PROCEDURE/S

1. Stop On-Going Operation/s:


KERRY supervisor/s or ZTE personnel on duty should stop all
on-going activities.
Remarks:

2. Evacuate Working Area:


Ensure that all the personnel/s evacuate the working area
inside the factory.
Remarks:

3. Operate Generator:
KERRY supervisor/s should operate the generator set to
resume the power inside the factory.
Remarks:

4. Resume Operation/s:
Once the power resumes, continue activities inside the
factory.
Remarks:

5. Notify ZTE Personnel/s:


KERRY supervisor/s should notify ZTEfactory personnel/s on
the incident thru SMS or EMAIL.
Remarks: