RE: BILL OF MATERIALS AND ESTIMATE OF

COST
NAME OF PROJECT: CONSTRUCTION OF EVACUATION CENTER PHASE-1

SCOPE OF WORKS:

1. SITE WORKS
1.1. EXCAVATION = 13.824 CU.M.

2. CONCRETE WORKS
2.1. CONCRETE FOOTING 9 SETS(L=1.2M;W=1.2M;T=0.30M)
2.2. CONCRETE COLUMN 9 SETSL=0.30M;W=0.30M;H=5.2m)
2.3. CONCRETE BEAM 4 SETS(L=10M;W=0.20M;T=0.30M)

3. STEEL WORKS
4. FORMWORKS AND SCAFFOLDINGS

LOCATION: BRGY.STA. LUCIA ,ABUYOG,LEYTE

APPROPRIATION: Php.350,000.00

SOURCE OF FUND: BRGY. IRA

Prepared by: CHECKED BY:

RAYMAR AGAPOY DOMINIQUE EVAN


COBILO
Brgy. Kagawad Infra Civil
Engineer

Recommending Approval:

LORENA REMANDABAN
Brgy. Chairman

Approved by:

AUXILIO C. RECAMADAS
Municipal Engineer