You are on page 1of 58

Preparation of Detailed Project Report (DPR)

Presentation on
Preparation of Detailed Project Report (DPR) for Road Projects
By

Rathnakara Reddy KB
Managing Director

Infra Support Engineering Consultants Pvt. Ltd.


Bangalore
rathnakarareddy@infrasupport.in
www.infrasupport.in

May 14, 2012, Bangalore


Preparation of Detailed Project Report (DPR)

Preparation of DPR involves following components

1.0 Understanding Scope of Work


2.0 Traffic Surveys
3.0 Engineering Investigations
4.0 Detailed Designs
5.0 Tender and Construction Drawings
6.0 Project Costing
7.0 Economic Analysis
8.0 Formulation of Construction Packages
9.0 Compiling Project Report
Preparation of Detailed Project Report (DPR)
Scope of Services
UNDERSTANDING THE TOR
First and foremost thing is to study carefully and understand the Terms of
Reference (ToR) or Scope of Services of the project.
Once the ToR is understood, the conceptualization of the project would be
easy.
Mostly the ToR for a particular type of projects remains same across any
organization.
Duration of the Project, Phases (Feasibility, PPR, DPR) and Reporting requirements
Proposals for improvements, if any, (type of cross section, grade separators, major
Bridges, Bypasses etc.)
Any special types of Surveys and project specific considerations
Requirements for Economic and Financial Analysis,
Issues on Right of Way (RoW) and Land Acquisition
Social and Environmental surveys
Preparation of Detailed Project Report (DPR)

SURVEYS AND INVESTIGATIONS

1. Reconnaissance Survey
2. Traffic Surveys
3. Topographic Surveys
4. Engineering Surveys
5. Soil & Material Investigations
6. Social And Environmental Surveys
Preparation of Detailed Project Report (DPR)

Traffic Surveys
The initial task of identifying the homogeneous traffic links shall be undertaken on
the identified road sections
homogeneous traffic links will be established through identification of the major
intersections and urban centres.
The fixation of locations will be made for traffic volume surveys, both at mid
sections and intersections

Traffic Volume Surveys


O-D And Commodity Surveys
Turning Movement Surveys
Parking Surveys
Speed And Delay Surveys
Cross Pedestrian And Animal Surveys
Axle Load Surveys
Truck Terminal Surveys
Willingness to pay Surveys
Preparation of Detailed Project Report (DPR)
Traffic Volume Count Survey Formats
Preparation of Detailed Project Report (DPR)
Traffic Volume Count Survey Formats
Preparation of Detailed Project Report (DPR)
Preparation of Detailed Project Report (DPR)
Preparation of Detailed Project Report (DPR)

TRFFIC FORECASTING
Traffic volume count survey gives ADT
ADT is to be converted to AADT based on seasonal variation factors
seasonal variation factors can be obtained by fuel consumption rates or past trafic
data
AADT thus obtained shall be used as base year traffic
Traffic is to be forecasted for at least next 10 years
Traffic Growth rates can be obtained using
Trend Analysis
Econometric Model

A more rational method will be to establish a relationship between the socio-


economic variables such as Population, Net State Domestic Product (NSDP)
and Per-Capita Income (PCI) on the one hand and the past registration data of
different categories of vehicles on the other to determine the elasticity of
transport demand with respect to different categories of vehicles. According to
IRC: 108 - 1996, an econometric model should be derived
Preparation of Detailed Project Report (DPR)

Axle Load Surveys


Traffic loading has a significant impact on pavement performance and design.
damage that vehicles create to a road depends very strongly on the axle loads of the
vehicles.
The exact relationship is influenced by the type of road structure and the way the
road deteriorates but a `fourth power damage law gives a good approximation.

