Balance Work in 117

Villa Inner works


1. MEP (Must complete for staring next activity)
2. Water Proofing for bathrooms (4 days - our people, 2 days outside
people)
3. Ceramic & Marbles work ( 14 days (GF) + 8 Days (FF)-our people),(10 to
14 days outside peoples)
4. Painting works. (outside peoples)
5. Doors & Windows (outside peoples)
6. False ceiling (outside peoples)
7. Steel Dcor work (outside peoples)
Service Block & Majlis Inner works
1.MEP
2.Water proofing for bathrooms (2 days - our people, 1 days outside
people)
3.Cermaic finishing (7 days - our people, 3 days outside people)
4.Painting works (outside peoples)
5.Doors & Windows (outside peoples)
6.False ceining (outside peoples)
7.Kitchen cabinet (outside peoples)

Outside works
1.Water proofing and tiles works (around 22 days our people, 10 days out
side people)
2.Parapet dcor work s (14 days our people)
3.Man hole correction (MEP Contractor )
4. Boundry wall plaster (13 days - our labour , 7 days outside peoples)

5. Stone work (outside people)


6. Pasco work