Professional Documents
Culture Documents
(QA/QC MEETING)
Meeting Attendees
OQ GEC Next Meeting Schedule
1. MURALI Vadlapatla - CSR 1. Abdul Jaleel - Manager (QA/QC)
2. Muraleedharan S - QA/QC lead (site base) 2. Vipin MP -Manager (QA/QC) Not attended
3. Praveen - QC Engineer (Pipeline) 3. Istiaq Ahmed - Welding Engineer
4. Shajan K - Sr. Engineer (QA/QC) - Pipeline Not attended
29-August-2022, 10.00 AM
5. Rajeev Thomas-Sr. Engineer (QA/QC) – E&P
6. Dipin - Sr. Engineer (QA/QC) - Piping
Distribution
Sl. Action required
Section Item Narrative
No Responsible Action Date Action
1 Quality Awareness session to be continued for project staff. QAQC Team Ongoing
Document /
2
Drawing Control
Dedicated Document Controller deployed to Sur.
Draft DDM prepared ad submitted for OQ review.
Request for EDMS to Document Controllers deployed at site
OQ advised Galfar to deploy a dedicated document controller to site. OQ enquired on individual is being taken up through the Project Manager. Discussed
reponsibility and the same was clarified by Galfar. OQ pointed out that with IM Lead of OQ for providing access. Password and user
4 (Galfar) Immediate
1. Requirement of DDM for having clarity in the distribution of document. name provided by OQ. Access to be provided by OQ.
2. Accessibility to the EDMS system to view the status of documents. Training to be provided to the Document Controller
deployed to site by the DC available at HO on receipt of
access. Access yet to be received. Galfar to send reminder to
OQ IM lead.
OQ also advised Galfar to submit the tentative mobilization for QA/QC resource in the project.
Galfar informed that QA/QC resources will be deployed based on the work progress. Galfar Quality
team will coordinate with Planning function to obtain the tentative schedule for start of activities at
site and will plan the mobilization accordingly. Draft mobilization plan to be provided to OQ.
Currently - QA/QC Manager, QA/QC Superintendent, Sr.
Galfar to plan in advance if the approved personnel are to be mobilized from outside Oman and to QA/QC Engineer (On Plot), Welding Engineers (Manual &
consider the visa process time and readiness etc. Automatic), Sr. Engineer (E&P), QC Inspectors (Pipeline) (2
nos), QC Inspector (Piping) (1 No.), QC Inspectors (Civil) -2
OQ asked Contractor to mobilize QA/QC Superintendent to site on priority basis as Pipeline activities Nos. and QC Inspector (Coating) (3nos) are already
Key personnel are progresssing ( Survey to Pipe stringing) at this stage as Senior Quality personnel is required at site deployed.
5 7 Galfar 19.04.22
mobilization for the dedicated control and coordination. Contractor can arrange accommodation as other
constuction personnel are mobilized and accommodated. Also OQ asked to mention the date of QA/QC Superintendent mobilized to site on 03.07.2022
mobilization. Sr. QA/QC ENgineer (GNH) mobilzed to site on 30.06.2022
Sr. QA/QC Engineer (Sur) mobilized to site on 28.07.2022
OQ asked the plan for the mobilization of QA/QC Manager of EPC contractor at site. GEC QCI instrumentation to be made available at site for FOC Duct
mentioned that their QA/QC Manager will be stationed at HO to coordinate in Enginneering, receiving inspection.
procurement and construction activities ate both GNH and Sur areas.
OQ advised that GEC's QA/QC Manager to do frequent site visit to SUR & GNH locations at
this time and to be stated/deployed at site once major Engineering phase done.
GNH Areas
OQ representative informed the Contractor that the Soil Testing is a Hold Point for Galfar and Galfar QA/QC Manager (Civil) has witnessed the testing that was
approved representative need to witness the testing at Third Party Lab. conducted this week. His CV to be submitted for OQ Approval
on 23.06.2022. Still pending approval.
Contractor informed that the testing will be witnessed by the QA/QC Manager (Civil) based at Head
Office. His CV will be submitted to OQ for review and approval. Mr. Joby has witnessed the testing of the soil sampled
Soil Testing &
6 8 Galfar 15.06.22 borrow pit 11.
