Ribbed slab - prestressed

Materials per m2
Rib
Beam
No.
Design
of floor area
o
f
load
floors Span Depth Spacing Span/depth Span B x D Span/depth Type Concrete Rebar Strand kN/r-$
m
5

mm

10.85 450

mm
850

ratio

mm

ratio

24.1

12.5

1500
x450

28.0

Prestressed

Typical floor plan

Typical section

Pt*

m3

kg

kg

0.280

8.3

6-63

5.0

Stability

Notes

Shear

Grade C40

walls

Code CP 110

Ribbed slab - prestressed

Materials per m*
Beam
Rib
Design
No.
of floor area
load
o
f
floor s Span Depth Spacing Span/depth Span B x D Span/depth Type Conc;ete Rebar Strand kN/m*
m
5

mm

135 475

mm

ratio

1500

28 4

mm

ratio

9 . 0 1500
x475

Pt*

18.9

0,285

kg

kg

15.0

4.93

Notes

Stability

Shear walls Grade C40


and frame
Code BS 8110
action

60

l Prestressed

I II II II
I
II
II
I
II
II
I
II
II

u
/

II II II
II
II II
II
II
II II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
II
I I II

II
II
II
II
II
II
II
II
II
II
II
I I II
II
II

I
I
I
I

L~LJLJL~LJLJLJLJLJLJLJLJLJL.~L.n
n
w

riririr~r~rlrlr~r~r~r~r~r~r~r~,

ririr

II II
II
II
II
I
II
II
I/
I
II
II
II
II
II
II
11
II
II
II
I II
I
II
I
II
II
II
II
II
II
II
II
II
II
II
L~L~L~L~L~L~L~L~L~L~~~~~~~~~~~~~~~~~,~~

I
I

I II
II
II
II
II
II
I /I
II
II
II
II
I I II

r-i r

II

II

I I I I II
II
II

iririr~r-lr~r~r~r1rlrlrlr~r~r~r~rlrl

II
II
II
II
II
I
I I
II
II
II
II II I
I I
II
II
II
II
II
I
I I
L J -JLJLJ LJLJLJL-ILJLJ
I
I
I

II
II
II

I
I
I

II

II
II

r -1 -1rir-i r Iririririrl

II
II

I
I
I

II
II
II

II
II
II

II
II
II

II
II
II

II
II
II

II
II
II

II
II
II

II
II
II

I
I
I

LJL~ILJLJLJLJLJLJLJ

n
riririririr

II
II
II II
II
II
II
II
I
II
II
II
II
II
I I
LA _ _J L A L A LJLJLJLJLALJ LJLJLJLJLJLJLJLJL.~J
II

II

10

ll~-lrlrl
-

Typical floor plan

1500
125

1500

Typical beam section

1, J:

425

Typical rib section

27

Ribbed slab - prestressed

Materials per m2
Rib
Beam
Design
No.
of floor area
of
load
floors Span Depth Spacing Span/depth Span B x D Span/depth Type Concrete Rebar Strand kN/m2
m

mm

14.4 650

mm

ratio

22.2

2400

mm

ratio

1200
7.2 x 6 5 0

R.C.*

0,268 1 4 . 7

Notes

Shear
walls

Grade C40
Code BS 8110

kg

kg

11 .0

Stability

4.33

7.0

Reinforced

B0

8 @ 7200
1

:
I
I

II

II
II
II

II

I
I

II

I II
I
II
I II

II
II
II
II
II

:I
II

jl
11

II

ll
iI
iI
II

II
II
II
II

II
II
II
I

ll

II

II

II

n
II

n
Ii

I7
II

11
II

r7
II

fl
II

I4
L L

M
-IL
I I - I I AIL u lb
/

Typical floor plan

2400

28

II
II

J
u
u
u
H
H
H
H
H
- u .-IL Al- u -IL ii- il -IL II_

Typical section

II

500

Ribbed slab - prestressed

Materials per m
Rib
Beam
Design
No.
of floor area
load
of
floors Span Depth Spacing Span/depth Span B x D Span/depth Type Concrete Rebar Strand kN/m
m
mm
mm
ratio
m
mm
ratio
kg
kg
4

16.3 525

31 .0

850

6.3

275
X1000

R.C.*

6.3

0.225

9.8

5.66

Stability

Shear
walls

6.0

Notes

Grade C40
Code CP 110
Reinforced

7 @ 6300

Typical floor plan

100

850

0
%

850

Typical section

29

SECTION 3
WAFFLE SLABS
No.
of
floors
5

Column
spacing
m

Waffle slab - reinforced

Materials per m*
Design
of floor area
Depth Span/depth
load
Stability
mm
ratio
Con-v$ete R e b a r S t r a n d kN/m2
21.2

