PROJECT INITIATION
PLANNING
EXTERNAL STAKEHOLDERS CONSULTATION
BER BPP
ADMINISTRATIVE OFFICE
of COURTS Preliminary Planning Documents
5 Year Plan
ANALYSIS
Operational Issues Other Financial Inputs Site Studies FORMAL CONSULTATION*
Discussion ACHP, SHPO
Public Comment
Re-examining
R & A Assumptions
ASSESS ALTERNATIVES
SELECT ALTERNATIVE
DECISION
Retain/Excess
Annex/Construction Off-Site
Basic R & A Scope
DESIGN & SITE
FUNDING REQUEST
ON-GOING CONSULTATION
OMB FINAL FEASIBILITY STUDY
FUNDING
Defer/Re-assess
CONSTRUCTION
FUNDING REQUEST
OMB CONSTRUCTION PROSPECTUS FORMAL CONSULTATION*
Identify Line Items & General Construction Estimate ACHP, SHPO
Public Comment
NOT funded CONGRESS
Detailed Design & Construction Documents
Defer
CONSTRUCTION FUNDED
IMPLEMENTATION
Design Modifications
CONSTRUCTION COMPLETION
*Regional Historic Preservation Offices
OCA, GSA Center for Historic Buildings