Sl Quantity Amount
no. Item A/C of Unit Rate Remarks
Previous Since Total Since Total
As shown in sheet 'Earth
1 Earth cutting cu ft 117960.022 11237.056 129197.078 5.00 56,185.00 645,985.39
excavation'
2 Daily labour for columns Eaichbee Enterprise Hrs 586.000 0.000 586.000 22.50 - 13,185.00
Note : We paid directly to Yusuf for PCC work(19.5Cum from Total work)
Earth Excavation
Total 31.5
Sl no. Date Item Weight (MT) Remarks
1 26.7.10 Cap lock & Bracing 1.240
2 28.7.10 Rod shifting 2.360
3 28.7.10 Cap lock & Bracing 4.950
4 29.7.11 Cap lock & Bracing 5.865
5 31.7.10 Cap lock & Bracing 4.760
6 1.8.10 Cap lock & Bracing 5.190
7 2.8.10 Rod shifting 2.000
8 12.8.10 Rod shifting 5.100
9 21.8.10 Rod shifting 11.290
10 27.8.10 Rod shifting 2.170
11 31.8.10 Cap lock & Bracing 5.350
12 13.9.10 Rod shifting 0.410
13 21.9.10 Rod shifting 7.400
14 26.9.10 Rod shifting 5.200
Total 63.285 MT
Sl Labour Rate Amount
no. Date Description of work (no) Each hrs. Total hrs (Rs.) (Rs.) A/C of Remarks
Eaichbee Enterprise
Sl Rate Amount
Date Description of work Unit Quantity Paid to A/C of Remarks
no. (Rs.) (Rs.)
1 9/2/2010 P. C. C. (M-10) cu m 6 220.00 1,320.00 Maa Laxmi Enterprise
2 26/2/2010 R. C. C. (M-30) cu m 168 50.00 8,400.00 Maa Laxmi Enterprise
Sarif Enterprise
Sanjay Shah
Sl Date Description of work Labour Each hrs. Total hrs Rate Amount Paid to A/C of Remarks
no. (no) (Rs.) (Rs.)
1 19/4/2010 Compresser 2.00 7.00 14.00 22.50 315.00 Maa Laxmi Enterprise
2 3/7/2010 Pump shifting 2.00 0.35 1.10 22.50 24.75
3 3/7/2010 Dewatering 4.00 2.30 10.00 22.50 225.00
4 14/7/10 Pump shifting 4.00 1.30 6.00 22.50 135.00
5 14/7/10 Bolder shifting 2.00 2.00 4.00 22.50 90.00
6 15/7/10 Dewatering 2.00 3.30 7.00 22.50 157.50
7 15/7/10 Bolder shifting 2.00 3.30 7.00 22.50 157.50
8 16/7/10 Dewatering 1.00 8.00 8.00 22.50 180.00
Sl Rate Amount
Date Description of work Unit Quantity Paid to A/C of Remarks
no. (Rs.) (Rs.)
1 - Pile Breaking R.M. 8.63 300.00 2,589.00 Maa Laxmi Enterprise
Sl Length Breath
no. Date Description of work (m) (m) Hight (m) Volume (cu m) Paid to A/C of Remarks
1 - Stand Road Side ( C ) 60.550 1.200 2.450 178.02 Maa Laxmi Enterprise
2 - Stand Road Side ( D ) 60.550 3.300 2.450 222.32 Maa Laxmi Enterprise
3 - Fairly Place Side ( C ) 58.345 1.200 2.450 171.53 Maa Laxmi Enterprise
4 - Fairly Place Side ( D ) 58.345 3.900 2.450 260.55 Maa Laxmi Enterprise
5 - North Side Pile ( C ) 58.620 2.500 3.200 468.96 Maa Laxmi Enterprise
6 - North Side Pile ( D ) 31.120 0.800 2.500 31.12 Maa Laxmi Enterprise
7 - Sump near Grid 3 3.000 3.000 1.200 10.80 Maa Laxmi Enterprise
Earth cutting in between
8 - Grid 3 - Grid 6 & Grid G - 24.300 1.000 0.300 7.29 Maa Laxmi Enterprise
Grid H
Total #VALUE! Cu m
#VALUE! Cu ft
S. B. Enterprise
Sl Length Breath
no. Date Description of work (m) (m) Hight (m) Volume (cu m) Paid to A/C of Remarks
1 - Stand Road Side ( A ) 60.550 8.000 1.250 605.500 Maa Laxmi Enterprise
2 - Stand Road Side ( B ) 60.550 2.635 1.260 100.516 Maa Laxmi Enterprise
Total 706.016 Cu m