6.6 X 7.43 350

5835

0.245

kg

kg

24.0

7425

Frame Grade C35


Code BS 8110
action

6-O

3 @ 4950

---*

Typical floor plan

Ribs at 900 crs

!
125

4;7
I

1600
Section at column head

30

Notes

Waffle slab - reinforced

No.
of
floors
3

Column
spacing
m

Materials per m2
Design
of floor area
Depth Span/depth
load
mm
ratio
Con;;ete R e b a r S t r a n d kN/m2

7.5x10 5 5 2 5

, 7500

typical

20.0

0.450

kg

kg

67.0

6-O

Stability

Notes

Frame Grade C35


action
Code BS 8110

Typical floor plan

Typical section

31

Waffle slab - reinforced

No.
of
floors

Column
spacing
m

10.18
x10.18

Depth Span/depth
mm
ratio
550

Materials per m*
of floor area

Design
load Stability

18-5

0.396

37.0

Typical section

9.0

Shear Grade C35


Code BS 8110
walls

3 @ 10180

Typical floor plan

32

Notes

Conc;ete R e b a r S t r a n d kN/m2
kg
kg

125 14

Waffle slab - prestressed

No.
of
floors
1

Materials per m2
of floor area

Design
Notes
Depth Span/depth
load Stability
(See page 4)
mm
ratio
Compete Rebar Strand kN/m2
kg
kg
Shear Grade C40
15.9
2.52
6.0
0.349
24.0
12.0x12.0 500
Code BS 6110
walls
Column
spacing
m

6000

4 @ 12000

CIOOOOOOO

rlnnnnnnrin

Typical floor plan

Typical section

125

33

Waffle slab - prestressed

No.
of
floors
2

Column
spacing
m

Materials per m*
Design
of floor area
Depth Span/depth
load Stability
mm
ratio
Cor?$ete R e b a r S t r a n d kN/m*

12.7x12.7 500

25.4

0.341

12700

Typical floor plan

Typical section

kg

kg

12.2

5.60

6.0

Shear
walls

Notes

Grade C35
Code BS 8110

Waffle slab - prestressed

Stability

Notes

~c~~~

Grade C40
Code BS 8110
CS TR No. 17*

*See Concrete Society Technical Report No 17

5 @ 15000

1
,;:j; ji

: : : _-:
::~:: ::p::-::-:,

;.:I.

-7..
:.::.

: ::
1

:.

li

ij

. -. .: ..-.. ~.i[:lI:
:.::..:..:.::.::
:~::..li:
::..LL

:
:~::z..

.I! j
:::.:
.::

a
:,
: .;_;;

1_~1;.1;.1;:1:.:1~1!_.
~..
:.~:.~::~

.,: :I..

.iilii:

:.!:~:.~I:.::.::.::.:!.:L.::!
!L :
:-::.::I:.,~ . . . . .
.~..~_.

,..,:

.,

: : ::r::

__,:

Lo:!

::~::

!!

.-..-.

:,

,,

:: :

::=::
,!

,I

: :, :
::-::-::.:,
,I

.,

,,

. . ..i.:

Atrium

Typical floor plan

Typical section

225

35

SECTION 4
ONE-WAY SPANNING
SOLID SLABS & BEAMS

One-way spanning
solid slab and beam

Materials per m2
Slab
Beam
No.
Design
of floor area
of
. load
floors Span Depth Span/depth Type Span B x D Span/depth Type Concrete Rebar Strand kN/+
m
4

mm

ratio

7.43 200

37.2

m
Pt*

9.0 1 5 0 0

Prestressed

Typical floor plan

Typical beam section

36

mm

x 500

ratio
18.0

m3
Pt*

0.261

kg

Stability

Notes

kg

1 4 . 0 4.11

4.0

Shear

Grade C35

walls

Code BS 8110

One-way spanning
solid slab and beam
Slab
Beam
No.
o
f
floors Span Depth Span/depth Type Span BxD Span/depth Type
m

mm

10.30 2 5 0

ratio

41.2

Pt*

mm

1500
6.0 x 4 5 0

ratlo

13.3

R.C.+

Materials per m2
of floor area

Design
load

Stability

Notes

Conc;ete Rebar Strand kN/m*


kg
kg

0.298

13.9

3.93

6.8

Shear
walls

Grade C30
Code CP 110

Prestressed +ReInforced

250 slab

Typical floor plan

Typical beam section

37

One-way spanning
solid slab and beam
Materials per m2
Beam
Slab
Design
No.
of floor area
load
of
floors Span Depth Span/depth Type Span BxD Span/depth Type Concrete Rebar Strand kN/m2
ratio
m3
kg
kg
mm
m
mm
m
ratio
7

