15 CLAIMS
2.15.1 CONSULTANT'S CLAIMS AND EOT PROCEDURE

Client PM Design Consultant Contractor

Produce Notice to Claim


(Copied to Client)

No

Approve
Notice for
Claims, Based
on Relevancy

Yes

Review Claim & Make


Determination and
Recommendation to
the Client

No

Review &
Approve
Recommedation

Yes

Arrange Meeting with


Design Consultant
Attended by PM, to
reach an Argreement
and Settlement

Payment made to
Design Consultant
through VO Procedure