Annexure-1

Stressing and grouting sequence for Inner Containment of unit-3

Reference Document: The stressing schedule is made as per the approved document no. KAPP-3&4/DC/21000/18/R2 issued by NPCIL

Stage Sr. no. Cable No. Stressing Date Grouting date Remarks
1 RH-6 21-Aug-17 23-Aug-17
2 RH-1 21-Aug-17 23-Aug-17
Both parts of single cable will be stressed
3 RH-2 21-Aug-17 23-Aug-17
Stage-1 4 RH-5 21-Aug-17 23-Aug-17
simultaneously. Stressing will be done in sequence
for cable no. at sr.no.1 to 6
5 RH-4 21-Aug-17 23-Aug-17
6 RH-3 21-Aug-17 23-Aug-17
7 JO -3, JO-84 22-Aug-17 24-Aug-17
8 JI-3, JI-85 22-Aug-17 24-Aug-17
Cable no. JO-3 & JO-84 will be stressed
9 JO 11, JO 76 22-Aug-17 24-Aug-17 simultaneously and then JI-3 & JI-85 will be
10 JI 13 E,W and JI 75 E,W 22-Aug-17 24-Aug-17 stressed simultaneously. In the same manner other
11 JO 22, JO 65 23-Aug-17 25-Aug-17 dome cables will be stressed. i.e. in pair of two
12 JI 19, JI 69 23-Aug-17 25-Aug-17 cables.
Both parts of JI 13(E,W) and JI 75 (E,W) will be
13 JO 33, JO 54 23-Aug-17 25-Aug-17 stressed simultaneously.
14 JI 36, JI 52 23-Aug-17 25-Aug-17
15 JI 44 25-Aug-17 28-Aug-17
16 V 2, V 162 25-Aug-17 28-Aug-17
17 V 81, V 241 25-Aug-17 28-Aug-17
18 V 22, V 182 25-Aug-17 28-Aug-17
Cables no. V2 and V162 will be stressed
19 V 101, V 261 25-Aug-17 28-Aug-17
simultaneously. In the same manner other vertical
20 V 41, V 201 26-Aug-17 29-Aug-17 cables will be stressed in pairs.
21 V 121, V 281 26-Aug-17 29-Aug-17
Stage-2 22 V 63, V 223 26-Aug-17 29-Aug-17
23 V 144, V 302 26-Aug-17 29-Aug-17
24 H2 28-Aug-17 30-Aug-17
25 H 11 28-Aug-17 30-Aug-17
26 H 21 28-Aug-17 30-Aug-17
27 H 29 28-Aug-17 30-Aug-17
28 H 33 28-Aug-17 30-Aug-17
29 H 43 28-Aug-17 30-Aug-17
Both parts of single horizontal cable will be
30 H 55 28-Aug-17 30-Aug-17
stressed simultaneously. Stressing will be done in
31 H 59 28-Aug-17 30-Aug-17 sequence for cable no. at sr.no.24 to 37
32 H 66 29-Aug-17 31-Aug-17
33 H 76 29-Aug-17 31-Aug-17
34 H 88 29-Aug-17 31-Aug-17
35 H 97 29-Aug-17 31-Aug-17
36 H 103 29-Aug-17 31-Aug-17
37 H 110 29-Aug-17 31-Aug-17
38 J0 43 N,M,S and J0 45 N,M,S 30-Aug-17 1-Sep-17
39 JI 32, JI 56 30-Aug-17 1-Sep-17
All the three parts of Cable no. JO-43(N,M,S) & Jo-
40 JO 36, JO 51 30-Aug-17 1-Sep-17 45 (N,M,S) will be stressed simultaneously and
41 JI 25, JI 63 30-Aug-17 1-Sep-17 then JI-32 & JI-56 will be stressed simultaneously.
42 JO 26, JO 61 31-Aug-17 2-Sep-17 In the same manner other dome cables will be
43 (JI 16 E,W) and (JI 72 E,W) 31-Aug-17 2-Sep-17 stressed. i.e. in pair of two cables. Both parts of JI
44 JO 16, JO 71 31-Aug-17 2-Sep-17 16 (E,W) and JI 72 (E,W) will be stressed
simultaneously. Both parts of JI 14 (E,W) and JI 74
45 (JI 14 E,W) and (JI 74 E,W) 31-Aug-17 2-Sep-17 (E,W) will be stressed simultaneously.
46 JO 6, JO 81 2-Sep-17 4-Sep-17
47 JI 8, JI 80 2-Sep-17 4-Sep-17
48 V 79, V 239 2-Sep-17 4-Sep-17
49 V 160 , V 318 2-Sep-17 4-Sep-17
50 V 57, V 217 4-Sep-17 6-Sep-17
Cables no. V79 and V239 will be stressed
51 V 138, V 296 4-Sep-17 6-Sep-17
simultaneously. In the same manner other vertical
52 V 39, V 199 4-Sep-17 6-Sep-17 cables will be stressed in pairs.
Stage-3 53 V 119, V 279 4-Sep-17 6-Sep-17
54 V 18, V 178 5-Sep-17 7-Sep-17
55 V 97, V 257 5-Sep-17 7-Sep-17
56 H 108 5-Sep-17 7-Sep-17
57 H 101 5-Sep-17 7-Sep-17
58 H 86 5-Sep-17 7-Sep-17
59 H 74 5-Sep-17 7-Sep-17
60 H 63 6-Sep-17 8-Sep-17
Both parts of single horizontal cable will be
61 H 52 6-Sep-17 8-Sep-17
stressed simultaneously. Stressing will be done in
62 H 47 6-Sep-17 8-Sep-17 sequence for cable no. at sr.no.56 to 67
63 H 41 6-Sep-17 8-Sep-17
64 H 31 6-Sep-17 8-Sep-17
65 H 19 6-Sep-17 8-Sep-17
66 H 09 6-Sep-17 8-Sep-17
67 H 01 6-Sep-17 8-Sep-17