12.6 3 3 5

37.6

Pt*

Precast perimeter wall support

Prestressed

335 slab

Typical floor plan

38

0 335

11.8 8.25

6.8

Stability

Shear
walls

Notes
(See page 4)

C40 lightweight
Code BS 8110

One-way spanning
solid slab and beam

Beam
Slab
No.
of
floors Span Depth Span/dept Tyee Spnn BxD Span/depth Type
m
10

mm

6 75 220

ratio

30 7

R.C.* 10

mm

600x
0 6oo

Materials pe r m2
of floor area

Design
load

Stability

Notes

Shear
walls

C40 lightweight
Code CP 110

Conc;et e %??r StFgn d kN/m2

ratio

16.7

R.C.*

0.26

42-O

5 0

*ReInforced

E0

Typical floor plan

Main beam section

39

One-way spanning
solid slab and beam

No.
of
floors

Slab

Materials per m2
of floor area

Beam

Design
load
Span Depth Span/depth Type Span B x D Span/depth Type Con-$ete Rebar Strand kN/&
m
mm
m
mm
ratio
ratio
kg
kg

6.0

175

34.3

R.C.*

9.0

1500
x425

21.2

R.C.*

0.25

52.0

Reinforced

Typical floor plan

425
:

Typical section

40

5.0

Stability

Notes

Shear
walls

Grade C40
Code BS 8110

SECTION 5
PRECAST SLABS

Precast slab

Materials per m2 of floor area


Beam
Slab
Design
No.
In situ
Precast
load Stability
of
floors Span Section Span/depth Span B x D Span/depth Conc;ete Rebar Strand Conc;ete Rebar kN/r-$
m

12

7.0

mm

203

ratio

34.5

mm

ratio

300
6.0 x 6 0 0

10.0

kg

0.145

4.8

kg

kg

40

Notes

0,011

0.4

7.0

Shear
walls

C50, BS 8110
7% in situ
Hollow core
planks
No topping

6 @ 6000

Typical floor plan

Precast

yqFy=

:z

300
Centre beam section

41

Precast slab

mm

7.2

200

36.0

Design
load
B xD Span/depth Concrete Rebar Strand Conc$ete Rebar kN/m2

mm

7.2

600
x600

ratio

m3

ratio

12.0

Typical floor plan

Typical section

kg

o-193

7200

5400

kg

Stability

Notes

Shear

Grade C50
Code BS 8110
Hollow core

kg

3.0

7.9

7200

7200

42

Materials per m of floor area


In situ
Precast

Beam

Slab
No.
of
floors Span Section Span/depth Span

7200

planks
No topping

7200

5400

7.0

7200

Precast slab

Materials per m2 of floor area


Slab
Beam
No.
- Design
In situ
Precast
load
of
floors Span Sectlon Span/depth Span B x D Span/depth Concrete Rebar Strand Con$ete Rebar kN/m*
m

77

mm

200

ratio

38.5

mm

m3

ratio

7 . 4 3 ,$;o 1 2 . 4

0.157

kg

10.5

kg

Stability

Notes
(See page 4)

kg

2.55

- -

6.5

Frame
action

Grade C50
Code BS 6110
Hollow core

planks
No topplng

Typical floor plan

Typical section

43

SECTION 6
COMPOSITE
PRECAST SLABS
Rib
No.
of .
floors Span Depth Span/depth Span
mm
m
m
ratio

14.5

560

25.9

4.8

Composite precast slab

Materials per m2 of floor area


In situ
Precast

Beam

Design
load
Depth Span/depth Concrete Rebar Strand Concrete Rebar kN/m2
mm
ratio
m3
kg
kg
m3
kg
500x
1000
(Perimeter)

Stability

Grade C60
Code CP 110
any$$ar Double Tees, wrth
In situ topping
walls
Precast H frame
Frame

4.8

0.150

5.75

0.080

6.3

14500

2.2

5.0

4800 typical

47600
Typical floor plan

1200

, In s i t u t o p p i n g

-/

Typical section

44

Precast double-T beams

Notes
(See page 4)

