Dipleg Bending Reworks Schedule

D-1503 2nd.Rg. / Cyclone Period : 2020.09.14.~2020.09. 2020.09.14. Rev.0

Volumn Sep.2020.
No Description Remarks
Q'ty Unit 14 15 16 17 18 19 20 21 22 23 24 25 26

1 Trickle V/V Removal (Grinding) 3 Sets F,G,H Cutting

2 Dipleg Cutting Point Marking 6 Points

●Top Side "2"Point (0°/90°) Plumbing check 3 Points

●Initial bending point marking 3 Points

●Dipleg Middle point marking 3 Points

3 Lifting H-Beam Top side setting 1 Set

●Chain block Setting (3Ton) 1 EA

4 Scaffold Modification (Removal) 1 Lot

●Bottom~Top side(EL.+41,530~EL.+52,000) 11 m

5 Dipleg Cutting (Grinding) 3 Points

●8" X Sch.80(12.7t) - 4.5m 6 Points

●Lug ring removal (Grinding cutting) 6 Sets

6 Removal the Dipleg outside of the manhole 16 Sets

●Lifting down (Using a Chain block) 8 Sets

7 Dipleg Cutting point beveling 18 Points

8 Pad bracket Fit-up & welding ("E") 4 Points

9 Dipleg lug ring Fit-up & welding ("E") 2 Points

10 Brace connecting & Fit-up,welding ("E") 4 Points

11 Dipleg Bending- Mechanical Rework 6 pcs By-Other company

Re-installation work
12 Scaffold Modification (Removal) 1 Lot D+1 1Day

13 Putting a Dipleg into a manhole 6 pcs D+3 2Day

●Lifting up (Using a Chain block)


14 Dipleg pipe Fit-up 6 Points D+5 1Day

●Dipleg beveling PT check

●Inside argon purge preparation


15 Fit-up Inspection 1 Lot D+6 1Day

16 Dipleg pipe Field welding 6 Points D+8 2Day

●Root pass - PT check

17 Welding point NDE (PAUT) Inspection 6 Points D+9 1Day

18 Dipleg lug ring Fit-up 6 Sets D+10 1Day

19 Pad bracket Fit-up 12 Sets D+12 2Day

20 Brace connecting & Fit-up 12 Sets D+13 1Day

21 Brace Fit-up Inspection 12 Sets D+14 1Day

22 Pad Bracket welding (19tX400X400) 12 Sets D+16 2Day

23 Lug ring welding (16tXØ228X232H) 6 Sets D+17

24 Brace connect welding (20tX200) 24 Points D+18 1Day

25 Welding point NDE(P.T) Inspection 1 Lot

26 Trickle V/V Fit-up 3 Points D+19 1Day

27 Trickle V/V Fit-up Inspection 3 Points

28 Trickle V/V welding 3 Points D+20 1Day

●Root pass - PT check 3 Points

29 Welding point NDE (PAUT) Inspection 3 Points D+21 1Day

30 Pad Area "V-Anchor welding 1 Lot By-OGS

31 Pad Area Refractory 16 Points By-POSCO