Professional Documents
Culture Documents
II. OBJECTIVES
The location of the building inspected is at Star St., Golden Country Homes
Subdivision, Alangilan Batangas. The building been inspected is a 4-storey
condominium with 24 units (6 units each floor) near BatStateU Main Campus II.
IV. DATE AND WEATHER OF INSPECTION
Dates of inspection were held last July 7, 11, 15, 20 and 25 of 2016 by the Civil
and Sanitary Engineering students of Batangas State University. The building was
inspected all with sunny weather at around 12 noon. This is to have a good and free
conversation with the laborers/ foreman/ engineer without bothering their work.
Regarding with the photos seen that the workers were working, those were taken
past 1pm and some were starting right away before 1pm. These were also
inspectors intention to capture how the workers work.
V. MATERIALS USED
Ground floor
Slab
Steel bars 12 mm
Lumber 2 x 2 lumber
Beam
Steel bars 16mm, 12 mm, 10 mm for ties
Lumber 2 x 2 lumber
Formworks marine plywood
Column
Steel bars 20 mm, 16mm, 10mm for ties
Lumber 2 x 2 lumber
Formworks - marine plywood
CHB
Size of outer wall 5
Size of division wall 4
Steel bars - 12 mm
Second floor
Slab
Steel bars 12 mm
Lumber -2 x 2 lumber
Formworks phenolic board
Beam
Steel bars -16mm, 12 mm, 10 mm for ties
Lumber -2 x 2 lumber
Formworks -marine plywood
Column
Steel bars 16 mm, 10 mm for ties
Lumber -2 x 2 lumber
Formworks - marine plywood
CHB
Size of outer wall 5
Size of division wall 4
Steel bars - 12 mm
Third floor
Slab
Steel bars -Steel bars 12 mm
Lumber -2 x 2 lumber
Formworks - phenolic board
Beam
Steel bars -16mm, 12 mm, 10 mm for ties
Lumber -2 x 2 lumber
Formworks marine plywood
Column
Steel bars -16 mm, 10 mm for ties
Lumber -2 x 2 lumber
Formworks -marine plywood
CHB
Size of outer wall 5
Size of division wall 4
Steel bars - 12 mm
Pipes
VII. MANPOWER
It is very natural that, the continual positive development of any business owe to
its effective planning. Making all the necessary preparations and appropriate
arrangements proactively basing upon what is expected to happen in future and
performing a series of tasks and activities accordingly in an organized, systematic
and capable way is one of the important functions of management, which needs
effective planning process. It is through the process of proper planning as well as
designing an effective organizational structure by assigning an assortment of
responsibilities to the concerned laborers may accomplish their set of objectives.
The concept of the right person should be placed at the right place and at the right
time is essentially important to a building construction as it includes a wide and
comprehensive range of activities in relation to "the management of man".
Manpower power planning focuses on the effective utilization of existing human
elements as well as fulfilling future needs of manpower in the organizations
whenever the situations necessitate. Man power planning is "the process of
determining manpower needs and the means and ways to meet those needs in
order to carry out the integrated plan of the organization." It is very much
indispensable for any organization to perform the activities efficiently and to produce
desired results.
In the on-going construction, there were 17 workers provided with different
activities depending on the need of the construction. Though the contractors are
stay-in, there were cases that someone needs to absent. The foreman has nothing
to do but split its job to still meet the right progress or have overtime.
The foreman in-charge was not only giving instructions to the workers, yet he
also works like one of them. The foreman and his workers scope of work were
mainly everything except on electrical works. The foreman stated that there was
other contractor assigned for electrical works. Most of the workers were stay-in
workers working 8 or 9 hours a day. Every Saturday and days with huge activities
like pump concreting, the Site Engineer was there for supervision and inspection of
the work progress. Instructions were given to the foreman by the Site Engineer, and
it was the foremans duty to inform it to other workers. The foreman is responsible
for reporting to the engineer whatever was done in the site.
Engr. Joey Bagos has the duty to check the materials required for the whole
week and orders it 3 days before it is needed to avoid delay. The engineer is also the
one who is in charge of giving what activity should be done in a week and the
foreman is responsible for giving those tasks to his workers. The construction
foreman is merely in charge of the man power scheduling and leveling.
In every business, either its construction or not are having problems. Some
problems are listed below.
From the first visit, the primary concerned problem was the safety. There
were hard hats but not worn, there were no safety shoes used, no hand
protection and eye and face protection as well for the laborers. They only
have hard hats just to comply the requirements needed. In addition,
ladders are unsafe to be used
Some materials used are not properly stored. Steel bars were exposed to
sunlight and rain which may affect its durability.
These contractors were not that strict regarding with the laborers
absences. Work production may be affected because of lack of workers in
each day.
IX. RECOMMENDATION
X. DOCUMENTARY PHOTOS
On-going construction
Use of Rope and Pulley to Lift Rebars Rebars Installed for Beam
Rebars fabrication for slab and beam Checking required materials to be ordered
TEAM SOLIDWORKS
ALANO, ALDIN Z.
CHAVEZ, MARIA NILEN D.
DELFIN, AIRA JOY S.
PALAS, ALYANNA KATE M.
August 1, 2016