SCHEME OF EVALUATION
Subject: Electrical Design, Estimating and Costing
Subject Code: 10EE81
Course Instructor: Saranya.S
Chief Course Instructor: Reba kundu
Semester: Even (08)
Scheme

1. Explain the following

a) To determine the input power to motor – 2 marks


b) Input current of motor – 2 marks
c) Rating of cable – 2 marks
d) Rating of fuse - 2 marks
e) Size of conduit, distribution board, main switch & starter - 2 marks Total –
10 marks

2. Assumption – ½ marks
Wiring diagram – 2 marks
Calculation - 4 ½ marks
Estimation table - 3 marks Cost = RS.21100.00 Total 10 marks

3. Types of service line


Overhead line
a) High roof building - 2 marks
b) Low roof building -2 marks
c) Weather proof cable -2 marks
d) Joint box -2 marks
Underground line -2 marks Total 10 marks

4. Calculation – 4 marks
Estimation table - 6 marks cost = RS. 8200 Total 10 marks

5. Classification based on
a) Nature of duties
b) Service rendered
c) Operating voltage
d) Importance of place - 6 marks
Design basis
Indoor – 2 marks
Outdoor - 2 marks Total 10 marks

6. Calculation – 4 marks
estimation table – 6 marks cost = RS. 282000.00 Total 10 marks

CMR
INSTITUTE OF
TECHNOLOGY
Internal Assessment Test 2– Feb- May 2014

Sub: Electrical Design Estimating & Costing Code: 10EE81

Date: 15/ 04 / 14 Duration: 90 mins Max Marks: 50 Sem: 8th Branch: EEE

Note: ANSWER ANY FIVE OF THE FOLLOWING

1. Explain the following a) to determine the input power to motor b) input current of motor c)
rating of cable d) rating of fuse e) size of conduit, distribution board, main switch & starter? ( 10
Marks)
2. A 10 hp motor, 415V, 3- phase, 50 HZ, induction motor is to be installed in a workshop, the plan
of which is shown in figure 1. Show the layout of the wiring and estimate the quantity of
material required and give its approximate cost. The wiring is to be surface conduit.(10
Marks)prepare a list of material and estimate the cost
3. Explain different method of installation of service line with neat sketch? ( 10 Marks)
4. Prepare a list of material and estimate the cost for providing service connection to a single
storey building at 240V single phase 50 HZ having a light and fan load of 5 KW. the supply is to
be given from an overhead line 20 M away from the building ( 10 Marks )
5. Explain about different type of sub – station ( 10 Marks )
6. Electric supply to a factory is taken from an 11kv overhead , 3 – phase line , which terminates at
2 – pole ( iron pole) structure at a distance of 20M from the main board of the factory , the
supply is to be given through a 11,000 V / 433 V , 3 – phase transformer and the factory has a
load of 80 KVA . explain the quantity of material required and the total cost(10 M arks )