Drawing Submittal Review Comments

Ground Floor Fire Alarm Overall Layout


Revise & Resubmit
-

Submit the drawing with the following services coordinated details:

All the MEP Services

Reflected False ceiling layouts

ELV services for the interfacing of Security and Door Access system etc.

Ensure to install all the MMs /CMs in coordinated accessible locations

Line isolators and transient circuit protection shall be indicated in the layout
as specified.

Complete system drawings and layouts shall be submitted with detailed


schematic riser, cause and effect matrix, battery sizing calculations, voltage
drop calculations / cable sizing calculations for the fire alarm system cabling
including the audible and visual alarm notification circuits etc.

Provide the additional loop wire for the connection of detectors as specified.

Indicate the installation details of the panels, call points, sounders etc. with
reference to the layouts.

The complete fire alarm and voice evacuation system shall be carried out in
full compliance with the DCD approval and requirements. Ensure to obtain
approval prior to the commencement of construction at site.