Page 1 of 6
Annexure-1

Stressing and grouting sequence for Inner Containment of unit-3

Reference Document: The stressing schedule is made as per the approved document no. KAPP-3&4/DC/21000/18/R2 issued by NPCIL

Stage Sr. no. Cable No. Stressing Date Grouting date Remarks
68 JO 14, JO 73 7-Sep-17 9-Sep-17
69 JI 11, JI 77 7-Sep-17 9-Sep-17
Cable no. JO-14 & JO-73 will be stressed
70 JO 24, JO 63 7-Sep-17 9-Sep-17 simultaneously and then JI-11 & JI-77 will be
71 (JI 15 E,W) and (JI 73 E,W) 7-Sep-17 9-Sep-17 stressed simultaneously. In the same manner other
72 JO 29 , JO 58 8-Sep-17 11-Sep-17 dome cables will be stressed. i.e. in pair of two
73 JI 17 E,W and JI 71 E,W 8-Sep-17 11-Sep-17 cables.
Both parts of JI 15 (E,W) and JI 73 (E,W) will be
74 JO 35, JO 52 8-Sep-17 11-Sep-17 stressed simultaneously. Both parts of JI 17 (E,W)
75 JI 28, JI 60 8-Sep-17 11-Sep-17 and JI 71 (E,W) will be stressed simultaneously.
All the three parts of Cable no. JO-41(N,M,S) &
76 (JO 41 N,M,S) and (JO 46 N,M,S) 11-Sep-17 13-Sep-17 JO-46 (N,M,S) will be stressed simultaneously