Measurements will be made for two days over a 24-hour period on random sampling basis.
analyse the axle load survey data to bring out the Gross Vehicle Weight (GVW) and Single Axle Load
(SAL) distributions by truck type and axle configuration.
Preparation of Detailed Project Report (DPR)
Preparation of Detailed Project Report (DPR)

AXLE LOAD SURVEY CALCULATIONS

Date &
Section : 31/01/2011
Time

Location :
Chainage :

Type : 2 -
Direction :
Axle

Wheel Load (Tonnes)


ESWL Individual VDF
Direction Type* Axle VDF

1st 2nd 3rd 4th 5th FW RW FW RW


DIR_01 2 1.9 1.75 0 0 0 0.4657 0.4289 0.05 0.03 0.08
DIR_01 2 1.8 4 0 0 0 0.4412 0.9804 0.04 0.92 0.96
DIR_01 2 2.6 6 0 0 0 0.6373 1.4706 0.16 4.68 4.84
DIR_01 2 2.2 1.95 0 0 0 0.5392 0.4779 0.08 0.05 0.14
DIR_01 2 1.8 1.5 0 0 0 0.4412 0.3676 0.04 0.02 0.06
DIR_01 2 1.8 4 0 0 0 0.4412 0.9804 0.04 0.92 0.96
DIR_01 2 1.8 2 0 0 0 0.4412 0.4902 0.04 0.06 0.10
Preparation of Detailed Project Report (DPR)
Multi Axle Vehicle
Wheel Load (Tonnes)
ESWL Individual VDF
Direction Type* Axle VDF

1st 2nd 3rd 4th 5th 6th FW RW1 RW2 RW3 FW RW1 RW2 RW3

DIR_01 4 2.2 1.9 1.45 1.6 0 0 0.539 0.466 0.408 0.000 0.085 0.047 0.028 0.000 0.16

DIR_01 4 2.9 5.7 6.3 4.2 0 0 0.711 1.397 1.403 0.000 0.255 3.809 3.875 0.000 7.94

DIR_01 4 1.7 2.95 4.1 4.9 0 0 0.417 0.723 1.203 0.000 0.030 0.273 2.091 0.000 2.39

DIR_01 4 1.8 4.75 5.1 5.15 0 0 0.441 1.164 1.370 0.000 0.038 1.837 3.519 0.000 5.39

DIR_01 4 2.3 1.8 1.45 1.5 0 0 0.564 0.441 0.394 0.000 0.101 0.038 0.024 0.000 0.16

DIR_01 4 2.15 4.35 1.55 3.65 0 0 0.527 1.066 0.695 0.000 0.077 1.292 0.233 0.000 1.60

DIR_01 4 1.9 4.5 5.6 4.55 0 0 0.466 1.103 1.356 0.000 0.047 1.480 3.383 0.000 4.91

DIR_01 4 3 5.2 5.6 4.5 0 0 0.735 1.275 1.350 0.000 0.292 2.639 3.317 0.000 6.25

DIR_01 4 2.1 6.2 6.45 6.85 0 0 0.515 1.520 1.777 0.000 0.070 5.332 9.974 0.000 15.38

DIR_01 4 2.5 3.2 5.6 5 0 0 0.613 0.784 1.416 0.000 0.141 0.378 4.024 0.000 4.54

DIR_01 4 2.8 5.65 6.2 4.2 0 0 0.686 1.385 1.390 0.000 0.222 3.678 3.729 0.000 7.63

DIR_01 4 2.8 4 5.5 4 0 0 0.686 0.980 1.269 0.000 0.222 0.924 2.596 0.000 3.74

DIR_01 4 2.1 4.5 2.05 3.6 0 0 0.515 1.103 0.755 0.000 0.070 1.480 0.325 0.000 1.87
Preparation of Detailed Project Report (DPR)

VDF CALCULATIONS

Vehicle VDF
Type LHS RHS AVG
LCV 0.08 0.13 0.10
2 Axle 2.90 1.10 2.00
3 Axle 4.85 3.24 4.04
MA 7.27 9.89 8.58
Preparation of Detailed Project Report (DPR)