MAS Approval
Contractor also informed that the information captured in the Quality Control Plan is having
ambiguities and Contractor will be revising the QCP to provide more clarity for the sampling and soil OQ raised concern over the delay in MAS approval of sand
testing. dune utilized at Sur (Hot tapping Pits padding). Galfar
informed that MAS is submitted to OQ for approval by
OQ stated that, at this stage Contractor has to follow the approved documents requirements. 04.08.2022. Approved by OQ in Code A with minor comments
OQ stated to `Galfar to compile the complete RCA report for the higher rate FDT failures at GNH areas
filling. The RCA report to prepared in project format and submit with document numbering.
Final RCA report submitted to OQ by 28.06.2022 (CGL48-
GEC-006060-0000-QA-RPT-0003-00 dt 28.06.2022)
Galfar shared a compiled data in excel sheet for OQ review.
OQ advised Contractor to deploy approved Quality Personnel to site witness the coating removal and MMEs being arranged for close out of the Observation.
AUT activity being carried out at Sur and GNH areas immediately.
Chemical analysis for all analysis Hot Tap locations at GNH and Sur- Metal shaving will be carried out by AUT Report has been submitted to OQ for review and
the NDT Subcontractor. Location identification shall be available in the report. approval.
OQ advised EPC contractor to prepare and verify all the dimensions in Hot tap locations. Ovality, straightness and roundness check carried out at
Coating Removal
both Sur and GNH and report submitted to OQ. Results
9 Activity at Sur 12 Galfar 09.06.22
OQ mentioned as per the project requirements, Pipe straightness and roundness to be checked at the fowarded to Vendor; confirmation/accepatance
and GNH
Hot tap locations and the details to be shared to MEC as well as Hot Tap vendor for their review and awaited.
confirmation.
Carbon equivalent analysis report received from NDE
OQ again mentioned the Hot tap/Tie-ins locations pipe straightness and roundness is very important Subcontractor (related to advance tie-in)
for the revoiew and conformation/acceptability from related parties ( MEC/Vendors) and to ensure the
propoer installation of Split Tee and Smart Plug for complete sealing. CE analysis, report submitted by Subcontractor commented
and returned to Subcontractor. Revised report received,
without stamp and signature from the Lab. Returned to sub-
contractor
OQ informed that the width of the trench obtained with trench operator is just adequate for the pipe Issue to be reviewed in coordination with Construction
to be lowered. This may have following adverse effect during the lowering operation: team.
- Pipes may hit against the trench wall during lowering - Can cause damage to coating
13 Trench Width 17 - Difficult to maintain the required gap between the pipe and trench wall. Galfar 22.06.2022 OQ advised Contractor to carryout a mock up lowering prior
to finalizing the process. Mock up carried out for the single
EPC contractor to ensure the required trench dimensions and smooth lowering of pipes ,pipeline pipe. OQ advised to keep this point open till completion of
section (s) without any damages to pipes as well as coatings. one section lowering successfully.
2). Engineering /OQ approvals on updated Typical drawings and related sketches/drawings proposals Deviation submitted for Plant Approval and Slump variation
of Wadi Crossings. as it is going to pumping. MAS for Mix Design submitted to
OQ. On approval of DVR and Mix Design, RFI for trial mix
will be raised. DVR for Plant approval obtained.GEC collected
the closed observaions from the plant (which were issued
during the last OQ audit on them). On approval of the DVR
pertaining to slump and MAS for Mix Design, new QC Plan
need to be prepared for the activity and submitted.
OQ highligthed that the Tie-In locations numbers identified in the drawings have changed. Initially the Galfar has written a mail to MEC on this regard for further
23 Hot Tap 29 Tie numbers were 16A & 16B and the Hot tap locations identified as 17A & 17B in Tie-in schedule Galfar Immediate clarifications and close. Clarification received, can be
document. OQ advised Contractor to obtain clarification the same removed
OQ advised Contractor to avoid IN cancellations as after IN raising, then at site related arrangements (
25 IN Cancellation 31 Galfar Info Noted: being monitored and advised site team accordingly
water etc.) are not available at site for execution of the works.