77 JI 38, JI 50 11-Sep-17 13-Sep-17


78 V 4, V 164 11-Sep-17 13-Sep-17
79 V 83, V 243 11-Sep-17 13-Sep-17
80 V 24, V 184 12-Sep-17 14-Sep-17
Cables no. V4 and V164 will be stressed
81 V 103, V 263 12-Sep-17 14-Sep-17
simultaneously. In the same manner other vertical
82 V 43, V 203 12-Sep-17 14-Sep-17 cables will be stressed in pairs.
Stage 4 83 V 123, V 283 12-Sep-17 14-Sep-17
84 V 65, V 225 13-Sep-17 15-Sep-17
85 V 146, V 304 13-Sep-17 15-Sep-17
86 H 12 13-Sep-17 15-Sep-17
87 H 18 13-Sep-17 15-Sep-17
88 H 22 13-Sep-17 15-Sep-17
89 H 34 13-Sep-17 15-Sep-17
90 H 40 14-Sep-17 16-Sep-17
91 H 46 14-Sep-17 16-Sep-17
Both parts of single horizontal cable will be
92 H 51 14-Sep-17 16-Sep-17
stressed simultaneously. Stressing will be done in
93 H 57 14-Sep-17 16-Sep-17 sequence for cable no. at sr.no.86 to 99
94 H 62 14-Sep-17 16-Sep-17
95 H 68 14-Sep-17 16-Sep-17
96 H 77 14-Sep-17 16-Sep-17
97 H 89 14-Sep-17 16-Sep-17
98 H 98 15-Sep-17 18-Sep-17
99 H 109 15-Sep-17 18-Sep-17
100 JO 40, JO 47 15-Sep-17 18-Sep-17
101 JI 40, JI 48 15-Sep-17 18-Sep-17 Cable no. JO-40 & JO-47 will be stressed
102 JO 32, JO 55 16-Sep-17 19-Sep-17 simultaneously and then JI-40 & JI-48 will be
stressed simultaneously. In the same manner other
103 JI 29, JI 59 16-Sep-17 19-Sep-17
dome cables will be stressed. i.e. in pair of two
104 JO 21, JO 66 16-Sep-17 19-Sep-17 cables.
105 (JI 18 E,W) and (JI 70 E,W) 16-Sep-17 19-Sep-17 Both parts of JI 18 (E,W) and JI 70(E,W) will be
106 JO 10, JO 77 18-Sep-17 20-Sep-17 stressed simultaneously.
107 JI 4, JI 84 18-Sep-17 20-Sep-17
108 V 77, V 237 18-Sep-17 20-Sep-17
109 V 158, V 316 18-Sep-17 20-Sep-17
110 V 55, V 215 19-Sep-17 21-Sep-17
Cables no. V77 and V237 will be stressed
111 V 136, V 294 19-Sep-17 21-Sep-17
simultaneously. In the same manner other vertical
112 V 37, V 197 19-Sep-17 21-Sep-17 cables will be stressed in pairs.
113 V 116, V 270 19-Sep-17 21-Sep-17
114 V 16, V 176 20-Sep-17 22-Sep-17
Stage 5 115 V 95, V 255 20-Sep-17 22-Sep-17
116 H 113 20-Sep-17 22-Sep-17
117 H 102 20-Sep-17 22-Sep-17
118 H 100 20-Sep-17 22-Sep-17
119 H 95 20-Sep-17 22-Sep-17
120 H 87 21-Sep-17 23-Sep-17
121 H 79 21-Sep-17 23-Sep-17
Both parts of single horizontal cable will be
122 H 75 21-Sep-17 23-Sep-17
stressed simultaneously. Stressing will be done in
123 H 65 21-Sep-17 23-Sep-17 sequence for cable no. at sr.no.116 to 129
124 H 53 21-Sep-17 23-Sep-17
125 H 44 21-Sep-17 23-Sep-17
126 H 32 21-Sep-17 23-Sep-17
127 H 23 21-Sep-17 23-Sep-17
128 H 10 22-Sep-17 25-Sep-17
129 H 04 22-Sep-17 25-Sep-17

Page 2 of 6
Annexure-1

Stressing and grouting sequence for Inner Containment of unit-3

Reference Document: The stressing schedule is made as per the approved document no. KAPP-3&4/DC/21000/18/R2 issued by NPCIL

