Balance Work in 117
Outside works
1.Water proofing and tiles works (around 22 days our people, 10 days out
side people)
2.Parapet dcor work s (14 days our people)
3.Man hole correction (MEP Contractor )
4. Boundry wall plaster (13 days - our labour , 7 days outside peoples)