Engineering Surveys And Investigation


Road Inventory Survey
Inventory And Condition Assessment Of Existing Cross Drainage
Structures
Preparation Of Strip Plan
Assess Adequacy Of Drainage
Pavement Condition Survey
Pavement Roughness Survey
Pavement Composition Survey
Benkelman Beam Deflection (Bbd) Survey
Preparation of Detailed Project Report (DPR)

Road Inventory Survey


The Road Inventory survey consists of recording the physical features along and
across the project road in a prescribed format.
Average width of pavement, shoulders and formation
Surface type of carriageway and shoulders
Right of Way (ROW)
Average embankment, height, type and condition
Location of major Bridges, RoBs, Flyovers.
Type and location of Side Drains
Road Side Land Use
Utility lines and trees within the boundaries
Location and Condition of Traffic Sign Boards
Location of Bus stops, Parking areas and other amenities
Location of Major industries and business centers
Location and details of cross roads
Sight distance details
Perched water table, HFL, Depth of submergence the road is subject to
Areas subject to chronic flooding and submergence
Recording urban and Rural areas, name of places and settlements
Preparation of Detailed Project Report (DPR)
ROAD INVENTORY SURVEY
Name of the road: Date:
Direction:

Chainage(k
m) Carriageway Shoulder Width(M) Ht. Of Fill/cut (m) Geometrics
extent of
Width Terrai slope Land Soil Enroute Draina
From To (M) Type Left Right Type n type Left Right erosion use type Horizontal Vertical Major Jn. villages ge Remarks

Silty-
0 1 3.75 SDBC 1.7P,1.1E 1.1B Plain 2 - No Erosion Agricultural Clay LC - SH - OK

Silty-
1 2 3.75 SDBC 1.0B,1.0E 1.0B,1.0E Plain 1.5 1.5 No Erosion Agricultural Clay valley - OK

Silty-
2 2.5 3.75 SDBC 1.0B,1.0E 1.0B,1.0E Plain 1.5 No Erosion Industrial Clay SC - - OK

Silty-
2.5 3 3.75 SDBC 1.0B,1.0E 1.0B,1.0E Plain 1.3 1.5 No Erosion Agricultural Clay - ABC OK

Silty-
3 3.2 3.75 SDBC 1.0B,1.0E 1.0B,1.0E Plain 1.2 1.3 No Erosion Agricultural Clay Poor
Preparation of Detailed Project Report (DPR)

Inventory and Condition Assessment of Existing Cross Drainage Structures


The location of each bridge and culvert shall be recorded, along with its type and
the carriageway width.
A detailed inspection of bridges and culverts shall be carried out to assess their
condition. This would lead to a report preparation on condition of bridges and
structures.
The structures, which show deficiency in terms of capacity and strength, shall be
reviewed in the light of repair/rehabilitation possibilities with suitable
recommendations.
Preparation of Detailed Project Report (DPR)

INVENTORY AND CONDITION SURVEY OF CULVERTS

HFL from Superstructure Substructure / Wing Wall / Return General


Total Road Flow Foundation Railing / Parapet
Structu Span Opening Bed / Pipe Headwall Wall Condition
CH Width Level from Directi
re No. (m) Height (m) Local
(m) Bed (m) on
Enquiry Type Material Type Material Type Material Details Condition Details Condition
Preparation of Detailed Project Report (DPR)

Assess Adequacy of Drainage


Inadequacy of drainage reflects in terms of fast deterioration of the pavement as
well as causes inconvenience to the traffic,
General condition of drainage
Connectivity of drainage turnouts en-route into the network topography
Condition in cut sections
Condition at embankments
Preparation of Detailed Project Report (DPR)
Preparation of Detailed Project Report (DPR)

Pavement Condition Survey


Detailed field studies shall be carried out to assess the adequacy and effectiveness
of the existing pavement. The data Shall generally cover
Pavement condition (surface distress type and extent)
Shoulder condition
Embankment condition
Drainage condition
Preparation of Detailed Project Report (DPR)
PAVEMENT CONDITION SURVEY
Name of Road: Date:
Direction:
Chainage(KM) Cracking % area Edge Unpaved Shoulder
Narrow Wide Potholes Patching Ravelling Break Dropoff Depressio Material
From To <3mm >3mm Area% Area% Area% %length (mm) n(mm) loss(M^3) Remarks
Preparation of Detailed Project Report (DPR)
Preparation of Detailed Project Report (DPR)

