100 PPM PROGRESS

at

Chennai plant
Road Map
In progress Plan Delay

Aspee springs chennai-100 ppm road map


Jul-10 Aug-10 Sep'10
Activity wk 1 wk 2 wk 3 wk 4 Wk 1 wk 2 wk 3 wk 4 Wk 1 wk 2 wk 3 wk 4 Wk 1

Awareness to down the leval people

GAP analysis and improvement

KAP preliminary visit & Closure

Obserbations &Closure

Re-Launching 100PPM with New team 12-Aug

TFT Formation 21-Jul

Re-gap Analysis & Improvement


commitments(& bench mark visit) 23-Jul

Road Map to achive & Progress review

Self Audit

GKN 1st Audit

GKN 2nd Audit

KAP & HMIL Audit

Sustaining confirmation revisit


TFT TEAM
CHAMPION
N.Ravichandran ( C E O)

TEAM LEADER
TET
S. Natarajan (Quality Head)

MEMBERS: Mr.B.JOTHIPRAKASH (MR)


Mr.VARINDER GUPTA (PRODUCT DEVELOPMENT)
Mr.S.SIVAKUMAR (PRODUCTION)
Mr.SARAVANAN (SETTER)
Mr.S.RAMAKRISHNAN (QUALITY CONTROL)
Mr.G.SELVARAJ (STORES)
Mr.PRAKASH (MAINTENANCE)
Mr.SATHYA NARAYANAN (OPERATOR)
GKN SUPPORT
Mr. ASOKAN VAITHINATHAN
Mr.BALAJI
Mr.SANKAR GANESH

HMIL SUPPORT: Mr. VIJAY GANESH


Machining / 100 PPM Requirements

100 PPM LAUNCH


12th August 2010
100 PPM launch process

SLOGAN : Achieve 100 PPM


100 PPM launch process
How?:

Control and Maintenance of :

In process control and Quality management .


3C & 5S ,Process standard,
Machine Maintenance and Inspection.

Target :

Upgrade ASPEE to by October 2010


ROAD MAP TO ACHIEVE 100 PPM
1.AWARENESS (LAUNCH, BENCH MARK VISIT)

2. TFT FORMATION

3. GAP ANALYSIS & IMPROVEMENT COMMITMENTS

4. ROAD MAP TO ACHIEVE AND PROGRESS REVIEW

5. SELF AUDIT AND CLOSURE

6. CUSTOMER AUDIT AND CLOSURE

7. HMIL AUDIT AND SCORING

8. SUSTAINING