MEETING ELECTRICAL STAFF

Present:
1.) RI
2.) ARI
3.) Sejahtera
4.) Bagus
Meeting started at around 10:00 AM; Venue: EA Conference Room
Matters Discuss:
Update of every Project being handled are the following:

a.) Usbekiestan RK 3 GPB 80 1 x 6 MW Basic Design Part 2 Ongoing


b.) Usbekiestan CHP GPB 180 1 x 16 MW Basic Design Part 2 Ongoing
c.) Sampoirna Kerawang MWM TCG 2020 V20 2 X 2