Stage Sr. no. Cable No. Stressing Date Grouting date Remarks
130 JO 2, JO 85 22-Sep-17 25-Sep-17
131 JI 2, JI 86 22-Sep-17 25-Sep-17
132 JO 13, JO 74 23-Sep-17 26-Sep-17
133 JI 12, JI 76 23-Sep-17 26-Sep-17 Cable no. JO-2 & JO-85 will be stressed
simultaneously and then JI-2 & JI-86 will be
134 JO 25, JO 62 23-Sep-17 26-Sep-17
stressed simultaneously. In the same manner other
135 JI 23, JI 65 23-Sep-17 26-Sep-17 dome cables will be stressed. i.e. in pair of two
136 JO 37,JO 50 25-Sep-17 27-Sep-17 cables.
137 JI 34, JI 54 25-Sep-17 27-Sep-17
138 JO 39, JO 48 26-Sep-17 28-Sep-17
139 JI 41, JI 47 26-Sep-17 28-Sep-17
140 V 06, V 166 26-Sep-17 28-Sep-17
141 V 85, V 245 26-Sep-17 28-Sep-17
142 V 26, V 186 27-Sep-17 29-Sep-17
Stage 6 143 V 105, V 265 27-Sep-17 29-Sep-17 Cables no. V06 and V166 will be stressed
simultaneously. In the same manner other vertical
144 V 47, V 207 27-Sep-17 29-Sep-17 cables will be stressed in pairs.
145 V 128, V 286 27-Sep-17 29-Sep-17
146 V 67, V 227 28-Sep-17 30-Sep-17
147 V 148, V 306 28-Sep-17 30-Sep-17
148 H 06 28-Sep-17 30-Sep-17
149 H 14 28-Sep-17 30-Sep-17
150 H 26 28-Sep-17 30-Sep-17
Both parts of single horizontal cable will be
151 H 36 28-Sep-17 30-Sep-17
stressed simultaneously. Stressing will be done in
152 H 48 3-Oct-17 5-Oct-17 sequence for cable no. at sr.no.148 to 155
153 H 58 3-Oct-17 5-Oct-17
154 H 69 3-Oct-17 5-Oct-17
155 H 81 3-Oct-17 5-Oct-17
156 JO 42 N,M,S and JO 44 N,M,S 3-Oct-17 5-Oct-17
157 JI 42, JI 46 3-Oct-17 5-Oct-17
158 JO 30, JO 57 4-Oct-17 6-Oct-17 All the three parts of Cable no. JO-42(N,M,S) &
JO-44(N,M,S) will be stressed simultaneously and
159 JI 31, JI 57 4-Oct-17 6-Oct-17
then JI-42 & JI-46 will be stressed simultaneously.
160 JO 18, JO 69 4-Oct-17 6-Oct-17 In the same manner other dome cables will be
161 JI 20, JI 68 4-Oct-17 6-Oct-17 stressed. i.e. in pair of two cables.
162 JO 7, JO 80 5-Oct-17 7-Oct-17
163 JI 7, JI 81 5-Oct-17 7-Oct-17
164 V 75, V 235 5-Oct-17 7-Oct-17
165 V 156, V 314 5-Oct-17 7-Oct-17
166 V 53, V 213 6-Oct-17 9-Oct-17
Cables no. V75 and V235 will be stressed
167 V 134, V 292 6-Oct-17 9-Oct-17
simultaneously. In the same manner other vertical
168 V 35, V 193 6-Oct-17 9-Oct-17 cables will be stressed in pairs.
169 V 113, V 273 6-Oct-17 9-Oct-17
170 V 14, V 174 7-Oct-17 10-Oct-17
Stage 7 171 V 93, V 253 7-Oct-17 10-Oct-17
172 H 112 7-Oct-17 10-Oct-17
173 H 99 7-Oct-17 10-Oct-17
174 H 90 7-Oct-17 10-Oct-17
175 H 78 7-Oct-17 10-Oct-17
176 H 83 9-Oct-17 11-Oct-17
177 H 67 9-Oct-17 11-Oct-17
Both parts of single horizontal cable will be
178 H 54 9-Oct-17 11-Oct-17
stressed simultaneously. Stressing will be done in
179 H 45 9-Oct-17 11-Oct-17 sequence for cable no. at sr.no.172 to 185
180 H 37 9-Oct-17 11-Oct-17
181 H 30 9-Oct-17 11-Oct-17
182 H 25 9-Oct-17 11-Oct-17
183 H 20 9-Oct-17 11-Oct-17
184 H 15 10-Oct-17 12-Oct-17
185 H 07 10-Oct-17 12-Oct-17

Page 3 of 6
Annexure-1

Stressing and grouting sequence for Inner Containment of unit-3

Reference Document: The stressing schedule is made as per the approved document no. KAPP-3&4/DC/21000/18/R2 issued by NPCIL

