CIN: L99999MH1946PLC004768

Ref: L&T/Allahabad/NHAI/2016-05
Dated: 16/12/2016

To
The Project Director,
National Highway Authority of India,
PIU-Allahabad & PIU-Naini Bridge
18-C/28-A, Sarojini Naidu Marg,
Near A.G Office, Civil Lines, Allahabad-211001
Dear Sir,

Sub - Allahabad Bypass Project-Construction of bridge across River


Ganga- Construction Package ABP-1-Release of L&Ts Bond and BG

Ref: 11015/NHAI/ABP-1/Settlement/PIU/Alld/19231
Egis India/HO/ABP-1/28859/2016
UQ/NHAI/OMT/ABP/633

Dear Sir,
This is with ref. to your letter no. 11015/NHAI/ABP-
1/Settlement/PIU/Alld/19231 dated 29 th November 2016,on the above
subject. The differential settlement with reference to the observation
taken on 23/9/2009 and 12/4/2011 along with the latest reading taken
jointly on 5-6 Sept,16 which was submitted by L&T clearly show that
there is a continuous increase in the P8(LCW) reading from 82 mm to 114
mm which needs to be monitored on regular basis along with the adjacent
wells P6 and P7.