COURTHOUSE PROJECTS DECISION TREE

PROJECT INITIATION

PLANNING
EXTERNAL STAKEHOLDERS CONSULTATION
BER BPP
ADMINISTRATIVE OFFICE
of COURTS Preliminary Planning Documents
5 Year Plan

Long Range Court Plan FEASIBILITY STUDIES INFORMAL CONSULTATION*


PT, OCA*, GSA Regional Offices ACHP, SHPO

Financial Studies Other Studies


R & A Alternatives EIS
Site Studies Historic Preservation*

ANALYSIS
Operational Issues Other Financial Inputs Site Studies FORMAL CONSULTATION*
Discussion ACHP, SHPO
Public Comment
Re-examining
R & A Assumptions

ASSESS ALTERNATIVES

SELECT ALTERNATIVE

DECISION
Retain/Excess
Annex/Construction Off-Site
Basic R & A Scope
DESIGN & SITE
FUNDING REQUEST

ON-GOING CONSULTATION
OMB FINAL FEASIBILITY STUDY

SITE & DESIGN PROSPECTUS

NOT funded CONGRESS


SITE & DESIGN FUNDED
Site Acquisition & Design Development

FUNDING
Defer/Re-assess
CONSTRUCTION
FUNDING REQUEST
OMB CONSTRUCTION PROSPECTUS FORMAL CONSULTATION*
Identify Line Items & General Construction Estimate ACHP, SHPO
Public Comment
NOT funded CONGRESS
Detailed Design & Construction Documents

Defer

CONSTRUCTION FUNDED
IMPLEMENTATION

Design Modifications

CONSTRUCTION COMPLETION
*Regional Historic Preservation Offices
OCA, GSA Center for Historic Buildings