Pavement Roughness Survey


Roughness is a critical attribute for modeling the economic variables of investment.
The roughness is measured in International Roughness Index (IRI), the unit of IRI
is m/km.
The roughness surveys shall be conducted using a fifth wheel Bump Integrator
(preferably vehicle equipped with ROMDAS).
The test vehicle shall be run on the wheel path on both the directions preferably
three times and the average result is reported as the IRI.

Kilometerwise IRI

8.00
7.00
6.00
5.00
IRI

4.00
3.00
2.00
1.00
0.00
52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 124 128 132 136 140 144 148
Chainage
Preparation of Detailed Project Report (DPR)

Summary
Chainage Section
Percentage distribution of IRI Avg.
Roughness (IRI)
Roughness
From To
IRI 2.5-5
(IRI)
IRI >=10
7% 0%
IRI 5-8 1 2 4.5
45%
2 3 5.14
IRI 8-10
..
48%
3 4 4.08

4 5 5.26

Percentage Distribution of IRI


Preparation of Detailed Project Report (DPR)

Pavement Composition Survey


To know the pavement composition and to collect the soil samples for testing, trial
pits of size 1m x 1m shall be made at the interface of pavement with shoulders
according to the following procedure:
Mark the location of the pit-half on the pavement and balance on the shoulders.
Dismantle the marked area to full depth of pavement.
Ascertain the pavement composition
Preparation of Detailed Project Report (DPR)

Summary of Pavement Composition Data

Thickness in MM
Total Thickness
Chainage Direction Testpit No Sand
BT WBM GSB Subgrade (MM)
Filling

0+250 UP UP-TP-1 20 225 150 - 300 395

1+500 UP UP-TP-2 25 225 150 100 - 400

2+000 DN UP-TPC-1

2+500 DN UP-TP-3

3+000 UP UP-TP-4

3+500 DN UP-TPC-2

4+000 UP UP-TP-5

4+500 DN UP-TP-6

5+000 UP UP-TPC-3

5+500 DN UP-TP-7
Preparation of Detailed Project Report (DPR)

Benkelman Beam Deflection (BBD) Survey


The procedure for carrying out BBD survey shall be in conformity with IRC:81-
1997. Deflections are measured at 50m intervals staggered on both directions of
traffic and then apply the method of cumulative differences to divide the sections
for arriving at the characteristic deflections.
Traffic regulation arrangement during carrying out Benkelman Beam Deflection surveys shall be as
follows
Cordon the area with suitably spaced cones and provide temporary traffic signs.
Carryout the Benkelman Beam survey work.
Shift the cones and temporary signs to next location.
Preparation of Detailed Project Report (DPR)
Preparation of Detailed Project Report (DPR)

