PT.

PRIMA PANEL LESTARI

WORK SCHEDULE

NO DESCRIPTION N O V E M B E R 2 0 0 5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

1 Persiapan Opening Office / Factory X X


2 Staff Adm Baru X
3 Pembuatan Form-2 ADM Y Y Y
4 Pembuatan Stempel , Name Card Y Y Y
5 Finishing Sample LIGNA Jk Jk
6 Penyerahan Sample ke LIGNA Y/D
7 Tanda tangan Kontrak dg LIGNA D
8 Evaluasi Sample / Revisi Jk Jk Jk
9 Penyerahan Revisi Sample ke LIGNA Y/D
10 Cek & Booking Raw Material Y
11 Pembuatan Meja Q/C Jk Jk
12 Ke NOTARIS A/D
13 Buat Daftar Harga & Data Supplier Y Y
14 Follow up Delivery Mesin D
15 Instalasi Genset X X X X X X X
16 Trial Mesin -Mesin X X
17 Masuk SDM Baru (Operator) X X
18 Estimasi PO dari LIGNA X
19 Order Raw Material ( P/B ) Y Y Y Y
20 Order Fitting / Assecories Y Y Y Y
21 Order Supercon Silver Y Y Y Y
22 Order Carton Box Y Y Y Y
23 Order Supercon 4244 dari LIGNA Y Y Y Y
24 Start & Running Production X X X X