Stage Sr. no. Cable No. Stressing Date Grouting date Remarks

186 JO 4, JO 83 10-Oct-17 12-Oct-17


187 JI 1, JI 87 10-Oct-17 12-Oct-17
188 JO 15, JO 72 11-Oct-17 13-Oct-17
Cable no. JO-4 & JO-83 will be stressed
189 JI 6, JI 82 11-Oct-17 13-Oct-17 simultaneously and then JI-1 & JI-87 will be
190 JO 27, JO 60 11-Oct-17 13-Oct-17 stressed simultaneously. In the same manner other
191 JI 21, JI 67 11-Oct-17 13-Oct-17 dome cables will be stressed. i.e. in pair of two
cables.
192 JO 34, JO 53 12-Oct-17 14-Oct-17
193 JI 26, JI 62 12-Oct-17 14-Oct-17
194 JO 38, JO 49 13-Oct-17 16-Oct-17
195 JI 37, JI 51 13-Oct-17 16-Oct-17
196 V 28, V 188 13-Oct-17 16-Oct-17
197 V 107, V 267 13-Oct-17 16-Oct-17
198 V 49, V 209 14-Oct-17 17-Oct-17 Cables no. V28 and V188 will be stressed
199 V 130, V 288 14-Oct-17 17-Oct-17 simultaneously. In the same manner other vertical
Stage 8 200 V 69, V 229 14-Oct-17 17-Oct-17 cables will be stressed in pairs.

201 V 150, V 308 14-Oct-17 17-Oct-17


202 V 73, V 233 16-Oct-17 18-Oct-17
203 H 05 16-Oct-17 18-Oct-17
204 H 16 16-Oct-17 18-Oct-17
205 H 24 16-Oct-17 18-Oct-17
206 H 35 16-Oct-17 18-Oct-17
207 H 42 16-Oct-17 18-Oct-17
Both parts of single horizontal cable will be
208 H 56 16-Oct-17 18-Oct-17
stressed simultaneously. Stressing will be done in
209 H 64 17-Oct-17 20-Oct-17 sequence for cable no. at sr.no.203 to 214
210 H 73 17-Oct-17 20-Oct-17
211 H 80 17-Oct-17 20-Oct-17
212 H 84 17-Oct-17 20-Oct-17
213 H 104 17-Oct-17 20-Oct-17
214 H 111 17-Oct-17 20-Oct-17
215 JO 31, JO 56 18-Oct-17 21-Oct-17
216 JI 30, JI 58 18-Oct-17 21-Oct-17
217 JO 28, JO 59 18-Oct-17 21-Oct-17
218 JI 22, JI 66 18-Oct-17 21-Oct-17 Cable no. JO-31 & JO-56 will be stressed
simultaneously and then JI-30 & JI-58 will be
219 JO 23, JO 64 20-Oct-17 23-Oct-17
stressed simultaneously. In the same manner other
220 JI 39, JI 49 20-Oct-17 23-Oct-17 dome cables will be stressed. i.e. in pair of two
221 JO 19, JO 68 20-Oct-17 23-Oct-17 cables.
222 JI 43, JI 45 20-Oct-17 23-Oct-17
223 JO 8, JO 79 23-Oct-17 25-Oct-17
224 JI 27, JI 61 23-Oct-17 25-Oct-17
225 V 71, V 231 23-Oct-17 25-Oct-17
226 V 142, V 300 23-Oct-17 25-Oct-17
227 V 51, V 211 24-Oct-17 26-Oct-17
228 V 132, V 290 24-Oct-17 26-Oct-17
Cables no. V71 and V231 will be stressed
229 V 36, V 157 24-Oct-17 26-Oct-17
simultaneously. In the same manner other vertical
Stage 9 230 V 115, V 275 24-Oct-17 26-Oct-17 cables will be stressed in pairs.
231 V 20, V 180 25-Oct-17 27-Oct-17
232 V 99, V 259 25-Oct-17 27-Oct-17
233 V 12, V 172 25-Oct-17 27-Oct-17
234 V 91, V 251 25-Oct-17 27-Oct-17
235 H 115 26-Oct-17 28-Oct-17
236 H 106 26-Oct-17 28-Oct-17
237 H 96 26-Oct-17 28-Oct-17
238 H 91 26-Oct-17 28-Oct-17
239 H 85 26-Oct-17 28-Oct-17 Both parts of single horizontal cable will be
240 H 61 26-Oct-17 28-Oct-17 stressed simultaneously. Stressing will be done in
241 H 50 26-Oct-17 28-Oct-17 sequence for cable no. at sr.no.235 to 245