Characteri
Seasona Mean
Standard stic
Dial Gauge Reading Calculation of Deflections l Deflecti
Correct Deviation Deflectio
Pavem Temp. Field Correcti on /km
Subgra ed n
Station ent Correcti Moistur on
Appare de PI Deflecti
Beam True Temp. on e Factor,
Intermedi Differenc nt on
Initial Final Correcti Deflecti As Per m d Dc=m+2d
ate e Deflecti
on on IRC 81:
on
1997
(km) (Div) (Div) (Div) (mm) (mm) (mm) (mm) (OC) (mm) (%) (%) (mm) (mm) (mm) (mm)
0.000 18.98 18.82 18.81 0.01 0.34 0.00 0.34 17 0.18 8.0 7.1 1.39 0.72
0.100 16.45 16.3 16.29 0.01 0.32 0.00 0.32 17 0.18 8.0 7.1 1.39 0.70
0.200 19.57 19.5 19.5 0.00 0.14 0.00 0.14 17 0.18 8.0 7.1 1.39 0.44
0.300 17.55 17.42 17.41 0.01 0.28 0.00 0.28 17 0.18 8.0 7.1 1.39 0.64
0.400 19.29 19.17 19.16 0.01 0.26 0.00 0.26 17 0.18 8.0 7.1 1.39 0.61
0.500 18.11 18.03 18.01 0.02 0.20 0.00 0.20 17 0.18 8.0 7.1 1.39 0.53 0.62 0.10 0.83
0.600 17.66 17.52 17.52 0.00 0.28 0.00 0.28 17 0.18 8.0 7.1 1.39 0.64
0.700 15.92 15.84 15.83 0.01 0.18 0.00 0.18 17 0.18 8.0 7.1 1.39 0.50
0.800 19.72 19.57 19.56 0.01 0.32 0.00 0.32 17 0.18 8.0 7.1 1.39 0.70
0.900 16.98 16.82 16.8 0.02 0.36 0.00 0.36 17 0.18 8.0 7.1 1.39 0.75
1.000 18.56 18.37 18.36 0.01 0.40 0.00 0.40 17 0.18 8.0 7.1 1.39 0.81
Preparation of Detailed Project Report (DPR)

The summary of Benkelman Beam Deflection data is as follows


Preparation of Detailed Project Report (DPR)

Material Investigations

Existing Sub-Grade And Embankment Soils


Construction Materials Investigation
Borrow Areas
Quarries For Aggregates
Quarries For Sand
Sources For Other Construction Materials
Preparation of Detailed Project Report (DPR)

Material Investigations
Material investigation aims at collecting all material samples that is being used
under the present road and anticipated borrow material and subject to standard
testing procedure to recommend most appropriate designs
Soil sampling, field density tests and laboratory tests on existing sub-grade and soil sampling of
embankment soils.
Investigating borrow materials for embankment, sub-grade and granular sub-base.
Investigating aggregate and sand quarries
Locating water sources for construction work
Identifying sources for other construction material such as cement, bitumen and steel.
Samples of borrow soils, sand, crushed rock and gravel for use in embankment, and pavement
structure.
Preparation of Detailed Project Report (DPR)
Material Quarry Map
Preparation of Detailed Project Report (DPR)

Subgrade Soil Samples


The tests being performed are
Grain size distribution test for each sample,
Atterberg limits for each sample,
Moisture density relationship (Heavy Compaction) for each sample,
Unsoaked CBR tests at optimum moisture content at three energy levels.
Four days soaked CBR at three energy levels on each homogenous group of soils. Soaked CBR at
FDD and 97% of the MDD is to be determined from the graphs plotted for CBR vs Density at three
energy levels.
Preparation of Detailed Project Report (DPR)

Testing Codes Adopted


Type of Test Method
Field dry density using sand replacement IS 2720 Part 28
method
Field dry density using core cutter method IS 2720 Part 29
Moisture content determination IS 2720 Part 2 (section I)
Atterberg limits IS 2720 Part 5
Sieve analysis
- natural soils IS 2720 Part 4
- rock aggregate IS 2386 Part 1
Compaction test (Heavy Compaction) IS 2720 Part 8
CBR and Swell
(Soaked and unsoaked at three energy IS 2720 Part 16
levels for sub-grade)
Aggregate impact value IS 2386 Part 4
Coating and stripping of Bitumen aggregate
IS 6241
mixtures
Soundness of Aggregates IS 2386 Part 5
Flakiness and Elongation Index IS 2386 Part 1
Water Absorption and Specific Gravity of
IS 2386 Part 3
aggregate
Stone Polishing Value BS 812 Part 114
10 % Fines Value for Aggregate BS 812 Part 111
Preparation of Detailed Project Report (DPR)

Topographic Surveys
Topographical survey is the backbone of detailed engineering design.
Accuracy of the information collected during this survey has direct bearing on
almost all the design activities involved in project preparation.
The beginning of topographical surveys is made with collection of preliminary
information of latitude and longitude of the region as well as approximate reduced
level above mean sea from Survey of India maps available in the region