Composite precast slab

f10 2 Span

16.7

22.0

4.9

600x
900
(Perimeter)

1.54

Frame
action

5.0

9 @ 4877

~f?~+kPl-rr~P~~~nn-n

II II II
I I
II
II II
II II Ii
II
Il l II II
I I II I
II II II
II II II
II II II
- + tit c- b !,

z
co

0,075

0,133 5 - 4 8 7 . 7 9

5.4

2438
i
*

111 1) 1

In situ

Notes

load Stability
Depth Span/depth Con;;ete Rebar Strand Conc;ete Rebar kN/m
mm
ratio
kg
kg
kg

Depth Span/depth Span


mm
ratio
m

785

Materials per m o
Precast

Beam

Rib

No.

II II I I

II

II

II

II

II

II

II

II

II

2438

II

I I I I II

II

II

II

I I II II

I I I I I I I I II

II

II

II

II

II

II

I I I I III
I I II III
Ill
II lib
II III
II
III
II III
II II IIP
II II III
I I II III

I I
I
I
I
I

I I

I I I I I I I I II II II II I I I I II I I II II I I II II II I I II I I I I II I I II II II II II II I II III
L
km c hL c Lu,u--u-uLu~
u-u~u-u,u-u-uLu,
u u4 Ad 4 u Am11 4 4 44 -IF

Typical floor plan

1200

In situ topping

1
j-=-f

Precast double-T beams


Typical section

n~nn~n~n-nn~~n~~n~nLr~~n111141ild 11111Vfb
II

75 (average)

Grade C60
Code CP 110
Double Tees, with
in situ topping
Precast H frame

;710

Composite precast slab

Rib
No.
of
floors Span Depth Span/depth Span
m

mm

/ 12.0 1

ratio

610

Design

. load

Stability

Notes

Depth Span/depth Concrete Rebar Strand Concrete Rebar kN/m*


ratio
mm
m3
kg
kg
m3
kg

750x
j 9.0 1 ,in;FU, 1

19.7

Materials per m2 of floor area


Precast
In situ

Beam

14.8

1 0.134 (13,751 - 1 0.111 110 721

5.7

Frame
action

In situ C35
Precast C45
Code BS 8110
55% In situ

r iririr i r i r i r
I
I

II
II
II

irir

II

II

II

II

II

II II

II

II

II

ir iririr irwirlir ir

II II II II II II II
II II II II II II II II
II
II II II II II II II II II II II II II II II II
II II II II Ii II II II II II II II II II II II II

II

II

II

II

II

II

II

II

II

II

Typical floor plan

55 precast soffit plank


Precast rib
Typical rib section

46

Typical in situ beam section

Composite precast slab

Materials per m2 of floor area


Precast
In situ

Beam

No.
o f
floors Span

Design
load

Depth Span/depth Concrete Aebar Strand Concrete Rebar kN/m

mm

ratio

m3

kg

kg

m3

kg

21.2

750
Precast

28.3

0,123

4.9

7.6

0.060

2-28

5.0

Stability

Shear
walls

Notes

Grade C62
Codes CP 115,
CP 116
40% In situ

72000

8
cv
i;

_
~n-=-rt-~n--~-un~~~~nn~~~~h~~n~n~n~~~~~nnnunu~~~=-n~~n~~~~
,, ,, II Ii II I II II II II I I I II 1 II II II II il II II II II I I II II II I II II II II II II
I II II II II I, II II II II II
,, ,,
1,

II

11

II

II

II

II

II I ~:I~_:~

11,
AlI
!I,
I,
JIl

II
II
II
I!
II

II
II

II llr
:! Id
II lli:

II I Nt ~ I I I I

II
II
II

~~11R#
II- 11~;

II
II
II

II
II

II v
,I
Ii

;~

II t

II II!
II IIL
IlL

II IIL
II II
II IIL
II II II II II II II 1: 1: I II I I! I II II II II II II II II II II II II II II II II II !I II II II II II II II II II II II II II II II II
vYv-Y~~Y~4_yu~~~L-L_-v~y~.~_yu_u_y-y-y _ y--y-y4~-y~y-&icy~~ 4 y u y~y-y~y--y~yy-yy

Typical floor plan

Beams @

Precast soffit planks

Precast beam
Typical section

1500 crs.

Economic long-span concrete floors


P.W. Matthew and D.F.H. Bennett
BRITISH CEMENT ASSOCIATION PUBLICATION 9 7.3 11

CI/SfB
I

(13)

q4

(Y6)

UDC
624.073.012.4.003.1

You might also like