242 H 39 26-Oct-17 28-Oct-17


243 H 28 27-Oct-17 30-Oct-17
244 H 17 27-Oct-17 30-Oct-17
245 H 08 27-Oct-17 30-Oct-17

Page 4 of 6
Annexure-1

Stressing and grouting sequence for Inner Containment of unit-3

Reference Document: The stressing schedule is made as per the approved document no. KAPP-3&4/DC/21000/18/R2 issued by NPCIL

Stage Sr. no. Cable No. Stressing Date Grouting date Remarks
246 JO 5, JO 82 27-Oct-17 30-Oct-17
247 JI 5, JI 83 27-Oct-17 30-Oct-17
248 JO 9, JO 78 28-Oct-17 31-Oct-17 Cable no. JO-5 & JO-82 will be stressed
simultaneously and then JI-5 & JI-83 will be
249 JI 9, JI 79 28-Oct-17 31-Oct-17
stressed simultaneously. In the same manner other
250 JO 17, JO 70 28-Oct-17 31-Oct-17 dome cables will be stressed. i.e. in pair of two
251 JI 10, JI 78 28-Oct-17 31-Oct-17 cables.
252 JO 20, JO 67 30-Oct-17 1-Nov-17
253 JI 24, JI 64 30-Oct-17 1-Nov-17
254 V 30, V 190 30-Oct-17 1-Nov-17
255 V 109, V 269 30-Oct-17 1-Nov-17
256 V 32, V 192 31-Oct-17 2-Nov-17
Cables no. V30 and V190 will be stressed
257 V 111, V 271 31-Oct-17 2-Nov-17
simultaneously. In the same manner other vertical
258 V 34, V 194 31-Oct-17 2-Nov-17 cables will be stressed in pairs.
Stage 10 259 V 117, V 277 31-Oct-17 2-Nov-17
260 V 89, V 249 1-Nov-17 3-Nov-17
261 V 140, V 298 1-Nov-17 3-Nov-17
262 H 03 1-Nov-17 3-Nov-17
263 H 13 1-Nov-17 3-Nov-17
264 H 27 1-Nov-17 3-Nov-17
265 H 38 1-Nov-17 3-Nov-17
Both parts of single horizontal cable will be
266 H 49 2-Nov-17 4-Nov-17
stressed simultaneously. Stressing will be done in
267 H 60 2-Nov-17 4-Nov-17 sequence for cable no. at sr.no.262 to 271
268 H 71 2-Nov-17 4-Nov-17
269 H 82 2-Nov-17 4-Nov-17
270 H 93 2-Nov-17 4-Nov-17
271 H 114 2-Nov-17 4-Nov-17
272 V 87, V 247 4-Nov-17 6-Nov-17

273 V 125 4-Nov-17 6-Nov-17


Cables no. V87 and V247 will be stressed
simultaneously. Cable no. VI 125, V295 and V
Stage 11 274 V 295 4-Nov-17 6-Nov-17 297 will be stressed individually. Cables no. V126
and V285 will be stressed simultaneously
275 V 297 4-Nov-17 6-Nov-17

276 V 126, V 285 4-Nov-17 6-Nov-17

277 JO 1, JO 86 6-Nov-17 Monitoring cables


Cable no. JO-1 & JO-86 will be stressed
simultaneously and then JI-35 & JI-53 will be
278 JI 35, JI 53 6-Nov-17 Monitoring cables
stressed simultaneously. In the same manner other
279 JO 12,JO 75 6-Nov-17 8-Nov-17 dome cables will be stressed. i.e. in pair of two
cables.JO-1,JO-86,JI-35 and JI-53 are monitoring
cables, hence will not be grouted.
280 JI 33, JI 55 6-Nov-17 8-Nov-17

281 V 1, V 161 7-Nov-17 9-Nov-17


282 V 8, V 168 7-Nov-17 9-Nov-17
283 V 10, V 170 7-Nov-17 9-Nov-17 Cables no. V1 and V161 will be stressed
simultaneously. In the same manner other vertical
284 V 45, V 205 7-Nov-17 9-Nov-17 cables will be stressed in pairs. As per drawing
21212/2154/DD/R5 cable no. V 168, V 59, V 312
285 V 61, V 221 8-Nov-17 10-Nov-17 are monitoring cables, however cable no. V 59 and
V 312 are stressed after their respective extra
286 V 152, V 310 8-Nov-17 10-Nov-17 margin cable V 61 and V 310. Hence, if stressing
Stage 12 of cable no. V 61 and V 310 are successful then
these cables will be considered for monitoring. This
287 V 59, V 219 8-Nov-17 10-Nov-17 is as per MOM dated 27th July 2017.