Setting up permanent bench marks and control stations to be used during construction
Establishment of horizontal control with GPS to have unique coordinate system of northing and
easting along the project corridor
Establishment of vertical control to have the elevation coordinate hooked to nearest GTS stations
along the project corridor
Collection of Digital Terrain Model data containing the existing highway, rivers, streams and other
topographical features to form the basis for the new designs;
Preparation of base plans containing the entire natural and man made features like buildings, fences,
walls, utilities, temples and other religious structures etc. that would govern the finalisation of
horizontal alignment.
Preparation of Detailed Project Report (DPR)

Coding for various types of features is comprised of four characters.


The first two characters describe the type of feature and the last two characters
indicate the string number.
The string number i.e. the last two characters are alphanumeric, such as, A1-A9, BO-
B9.......... ZO- Z9, AA-AZ, BA-BZ, ... ZA- ZZ.

CLV01 CLV01

X
X
EPL01 CLV01 EPL01
CLV01

X
X
X X
EPR01 CLV02 CLV02 EPR01

X
X

CLV02 CLV02

BG01 BG01 BG02 BG02

BG01 BG01 BG02


BG02
Preparation of Detailed Project Report (DPR)

Cross Sections

With a view to obtain an accurate surface cross section on the pavement


shall be collected at 25 m intervals at the tangent sections and 10-25m in
curve sections.
The cross-sections levels were taken on the embankment profile or ground
as necessary to define ground profile, properly.

Center line of carriageway (Code CC**);


Edge of carriageway (Code CE**);
Paved shoulder (Code SH**). This is where the seal has been extended past the
normal edge of the road to include a part of the shoulder;
Edge of shoulder (Code SS**); Where ** indicates left or right string
Point on undisturbed original ground level (OG);
Point on partially or completely filled surface of the top of embankment/ formation
(ET**)
Point on bottom of embankment (EB**); Where ** indicates left or right string
Preparation of Detailed Project Report (DPR)

Cross Section of Road in Topographic Survey


Preparation of Detailed Project Report (DPR)
4.0 DETAILED ENGINEERING DESIGN
4.1 Engineering Design
4.1.1 Highway Geometric Design
4.1.2 Design Of Built-up Areas
4.1.3 Design Of Pavement And Shoulders
4.1.4 Overlay Design
4.1.5 Design Of Service Road And Bypass
4.1.6 Design Of Embankments
4.1.7 Design Of Roadside Drainage
4.1.8 Detailed Design Of Bridges/Structures
4.1.9 Design Of Arboricultural And Landscaping
4.1.10 Design Of Intersection And Interchange
4.1.11 Design Of Traffic Safety Features, Road Furniture And Road Markings
4.1.13 Weighing Station, Parking Areas And Rest Areas
4.1.14 Design Of Wayside Amenities
4.1.15 Design Of Communication System
4.1.16 Design Of Bus-Bays And Lay-By
4.1.17 Design Of Miscellaneous Items
Preparation of Detailed Project Report (DPR)
5.1 Project Costing
5.1.1 Finalisation Of Unit Rates
4.1.2 Preliminary Estimate Of Quantities
4.1.3 Preliminary Costing
5.2 Economic Analysis
5.2.1 Construction/Improvement Cost
5.2.2 Vehicle Operating Costs And Time Costs
5.2.3 Accident Costs
5.2.4 Social And Environmental Costs
5.2.5 Estimation Of Project Benefits
5.2.6 Economic Analysis By Section
5.2.7 Finalisation Of Improvement Option
5.3 Financial Analysis
5.3.1 Determination Of Toll Rates
5.3.2 Compilation Of Project Costs
5.3.3 Identification Of Preliminary Project Revenue Stream
5.3.4 Financial Analysis
5.4 Formulation Of Construction Packages
5.5 Submission Of Project Report
Preparation of Detailed Project Report (DPR)

Highway Geometric Design


Horizontal Alignment: The proposed centerline shall be finalised using a
sophisticated highway design software, All the curves having poor geometry shall
be improved to the acceptable design standards
Preparation of Detailed Project Report (DPR)

Vertical Profile: The existing longitudinal section of the project road shall be
obtained from modeling the ground data. The finished profile shall depend on the
thickness of the pavement layer determined from pavement design provision for
necessary profile corrective and camber corrective course.
Avoid cutting/scraping of existing pavement at strengthening only sections
Compatibility of design speed to horizontal geometry of the section
Provide adequate vertical curve at the grade change from stopping sight distance criterion.
Preparation of Detailed Project Report (DPR)

Cross Section: The proposed cross sections are broadly composed of carriageway,
medians, raised footpath, hard shoulders, earth shoulder and drainage provisions.
While running cross-sections care shall be taken in applying appropriate super
elevation parameters, strengthening & widening, and improvement options based
on rural, built-up etc.

The earthwork in cutting and filling shall be obtained form the software directly at a
specified interval along with Mass haul diagram.
Preparation of Detailed Project Report (DPR)
Preparation of Detailed Project Report (DPR)
Preparation of Detailed Project Report (DPR)

Design of Built-upAreas
This activity shall focus on design of urban areas in the form of parking lane,
service road, sidewalk and roadside drainage underneath the sidewalk etc. All these
details shall be clearly shown in the horizontal plan and also typical cross sections
shall be prepared.
Design of Pavement and Shoulders
Overlay Design
The performance of pavement in terms of functional performance, structural
performance, structural capacity, and safety contribute to the need for an overlay.
Functional performance refers to the ability of the pavement surface to provide a
reasonable riding quality measured in terms of roughness.
Structural performance is the ability to retain the integrity of the pavement by
preventing distress in the form of cracks, ruts, potholes, etc.
Structural capacity is the pavement's ability to accommodate the axle load on the
pavement. Safety aspect refers mainly the skid resistance and hydroplaning
potential.
Preparation of Detailed Project Report (DPR)

Design of Service Road and Bypass


This activity shall focus on design of service road and bypass in terms of number of
lanes and pavement composition.
The local traffic component shall be segregated and would determine the number of
lanes to be provided in the service road. Depending on this traffic loading and soil
investigation already carried out, the pavement composition shall be decided.
Design of Embankments
The embankments would be designed after detailed analysis and as per the relevent
standards and latest software available. General design parameters shall follow IRC
guidelines.
Design of Roadside Drainage
Drainage is an important aspect in the design of highway. With poor drainage
conditions the pavement will not sustain till the end of design life.
Design of kutcha drain on both sides near RoW limits in rural sections
Covered pucca drains near urban areas if necessary
Design of chutes in high embankment areas for drainage of surface water
In super elevation sections median drains shall be provided
As a slope protection measure for high embankment section, turfing on slopes or pitching shall be
designed as per the design standards.
Preparation of Detailed Project Report (DPR)

Detailed Design of Bridges/Structures


Based on the detailed survey, sub-surface investigation and design standards and
specifications developed bridge/structures shall be designed.
General design parameters and loadings shall follow IRC guidelines, amended
when necessary in consultation with client.
In selecting foundation type, the consultant shall also take into account the time
required for construction of alternatives, and give preference to those which
minimise construction time.
In developing the standard designs and for those designs, which cannot be
standardized, computer programs for design and drawing shall be used extensively.
On the basis of the investigation and design standards, detailed designs for minor
bridges and culverts shall be prepared.
Design of Arboricultural and Landscaping
Appropriate plans shall be developed for planting of trees, horticulture and
floriculture on the unused land of the RoW in order to beautify the project corridor
view and improve the overall aesthetics.
Preparation of Detailed Project Report (DPR)