288 V 154, V 312 8-Nov-17 10-Nov-17

289 H 70 9-Nov-17 Monitoring cable


Both parts of single horizontal cable will be
290 H 92 9-Nov-17 Monitoring cable stressed simultaneously. Stressing will be done in
sequence for cable no. at sr.no.289 to 294. As per
291 H 72 9-Nov-17 11-Nov-17 drawing 21212/2154/DD/R5 cable no.H70, H94,
H105 are monitoring cables, however cable no. H
94 is stressed after it's respective extra margin
292 H 94 9-Nov-17 11-Nov-17 cable H 92. Hence, if stressing of cable no. H 92 is
successful then it can be considered for
293 H 105 9-Nov-17 Monitoring cable monitoring.This is as per MOM dated 27th July
2017.
294 H 107 9-Nov-17 11-Nov-17

Page 5 of 6
Annexure-1

Stressing and grouting sequence for Inner Containment of unit-3

Reference Document: The stressing schedule is made as per the approved document no. KAPP-3&4/DC/21000/18/R2 issued by NPCIL

Stage Sr. no. Cable No. Stressing Date Grouting date Remarks
295 CH 07, CH 08 10-Nov-17 13-Nov-17
296 CH 01, CH 14 10-Nov-17 13-Nov-17
297 CH 04, CH 11 10-Nov-17 13-Nov-17
298 CH 06, CH 09 10-Nov-17 13-Nov-17
299 CH 02, CH 13 11-Nov-17 14-Nov-17 Cables no. CH07 and CH08 will be stressed
Stage 13 300 CH 05, CH 10 11-Nov-17 14-Nov-17 simultaneously. In the same manner other CH
301 CH 03, CH 12 11-Nov-17 14-Nov-17 cables will be stressed in pairs.

302 CH 18, CH 19 11-Nov-17 14-Nov-17


303 CH 15, CH 22 13-Nov-17 15-Nov-17
304 CH 17, CH 20 13-Nov-17 15-Nov-17
305 CH 16, CH 21 13-Nov-17 15-Nov-17

NOTE

1. The stressing schedule is made as per the document no. KAPP-3&4/DC/21000/18/R2

2. The starting date may change depending upon the strength gaining period of concrete.

3. Schedule is made considering not more than 16 dome cables are left ungrouted at any stage
as mentioned in the document no. KAPP-3&4/DC/21000/18/R2.

4. Min. of 2 days gap is left between stressing and grouting for 24 hour slip checking, dry
packing and strength gaining of dry packing. However, if the grouting is done using the grout
cap (instead of dry pack), the grouting of cables can be done after 1 day ( after 24 hrs slip
measurement) only

5. First 2 JO cables will be stressed simultaneously and then 2 JI cables will be stressed
simultaneously

6. Two parts of a single horizontal cable are to be stressed simultaneously.Then the next
horizontal cable is to be taken up for stressing.
7. The dates for stressing and grouting may vary however, the sequence of the cables will
remain the same.
8. As per MOM dated 27th July 2017, in case of breaking of strand/plies , the cable should be
locked and referred to the designers for further action. Further, stressing operation shall be
taken up only after clearance from designers.

9. As per MOM dated 27th July 2017,while stressing, adjacent RH and CH cables can be left
ungrouted.

10. If required elongation is not achieved at a specified jack pressure, then the tensioning may
be continued until the desired elongation is reached. However, for any cable, the jack
pressure shall not exceed more than 5% of the pressure indicated.If required jack pressure is
not achieved at a specified elongation, then the tensioning may be continued until the desired
jack pressure is reached. However, for any cable, the elongation shall not exceed more than
5% of the elongation indicated.Any shortfall in the elongation shall be intimated to the design
office.
11. The monitoring cables indicated above can be changed with extra margin cables if there
is any unforseen issues in monitoring cables as given in drawing no. KAPP-
3&4/21212/2154/DD/R5

Page 6 of 6