Design of Intersection and Interchange


To avoid skew crossing wherever possible
To provide control radius of minimum 12.5 m for right turning traffic
To provide radius of minimum 9.0m for left turning traffic
To provide maximum possible length for weaving section in case of rotary
To provide 3.0m additional width of carriageway at weaving sections
To provide adequate sight distance for all traffic movements
To provide slip lanes for left turning where the volume is assessed to be high and
also land is available
IRC: SP41-1994 Guidelines of Design of At-grade Intersection in Rural and Urban
areas and M/ORT&H type designs for intersection on National Highway, 1992
shall be followed in the design of intersections. For developing designs for
interchanges at identified intersections IRC: 92-1985 Guidelines for the design of
interchanges in urban areas and AASHTO guidelines shall be followed.
Preparation of Detailed Project Report (DPR)

Design of Toll Plaza


Design toll plaza layout based on traffic segregation, acceptable queue length, toll
collection system and the average waiting time shall be made.
The plaza shall be designed based on the forecast traffic in such a way that the
traffic shall be subject to minimum delay and inconvenience. Also necessary
facilities shall be provided in the design for effective toll collection.
Design of Traffic Safety features, Road Furniture and Road Markings
Design of traffic signs and road markings, to effectively guide and control the
traffic, shall be carried out based on current national and international practices.
Weighing Station, Parking Areas and Rest Areas
Sites for Weighing stations, parking areas and rest areas shall be selected based on
the data collected and as per the discussions with the MoRT&H.
Design of Wayside Amenities
Design of the Wayside Amenities carried out in accordance with the comments and
suggestions of client and suitable layouts shall be prepared accommodating petrol
pump, first-aid medical facilities, restaurant, vehicle parking, toilets, telephone
kiosks, etc.
Preparation of Detailed Project Report (DPR)

Design of Communication System


An emergency telephone communication system to be used even by a person in
emergent condition with little effort shall be designed. This would be a public
access telephone system dedicated to control center, which shall coordinate services
like fire, ambulance, police and retrieval of breakdown vehicles, besides emergency
highway maintenance operations.
Design of Bus-bays and Lay-by
Review of design of bus-bays, in accordance with comments of clients, as per IRC
and M/ORT&H guidelines and drawings shall be made.
Design of Miscellaneous Items
Designs for guardrails, street lighting and other necessary roadside appurtenance
shall be carried out based on IRC and other current international practices.
Traffic Management Schemes during Implementation
Traffic management during construction is an integral part of execution of highway
projects. An efficient scheme or traffic management shall be developed based on
MoRT&H and IRC guidelines, which would include traffic diversion plans during
construction and maintenance and other measures for traffic control and safety.
Preparation of Detailed Project Report (DPR)

Project Costing
Unit rates shall be normally based on Schedule of Rates of respective departments
The unit rates calculated for similar roadwork and bridgework items shall be
reviewed and updated for cost calculation. In specific projects
Preliminary Estimate of Quantities
Quantities of various items shall be worked out based on the typical cross sections
already prepared chainage wise. Total item wise quantities for bridges and C-D
structures shall also be calculated considering the design features and present
condition of bridges.
Construction Cost
Maintenance Cost
Land Acquisition Cost
Environmental Cost
Cost of Utility Relocation.
Preparation of Detailed Project Report (DPR)

Economic Analysis
In order to carry out the economic analysis, all economic costs shall be estimated by
each homogenous section. These costs comprise of the following:
Cost of construction/improvement
Vehicle operating costs and time costs
Accident costs
Social and environmental costs
Estimation of Project Benefits
The benefits from each improvement option shall be derived by using the approach
of "with" and "without" project scenario, for each homogeneous section. The
benefits would comprise the following:
VOC savings
Travel time savings
Savings in Accident costs
Socio-Environmental benefits
Preparation of Detailed Project Report (DPR)

Financial Analysis
Financial analysis, by each section, shall be carried out for the identification of
potential BOT candidates. The revenue stream, as generated in the previous tasks
shall be included into the analysis in two stages:
Revenue only from toll imposition
Revenue from other sources as well.
Formulation of Construction Packages
The project corridor shall be divided into several construction packages depending
on the length of the project corridor. These shall cover and facilitate:
Enabling more contractors to bid
Uniformity in work
Speed in implementation of the project speedily
Economy in construction
Efficient Project management

You might also like